Components Wise Physical Progress

Physical Progress Phase-2, 3 & 5

Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 38300 37839 98.80
2 Pump House 38300 36183 94.47
3 OHT 36376 35565/7872 97.77
4 Distribution (Line Laying in Km.) 410596 410596 90.97
5 Solar Plant 32898 27368 83.19
6 HGJ Status 72207 25374 35.14
7 Comissioning of Village 72207 25612 35.47
8 ROAD DISMENTLING/RESTORATION(KM) 164804 133078 80.75