Total Record : 3
S. No. | Nodal Officer Name | District | Inspection Date | Scheme Name | Village Name | HGJ Certificaton Date | Agency Name/Phase | Regular water supply Status | Road Restoration (KM) | OHT Progress Completed (%) | FHTC | Distribution (KM) | Complaints | ||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Target | Completed | Target | Completed | Target | Completed | Received | Closed Complains | ||||||||||
Total | 16.80 | 16.80 | -- | 1473 | 1473 | 0 | 0 | 32 | 28 | ||||||||
1 | Sewa Lal | Pilibhit | 11-Jul-2025 | NAGRIA (MUSTQIL) +1 MULTI GP WATER SUPPLY SCHEME | Nagria (mustqil) | 17-Sep-2024 | VISHVARAJ | हाँ | 5.42 | 5.42 | 0% | 400 | 400 | 0 | 0 | 18 | 14 |
2 | Sewa Lal | Pilibhit | 10-Jul-2025 | BAMRAULI VILLAGE WATER SUPPLY SCHEME | Bamrauli | 25-Oct-2023 | PNC-SPML-JV | हाँ | 7.15 | 7.15 | 0% | 741 | 741 | 0 | 0 | 9 | 9 |