It was committed that Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 10.8.25 and 18.8.25 respectively .
It was committed that Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 10.8.25 and 18.8.25 respectively . But only intake SCADA commissioned . Firm committed to complete commissioning of WTP , CWR SCADA work till 7.9.25 . V set are being procured for Sites having network issue & same will be received at site till 6.9.25 .
It was committed that Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 10.8.25 and 18.8.25 respectively . But only intake SCADA commissioned . Firm committed to complete commissioning of WTP , CWR SCADA work till 7.9.25 . V set are being procured for Sites having network issue & same will be received at site till 6.9.25 .