Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38318 | 37927 | 98.98 |
2 | Pump House | 38318 | 37131 | 96.90 |
3 | OHT | 36378 | 35741/17556 | 98.25 |
4 | Distribution (Line Laying in Km.) | 450118 | 424405 | 94.29 |
5 | Solar Plant | 32809 | 28785 | 87.74 |
6 | HGJ Status | 72213 | 35014 | 48.49 |
7 | Comissioning of Village | 72213 | 44374 | 61.45 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 180384 | 175526 | 97.31 |