Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38324 | 37922 | 98.95 |
2 | Pump House | 38324 | 37133 | 96.89 |
3 | OHT | 36384 | 35749/17081 | 98.25 |
4 | Distribution (Line Laying in Km.) | 450148 | 424286 | 94.25 |
5 | Solar Plant | 32815 | 28741 | 87.58 |
6 | HGJ Status | 72219 | 34727 | 48.09 |
7 | Comissioning of Village | 72219 | 44059 | 61.01 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 178868 | 173995 | 97.28 |