No technical staff/team available at site for operation and rectification. Assurance by firm- All OHTs, Intake, WTP and CWRs will be integrated and functional on portal by 30.06.2025.
As per the instruction, notice regarding slow progress of automation & integration work is to be issued. No technical staff/team available at site for operation and rectification. Assurance by firm- vendor team is now available at WTP. Rectification work in progress and all OHTs, Intake, WTP and CWRs will be integrated and functional on portal by 05.07.2025.
Team is now available at site. Rectification work in progress and all OHTs, Intake, WTP and CWRs will be integrated and functional on portal by 15.07.2025.
Team is now available at site. Assurance by firm - Rectification work in progress and all OHTs will be integrated and functional on portal by 25.07.2025.
Calibration of flowmeter is required. All flow data is not matching with site. Assurance by firm- Rectification work in progress and all OHTs will be integrated and functional on portal by 31.07.2025.
Calibration of flowmeter is required. All flow data is not matching with site. Assurance by firm- Rectification work in progress and all OHTs will be integrated and functional on portal by 15.08.2025.
Calibration of flowmeter is required. Assurance by firm- Rectification work in progress and all 13 nos. OHTs will be integrated and functional on portal by 20.08.2025.