20 OHT instruments has been commissioned . It was commited that other 4 OHTs instruments work will be commissioned till 20.8.25 . 11 OHT has been made functional . Also Firm had commited to make commissioned 20 OHT functional on portal till 20.8.25 .
22 Nos. OHT instruments has been commissioned . Among them 12 OHt has been made functional and remaining 10 OHT will be made functional till 31.8.25 . Firm also committed to installed Voltage stablizer at all CWR till 15.9.25
22 Nos. OHT instruments has been commissioned . As per microplanning all commissioned OHT were supposed to be functional till 31.8.25 . Integrated components instrument value are eiher constant or zero . Firm also committed to installed Voltage stablizer at all CWR till 15.9.25.
22 Nos. OHT instruments has been commissioned . As per microplanning all commissioned OHT were supposed to be functional till 31.8.25 . Integrated components instrument value are eiher constant or zero . Firm comitted to make 18 nos. OHT functional till 19.9.25 and remaining 4 nos. till 26.9.25 . Firm also committed to installed Voltage stablizer at all CWR till 15.9.25.
22 Nos. OHT instruments has been commissioned . As per microplanning all commissioned OHT were supposed to be functional till 31.8.25 . Integrated components instrument value are eiher constant or zero . Firm comitted to make 18 nos. OHT functional till 19.9.25 and remaining 4 nos. till 26.9.25 . Firm also committed to installed Voltage stablizer at all CWR till 15.9.25.
22 Nos. OHT instruments has been commissioned . As per microplanning all commissioned OHT were supposed to be functional till 31.8.25 . Integrated components instrument value are eiher constant or zero . Firm comitted to make 18 nos. OHT functional till 19.9.25 and remaining 4 nos. till 26.9.25 . Firm also committed to installed Voltage stablizer at all CWR till 15.9.25.
22 Nos. OHT instruments has been commissioned . As per microplanning all commissioned OHT were supposed to be functional till 31.8.25 . Integrated components instrument value are eiher constant or zero . Firm had comitted to make 18 nos. OHT functional till 19.9.25 and remaining 4 nos. till 26.9.25 . Firm also committed to installed Voltage stablizer at all CWR till 15.9.25. Integration work to be expedite .