Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in
Check List Form

      Gurmura GOV (8177926)

Project Completion Plan


Minutes of Meeting Date - 19-Aug-2025

It was committed that Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 10.8.25 and 18.8.25 respectively .


Minutes of Meeting Date - 26-Aug-2025

It was committed that Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 10.8.25 and 18.8.25 respectively . But only intake SCADA commissioned . Firm committed to complete commissioning of WTP , CWR SCADA work till 7.9.25 . V set are being procured for Sites having network issue & same will be received at site till 6.9.25 .


Minutes of Meeting Date - 26-Aug-2025

It was committed that Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 10.8.25 and 18.8.25 respectively . But only intake SCADA commissioned . Firm committed to complete commissioning of WTP , CWR SCADA work till 7.9.25 . V set are being procured for Sites having network issue & same will be received at site till 6.9.25 .


Minutes of Meeting Date - 09-Sep-2025

Intake well, WTP, CWRs SCADA commissioning work & it integration work would have been completed till 10.8.25 and 18.8.25 respectively . But only intake SCADA commissioned . Firm again committed to complete commissioning of WTP , CWR OHT SCADA work with Integration till 25.9.25 .


Minutes of Meeting Date - 16-Sep-2025

SCADA commissioned has been completed at intake . Firm had committed to complete commissioning of WTP , CWR , OHT SCADA work with Integration till 25.9.25 . Due to network issue same could not completed . same shall be completed till 7.10.25.


Minutes of Meeting Date - 23-Sep-2025

SCADA commissioned has been completed at intake . Firm had committed to complete commissioning of WTP , CWR , OHT SCADA work with Integration till 25.9.25 . V set has been receaved . Integration work shall be completed till 7.10.25.


Minutes of Meeting Date - 07-Oct-2025

SCADA commissioned has been completed at intake . Firm had committed to complete commissioning of WTP , CWR , OHT SCADA work with Integration till 25.9.25 . V set has been receaved . 4 nos. V set has been installed it commissioning shall be completed till 19.10.25 . Instruct to expedite integration work .