Components Wise Physical Progress

Physical Progress Phase-2, 3 & 5

Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 38388 37990 98.96
2 Pump House 38388 37242 97.01
3 OHT 36457 35519/18135 97.43