Physical Progress Phase-2, 3 & 5 |
||||
|---|---|---|---|---|
| Sr.No. | Components | Taget | Achivement | % |
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 38389 | 37991 | 98.96 |
| 2 | Pump House | 38389 | 37255 | 97.05 |
| 3 | OHT | 36450 | 35520/18388 | 97.45 |
| 4 | Distribution (Line Laying in Km.) | 450565 | 425752 | 94.49 |
| 5 | Solar Plant | 32867 | 28977 | 88.16 |
| 6 | HGJ Status | 72819 | 37185 | 51.06 |
| 7 | Comissioning of Village | 72819 | 45772 | 62.86 |
| 8 | ROAD DISMENTLING/RESTORATION(KM) | 181750 | 177110 | 97.45 |