Status Of NCs & Compliances

S.No.
District
TKC Total NCs reported Complainces Submitted By TKCs % Of Compliance Submitted No. of bills processed without compliances
(J)
Remarks(Only Critical in few words)
Critical
(A)
Major
(B)
Minor
(C )
Total
D = A+B+C
Critical
(E )
Major
(F)
Minor
(G)
Total
H=E+F+G
I = H*100/D
Total 51374 242590 15170 309134 40332 187431 11970 239733 77.55 10846
1 Jalaun
BGCCPL-Ramky (JV) 118 80 32 230 47 27 12 86 37.39 17 Revised drawings are still awaited for approval. Approved drawings are often not available at site of work.
GVPR 40 40 16 96 29 26 12 67 69.79 18 Revised drawings are still awaited for approval. Approved drawings are often not available at site of work.
2 Shravasti
Larsen & Toubro Ltd 13 18 13 44 11 15 13 39 88.64 0 1) Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. Many schemes HDPE Pipe distribution line is found open without providing end caps. 2. Site Order Book , Approved drawings are not available at site premise during execution. 3. As build drawing not submitted to UPJN and TPI.
GA INFRA-VPL 0 33 0 33 0 12 0 12 36.36 0 Cube fail -2 / Honeycomb -3 / Water logged -1 / Steel cut upto GL -1 / Steel rusted -5
3 Bahraich
GA INFRA-VPL 9 14 8 31 5 12 8 25 80.65 0 HDD Method is not implementing in possible site locations 2. Lack of proper road restoration works. 3. Lack of manpower, physical work progress is very slow. 4. As build drawing not submitted to UPJN office and to TPI also.
PNC-SPML-JV 44 76 18 138 44 70 16 130 94.20 0 1. Piling work is being done without approval of Methodology . 2. As build drawing not submitted to UPJN and TPI also
4 Balrampur
Larsen & Toubro Ltd 13 30 32 75 10 27 30 67 89.33 0 Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. 2) Pump house finishing work is not proper. 3) Lot of road restoration work is pending from the agency and quality of road restoration is not as per standard. 4. As build drawing not submitted to UPJN and TPI.
Dara- Eco Protection (JV) 14 25 22 61 11 22 21 54 88.52 0 Plywood doors have been installed in 17 Gram Panchayats. 2) HDD Method is not implementing in possible site locations. 3. Hydrotesting, disinfection, and flushing of the pipeline not done before water supply. 4. As build drawing not submitted to UPJN and TPI.
5 Lucknow
NCC Ltd. 202 1679 553 2434 88 820 553 1461 60.02 0
6 Hardoi
NCC Ltd. 1329 1616 1313 4258 996 1279 1165 3440 80.79 0 1)Major cracks seen on boundary wall. 2)Pea gravel not stacked properly at site. 3)FHTC installed outside the house. 3) Disinfection of pipe not done 4) Lifting appliances, lifting gears and Compressor was not inspected by competent agency 5) Test certificate scaffolding material not submitted.6) Nonstandard scaffolding used at site.7) Non-standard DG used at site.7) Quality issues during OHT work
7 Hathras
BGCCPL-Ramky (JV) 28 67 152 247 10 21 81 112 45.34 0 Quality of material ( sand , Brick & aggregate ) Not as per standard specification
ION EXCHANGE 11 21 14 46 8 17 8 33 71.74 0 Work done without RFI & Reinstatement work not as per standard specification
8 Rampur
LC INFRA 1 4 0 5 0 0 0 0 0.00 0 Brick Quality is not good 2.Poor workmanship3.Caution Tape not used 4.Safety belt not used 5.PPE kit not used.
NKG-PRIMUS (JV) 11 22 4 37 9 13 0 22 59.46 0 OHT construction,cube testing failure,CC road restoration ,Done work without raised RFI
SPML Infra 16 28 8 52 10 17 3 30 57.69 0 RFI was Not raised.2.Staging done without stair case 3Road restoration not done properly 4.Safety belt not used 5.PPE kit not used.6.Safety net not used.
