As per microplanning integration work should have completed as below ;- WTP till 12.8.25 & ESR 8, 9, 10 till 24.8.25 . Firm again commited to complet the work till 26.8.25
As per microplanning integration work should have completed as below ;- WTP till 12.8.25 & ESR 8, 9, 10 till 24.8.25 . Jio ILL installation completed but it configuration are being done . same will be completed till 31.8.25 afterward except 3 OHT all OHT data shall be integrated .
As per microplanning integration work should have completed till 31.8.25 . JIO network configuration work has been completed . Firm again committed that 8 OHT shall be made functional till 15.9.25 .
JIO network configuration work has been completed . Firm again committed that 8 OHT shall be made functional till 15.9.25 . Only 1 OHT has been made functional yet . Again committed that remaining 7 OHT will be made functional till 10.10.25
As per commitment 8 OHT should have functional till 15.9.25 . Only 1 OHT has been made functional yet . Again committed that remaining 7 OHT will be made functional till 10.10.25. Integration work to be expedite .
As per commitment 8 OHT should have functional till 15.9.25 . Only 1 OHT has been made functional yet . Again committed that remaining 7 OHT will be made functional till 10.10.25. Integration work progress to be expedite .