It was committed that Integration work will be completed till following dates mentioned below: 1) Intake well, WTP, GLR 1, 2, 3 till 15.7.2025 . 2) GLR 4 till 31.8.25 3) GLR 5, 6, 7, 8, 9 & 10 till 31.7.25 4) GLR 11, 12, 13, 14 till 15.8.25 But work progress are slow and as per site work status could not be completed in cited dates .
It was committed that Integration work will be completed till following dates mentioned below: 1) Intake well, WTP, GLR 1, 2, 3 till 15.7.2025 . 2) GLR 4 till 31.8.25 3) GLR 5, 6, 7, 8, 9 & 10 till 31.8.25 4) GLR 11, 12, 13, 14 till 15.8.25 . But work progress are slow and as per site work status could not be completed in cited dates .
As per microplanning all components should have integrated till 31.8.25 . But only 2 nos OHT has been made functional yet . SCADA automation work has to be expedite.
As per microplanning all components should have integrated till 31.8.25 . But only 2 nos OHT has been made functional yet . 6 OHT EMF send to manufacturer for resolving technical issue , same shall be functional till 8.10.25 .
As per microplanning all components should have integrated till 31.8.25 . But only 2 nos OHT has been made functional yet . 6 OHT EMF send to manufacturer for resolving technical issue , same shall be functional till 8.10.25 . Revised microplanning to be provided.
As per microplanning all components should have integrated till 31.8.25 . But only 2 nos OHT has been made functional yet . 6 OHT EMF send to manufacturer for resolving technical issue , same shall be functional till 8.10.25 . Revised microplanning to be provided. Integration work to be expedite .