OMIL-JWIL (JV) 16 27 2 45 13 19 2 34 75.56 0 RFI was not raised. 2.Quality of material not as per specification.3.Safety norms not followed, approved drawing not at site.
9 Meerut
Power Mech Projects Ltd 3 32 1 36 3 32 1 36 100.00 0
10 Raebareli
NCC Ltd. 47 428 78 553 44 428 78 550 99.46 0 Honey combing found in OHT, Leakage observed in OHT
Vindhya-GAJA (JV) 36 211 20 267 26 195 20 241 90.26 0 Poor quality of workmanship in OHT work, Leakage found in pipeline, Honey combing found in OHT.
11 Etawah
Indian Hume Pipe 24 42 20 86 24 42 20 86 100.00 0 All NC had been raised for OHT, Tubewell, Building, Safety and other issues. All work has been rectified by the agency and compliance has been provided by letter or mail.
OMIL-JWIL (JV) 38 17 4 59 28 17 4 49 83.05 0 1. NC raised for column beam misalignment, Spalling of concrete. 2. Fixing of anchor bolt is not proper. 02 Nos. sheet has been used to fulfill the requirement of 1.6 mm thick ring in Zn Al tank without proper butt fusion welding. Slab surface finishing is also not proper dur to which a gap has been occurred between the slab and tank sheet.
12 Hamirpur
PNC-SPML-JV 6 4 68 78 6 4 68 78 100.00 0
JWIL 5 4 86 95 5 4 86 95 100.00 0
13 Mahoba
JMC-JWIL (JV) 13 27 24 64 13 27 24 64 100.00 0
N.K. Gupta & K.B. Gupta Contractors 6 10 8 24 6 10 8 24 100.00 0
Larsen & Toubro Ltd 6 14 12 32 6 14 12 32 100.00 0
SLC-SMC (JV) 7 16 12 35 7 15 12 34 97.14 0
14 Sitapur
NCC Ltd. 317 0 0 317 18 0 0 18 5.68 0
Larsen & Toubro Ltd 0 46 110 156 0 24 60 84 53.85 0
15 Kasganj
ION EXCHANGE 0 0 0 0 0 0 0 0 0.00 0
PNC-SPML-JV 52 165 91 308 45 131 78 254 82.47 0
16 Bijnor
Vindhya-GAJA (JV) 23 6 19 48 22 4 15 41 85.42 0 un approved steel and cement,column alignment not in plumb,major honeycombs.
LC INFRA 7 3 4 14 7 2 4 13 92.86 0 column alignment not in plumb,major honeycombs,brace beam shuttering found bulge.
17 Lalitpur
DARA ENGINEERING 45 79 348 472 45 79 302 426 90.25 0
JMC-JWIL (JV) 48 66 413 527 48 66 344 458 86.91 0
Brija Banco Pvt. Ltd 10 18 52 80 10 18 31 59 73.75 0
Banko Ganga 5 10 85 100 5 10 74 89 89.00 0
M/s Sudhakara Infratech Pvt. Ltd 67 55 829 951 67 55 741 863 90.75 0
18 Lakhimpur Kheri
NCC Ltd. 45 467 230 742 36 397 198 631 85.04 0 1- Hydrotest disinfection and flushing of pipe line not done before Supply of water. 2- Road restoration work not done as per original specification. 3- Water tightness test of OHT is not done as per IS specification 10500.
Vindhya-GAJA (JV) 39 311 131 481 35 255 102 392 81.50 0 1-Weigh Batcher not used for Design Mix Concreting of OHT. 2- End Cap of the HDPE pipeline not installed after completion of day work. 3- Electrical hazard safety sign board to be display at site.
19 Jhansi
NCC Ltd. 26 93 295 414 26 93 269 388 93.72 0
Indian Hume Pipe 16 40 65 121 16 40 56 112 92.56 0
DARA ENGINEERING 19 31 62 112 19 31 58 108 96.43 0
Unipro 20 28 50 98 20 28 48 96 97.96 0
BGCCPL-Ramky (JV) 29 140 303 472 29 102 196 327 69.28 0
20 Hapur
LC INFRA 4 4 19 27 3 2 0 5 18.52 0
21 Sambhal
LC INFRA 1 2 4 7 1 1 0 2 28.57 0
NKG-PRIMUS (JV) 15 30 38 83 12 11 13 36 43.37 0 Zinc-Alum tank, Location and position of nut bolt is not as per specification, Tampering of bolt, gap in zinc laum sheet and OHT slab is seen.honey comb,steel exposer.
