Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38329 | 37908 | 98.90 |
2 | Pump House | 38329 | 36928 | 96.34 |
3 | OHT | 36386 | 35812/14988 | 98.42 |
4 | Distribution (Line Laying in Km.) | 424245 | 424245 | 100.00 |
5 | Solar Plant | 32827 | 28562 | 87.01 |
6 | HGJ Status | 72117 | 32154 | 44.59 |
7 | Comissioning of Village | 72117 | 42178 | 58.49 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 178197 | 174068 | 97.68 |