Components Wise Physical Progress

Physical Progress Phase-2, 3 & 5

Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 38364 37891 98.77
2 Pump House 38364 36010 93.86
3 OHT 36436 35814/6625 98.29
4 Distribution (Line Laying in Km.) 404803 404803 89.62
5 Solar Plant 32933 26839 81.50
6 HGJ Status 72293 23722 32.81
7 Comissioning of Village 72293 15518 21.47
8 ROAD DISMENTLING/RESTORATION(KM) 163221 130187 79.76