Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Siddharth Nagar
AGENCY VSA
SCHEME ID 20059761
SCHEME NAME ROHUDILA GP WSS
ESTIMATED COST 301.97
EXPENDITURE 228.11
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11246.00 Meter
Length Laid 11246.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Siddharth Nagar Naugarh Rohudila 446639 Rohudila 477 453 95% Work In Progress Not Certified