SPML Infra 20 30 35 85 16 10 15 41 48.24 0 Zinc-Alum tank,Location and position of nut bolt is not as per specification,Tampering of bolt, gap in zinc laum sheet and OHT slab is seen.Column beam misalignment. Honey comb
22 Etah
ION EXCHANGE 0 4 0 4 0 3 0 3 75.00 0
Power Mech Projects Ltd 12 78 95 185 12 47 65 124 67.03 0
JMC - Lakshmi (JV) 4 25 26 55 3 16 18 37 67.27 0
23 Chitrakoot
GVPR 5 5 27 37 4 1 15 20 54.05 0
Larsen & Toubro Ltd 9 31 109 149 9 16 104 129 86.58 0
24 Mirzapur
NCC Ltd. 374 3127 270 3771 374 3127 270 3771 100.00 62 -
Megha 707 2703 81 3491 448 2118 72 2638 75.57 49 Many Leakage/seepage points have been observed in the CWR tank.
GA INFRA 963 3192 125 4280 963 3192 125 4280 100.00 25 -
GVPR 172 1350 49 1571 67 560 26 653 41.57 20 1- Leakage/seepage found in ESR bottom dome. 2 -The level of the stairs does not seem to be correct, the stairs appear to be tilted to one side.
Ramky baba 423 2037 153 2613 38 213 25 276 10.56 32 1 - Significant water stagnation observed around the RCC pedestal of the OHT 2 - The adjacent soil appears soft ,damp, and partially eroded. 3- Signs of algae formation and water logging persist despite multiple site visits
Multiurban 50 263 10 323 50 263 10 323 100.00 19 -
25 Sonbhadra
Jain Const. 9 176 14 199 9 176 14 199 100.00 18 -
Larsen & Toubro Ltd 47 1794 60 1901 47 1439 43 1529 80.43 76 1. Pipe joint is leakage from more than 4 months. 2. Flange is welded with pipe which is not acceptable at any cost.
GVPR 119 1233 34 1386 119 1023 23 1165 84.05 26 1. Pipe were not laid as per required Depth and left open. 2. Pipe laid directly on the surface.
VPRPL 165 2357 76 2598 165 2284 55 2504 96.38 81 After completion of pipe laying work BT road dismantled but it has not been restored.
NCC Ltd. 106 1794 21 1921 106 1624 17 1747 90.94 20 1.Waste slab thickness not found as per drawing specifications. 2. Rise and trade not found as per drawing specifications.
26 Azamgarh
ECO PROTECTION ENGINEER 181 396 3 580 166 374 0 540 93.10 0 The depth of the trench was found 700 mm at many locations whereas as per IS standard it should be 1 meter+dia of pipe.
GA INFRA - BABA (JV) 409 1354 53 1816 141 464 13 618 34.03 0 1.) Backfilling of trenches after pipe laying is not being done layer-wise which could cause major accidents. 2.)The dia of the reinforcement bar was used 6 mm instead of 8mm in pump house slab beam. 3.)Material testing are not being done as per the norms due to which inadequate materials are used at site and could cause major failure of structure.
GAJA - SGIPL (JV) 221 1098 23 1342 140 790 5 935 69.67 0 1.) The oversized gravel was used at site for raft foundation. 2.) The spacing of the Shear stirrups were not provided properly In column and Brace Beam.
LC INFRA 1725 6158 276 8159 1608 4978 192 6778 83.07 0 1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.) Construction materials such as cement, sand, aggregate, bricks and shuttering materials were not found of satisfactory quality and standards. 3) honeycomb was observed in major area of the raft foundation.
