Total Record : 2
S. No. | Nodal Officer Name | District | Inspection Date | Scheme Name | Village Name | HGJ Certificaton Date | Agency Name/Phase | Regular water supply Status | Road Restoration (KM) | OHT Progress Completed (%) | FHTC | Distribution (KM) | Complaints | ||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Target | Completed | Target | Completed | Target | Completed | Received | Closed Complains | ||||||||||
Total | 6.59 | 6.59 | -- | 310 | 310 | 0 | 0 | 7 | 5 | ||||||||
1 | Sewa Lal | Etah | 24-Jul-2025 | PAHARPUR | Pahar Pur | 02-Jun-2024 | JMC - Lakshmi (JV) | नहीं | 2.81 | 2.81 | 0% | 145 | 145 | 0 | 0 | 1 | 1 |
2 | Sewa Lal | Etah | 25-Jul-2025 | NAGLA SHYAM AND AMIRPUR | Nagala Shyam | 21-Jun-2023 | Power Mech Projects Ltd | नहीं | 3.78 | 3.78 | 0% | 165 | 165 | 0 | 0 | 6 | 4 |