Components Wise Physical Progress

Physical Progress Phase-2, 3 & 5

Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 38386 38011 99.02
2 Pump House 38386 37306 97.19
3 OHT 36444 35849/21154 98.37
4 Distribution (Line Laying in Km.) 450571 426777 94.72
5 Solar Plant 32838 29176 88.85
6 HGJ Status 72776 42108 57.86
7 Comissioning of Village 72776 47751 65.61
8 ROAD DISMENTLING/RESTORATION(KM) 194486 192880 99.17