Physical Progress Phase-2, 3 & 5 |
||||
|---|---|---|---|---|
| Sr.No. | Components | Taget | Achivement | % |
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 38388 | 37990 | 98.96 |
| 2 | Pump House | 38388 | 37274 | 97.10 |
| 3 | OHT | 36449 | 35505/18774 | 97.41 |
| 4 | Distribution (Line Laying in Km.) | 450540 | 425959 | 94.54 |
| 5 | Solar Plant | 32866 | 29010 | 88.27 |
| 6 | HGJ Status | 72798 | 37305 | 51.24 |
| 7 | Comissioning of Village | 72798 | 46283 | 63.58 |
| 8 | ROAD DISMENTLING/RESTORATION(KM) | 181818 | 177159 | 97.44 |