EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 2 nos. OHT EMF installed and remaining to be installed . Firm again comitted to integrat all till 10.9.25
EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 3 nos. OHT EMF installed and remaining to be installed . Firm again comitted to integrat all till 15.9.25
EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 3 nos. OHT EMF installed and remaining to be installed . Firm again comitted to integrat all till 15.9.25
EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 4 nos. OHT EMF installed and remaining to be installed . Commissioning of installed equipment shall be completed till 30.9.25
EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 4 nos. OHT EMF installed and remaining to be installed . Commissioning of installed equipment shall be completed till 30.9.25 . Commissioning team yet to be reach at site .
EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 4 nos. OHT EMF installed and remaining to be installed . Commissioning of installed equipment shall be completed till 30.9.25 . Commissioning team reached at site . Work progress are slow .
EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 4 nos. OHT EMF installed and remaining to be installed . Commissioning of installed equipment shall be completed till 30.9.25 . Commissioning team reached at site . Work progress are slow . Integration work to be expedite .
EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 4 nos. OHT EMF installed and remaining to be installed . As per firm recommittment Commissioning of installed equipment should have completed till 30.10.25 . Work progress are slow .
EMF and other instruments of OHT are being installed . Among 5 nos. OHT, 4 nos. OHT EMF installed and remaining to be installed . As per firm recommittment Commissioning of installed equipment should have completed till 6.11.25 . Work progress to be expedite .
EMF and other instruments of OHT has been installed . As per firm recommittment Commissioning of installed equipment should have completed till 6.11.25 . Work progress to be expedite . Work status are same as previous .