Firm had commited to complet the integration work of intake well, WTP, CWRS and all OHT till 15.8.25 . Only 1 OHT has been made functional yet and remaining work are in process and progress are slow .
Integration work of intake well, WTP, CWRS and all OHT was supposed to complete till 20.8.25 . Jio ILL work completed for network issue at WTP . EMF coil has issue which has to be repaired . Firm committed again that ordered V set will be receaved at site and integration will be comleted till 14.9.25 .
Integration work of intake well, WTP, CWRS and all OHT has been completed . Firm committed again that remaining ordered V set will be receaved at site and integration will be comleted till 14.9.25 .
Integration work of intake well, WTP, CWRS and all OHT has been completed . Firm committed again that remaining ordered V set will be receaved at site and integration will be comleted till 30.9.25 .
Among 12 Nos of OHT, 11 OHT has been made functional . Work for Instruments Calibration and data tranansfering are being done , same shall be comleted till 12.10.25 .
Among 12 Nos of OHT, 11 OHT has been made functional . Work for Instruments Calibration and data tranansfering are being done , same shall be comleted till 12.10.25 .
Among 12 Nos of OHT, 11 OHT has been made functional . Work for Instruments Calibration and data tranansfering are being done , same should have comleted till 12.10.25 . Calibration to be expedite for Verification. Firm again comitted to complete the same till 3.11.25
Among 12 Nos of OHT, 11 OHT has been made functional . Work for Instruments Calibration and data tranansfering are being done . As per recommittment same should have comleted till 3.11.25 . Work progress are very slow .
Among 12 Nos of OHT, 11 OHT has been made functional . Work for Instruments Calibration and data tranansfering are being done . As per recommittment same should have comleted till 3.11.25 . Work progress are slow .
Among 12 Nos of OHT, 11 OHT has been made functional . Work for Instruments Calibration and data tranansfering are being done . As per recommittment same should have comleted till 3.11.25 . Work progress are very slow & it status are same as previous .