Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38329 | 37911 | 98.91 |
2 | Pump House | 38329 | 36932 | 96.36 |
3 | OHT | 36386 | 35687/14986 | 98.08 |
4 | Distribution (Line Laying in Km.) | 424260 | 424260 | 100.00 |
5 | Solar Plant | 32826 | 28560 | 87.00 |
6 | HGJ Status | 72117 | 32311 | 44.80 |
7 | Comissioning of Village | 72117 | 42236 | 58.57 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 178198 | 174079 | 97.69 |