Project Completion Plan


Minutes of Meeting Date - 24-Jun-2025

No technical staff/team available at site for operation and rectification. Assurance by firm- All OHTs, Intake, WTP and CWRs will be integrated and functional on portal by 30.06.2025.


Minutes of Meeting Date - 24-Jun-2025

As per the instruction, notice regarding slow progress of automation & integration work is to be issued. No technical staff/team available at site for operation and rectification. Assurance by firm- vendor team is now available at WTP. Rectification work in progress and all OHTs, Intake, WTP and CWRs will be integrated and functional on portal by 05.07.2025.


Minutes of Meeting Date - 08-Jul-2025

Team is now available at site. Rectification work in progress and all OHTs, Intake, WTP and CWRs will be integrated and functional on portal by 15.07.2025.


Minutes of Meeting Date - 22-Jul-2025

Team is now available at site. Assurance by firm - Rectification work in progress and all OHTs will be integrated and functional on portal by 25.07.2025.


Minutes of Meeting Date - 29-Jul-2025

Calibration of flowmeter is required. All flow data is not matching with site. Assurance by firm- Rectification work in progress and all OHTs will be integrated and functional on portal by 31.07.2025.


Minutes of Meeting Date - 05-Aug-2025

Calibration of flowmeter is required. All flow data is not matching with site. Assurance by firm- Rectification work in progress and all OHTs will be integrated and functional on portal by 15.08.2025.


Minutes of Meeting Date - 19-Aug-2025

Calibration of flowmeter is required. Assurance by firm- Rectification work in progress and all 13 nos. OHTs will be integrated and functional on portal by 20.08.2025.