Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38328 | 37922 | 98.94 |
2 | Pump House | 38328 | 37108 | 96.82 |
3 | OHT | 36387 | 35737/16665 | 98.21 |
4 | Distribution (Line Laying in Km.) | 450157 | 423951 | 94.18 |
5 | Solar Plant | 32817 | 28694 | 87.44 |
6 | HGJ Status | 72115 | 34222 | 47.45 |
7 | Comissioning of Village | 72115 | 43867 | 60.83 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 178448 | 174207 | 97.62 |