Firm commited again that SCADA Automation Installation & it Commissioning work shaal be completed till 15.8.25 . Also commited to complet Integration work till 25.8.2025.
Firm had commited that SCADA Automation Installation & it Commissioning work would have been completed till 15.8.25 . At WTP SCADA installation work completed. At intake well SCADA installation work will be comleted till 7.9.25 .
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.9.25 . But SCADA instalation work has not been completed yet . Installtion & commissining work to be expedite. Work status are same as previous .
Firm recommitted that PLC SCADA Installation & Commissioning work shall be completed till 30.1.26. Installtion and commissioning work are slow & same to be expedite.
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.12.25 . But SCADA instalation work has not been completed yet . Firm again committed to complete Installtion & commissining work till 31.1.26 .
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.12.25 . But SCADA instalation work has not been completed yet . Firm again committed to complete Installtion & commissining work till 31.1.26 . Dedicated team not deputed , hence work not completed
Firm again committed that SCADA Automation Installation & Commissioning work shall be completed till 7.12.25 . But SCADA instalation work has not been completed yet . Firm again committed to complete Installtion & commissining work till 31.1.26 . Dedicated team not deputed , hence work not completed
As per Firm recommittment SCADA Automation Installation & Commissioning work should have completed till 7.12.25 . But SCADA instalation work has not been completed yet . Firm again committed to complete Installtion & commissining work till 31.1.26 . Dedicated team not deputed , hence work not completed
SCADA instalation work has not been completed yet . Firm again committed to complete Installtion & commissining work till 31.1.26 . Dedicated team require . Work status are same as previos .