Firm had commited to complet the integration work of intake well, WTP, CWRS and all OHT till 15.8.25 . Only 1 OHT has been made functional yet and remaining work are in process and progress are slow .
Integration work of intake well, WTP, CWRS and all OHT was supposed to complete till 20.8.25 . Jio ILL work completed for network issue at WTP . EMF coil has issue which has to be repaired . Firm committed again that ordered V set will be receaved at site and integration will be comleted till 14.9.25 .