Physical Progress Phase-2, 3 & 5 |
||||
|---|---|---|---|---|
| Sr.No. | Components | Taget | Achivement | % |
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 38317 | 37928 | 98.98 |
| 2 | Pump House | 38317 | 37134 | 96.91 |
| 3 | OHT | 36377 | 35603/17846 | 97.87 |
| 4 | Distribution (Line Laying in Km.) | 450120 | 424632 | 94.34 |
| 5 | Solar Plant | 32808 | 28807 | 87.80 |
| 6 | HGJ Status | 72210 | 35261 | 48.83 |
| 7 | Comissioning of Village | 72210 | 44434 | 61.53 |
| 8 | ROAD DISMENTLING/RESTORATION(KM) | 180450 | 175549 | 97.28 |