SIEPL – BRCCPL (JV) / SKYLARK 221 527 84 832 93 228 15 336 40.38 0 Proper layer wise compaction is not being performed which causes depression on road, resulting accidents
M/s Sudhakara Infratech Pvt. Ltd 1635 4658 115 6408 1175 3239 41 4455 69.52 0 1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.)Rusted steel bars were used for slab and OHT work which Is not as per IS specification's.
VIKRAN-VPRPL (JV) 380 863 120 1363 288 412 35 735 53.93 0 Curing is not being done properly hence structure is not able to achieve its optimum strength.
27 Ballia
Eagle Infra- Sudhakara Infra JV 253 641 10 904 249 557 8 814 90.04 0 Trench has been found open in pakkakote,After pipe laying work compaction must be done in layer wise using compactor.
GAJA - GAIPL JV 218 1338 0 1556 195 1203 0 1398 89.85 0 1- Compaction not done after backfilling .pipe laying work is completed, trench is backfilled haphazardly without any proper layering , watering and Compaction which is not as per clause no-8.1.2 of Indian Standard 7634:2012 (part-2) 2. Depth of the trench observed is 470mm at the top of the 63mm HDPE Pipe whereas as per DPR the Depth should be at least 1000mm+ of pipe
Larsen & Toubro Ltd 408 770 10 1188 394 680 8 1082 91.08 0 Proper finishing not found of OHT Stair .Curing not properly done 2. Trench has been found open in pakkakote, After pipe laying work compaction must be done in layer wise using compactor.
28 Mau
LC INFRA 738 5179 149 6066 595 2345 108 3048 50.25 0 1.) Severe cracks were observed in the boundary wall due to lack of curing work 2.)Multiple lapping is provided at a single section of the beam/raft which could reduce the strength of structure at those locations.
GA INFRA-VPL 429 4328 17 4774 221 2384 14 2619 54.86 0 1.)End cap found open due to which insects are entering through the inlet of the pipe, it may cause various diseases in supplied water. 2.)Soil compaction of trenches after pipe laying is not being done layer-wise which could cause major accidents.
KLSR - RAYS (JV) 75 1792 16 1883 56 690 2 748 39.72 0 1.) Open trench was found, after laying HDPE pipe soil back filling was not done it's more than 3days; which may cause accidents. 2.) Dent was found over the screen pipe which may leads to collapse of assembly system.
29 Amethi
Vindhya-GAJA (JV) 18 33 26 77 16 20 13 49 63.64 0 Size of Riser tread of staircase not found as per specifications. Landing beam bars are curtailed.
Gayatri Projects LTD 12 26 24 62 10 10 6 26 41.94 0 Regarding Honey combing and UPV test.
Welspun Kaveri Infraprojects JV 9 13 19 41 9 10 16 35 85.37 0
30 Bulandshahr
Welspun Kaveri Infraprojects JV 0 24 0 24 0 24 0 24 100.00 0
Power Mech Projects Ltd 2 10 1 13 2 10 1 13 100.00 0
JMC - Lakshmi (JV) 1 59 2 62 1 59 2 62 100.00 0
31 Sant Ravidas Nagar
Welspun Kaveri Infraprojects JV 1089 2531 149 3769 770 1899 139 2808 74.50 87 1. Washer and lock nut not provided in solar foundation. 2. Crack has been found in pump house wall. 3. Staircase thread & riser size is not found ok. 4. Staircase 1st landing slab size & level not found properly. 5. ESR work has been stopped for almost 5 months. 6. There is a lot of rust in the reinforcement used in ESR, due to which the upper layer of the steel is slowly getting destroyed.
GA INFRA - BABA (JV) 980 1882 166 3028 531 1442 153 2126 70.21 36 1. The cement placed in rampur ESR location has completely set. 2. The soil of the foundation of the boundary wall of Rampur ESR has been washed away by rain, due to which the boundary wall can collapse any time. 3. Crack has been found in boundary wall at many places. 4. Boundary wall plumb & alignment is not found properly. 5. Honeycombing has been found in ESR column and beam at many places. 6
32 Pilibhit
VISHVARAJ 11 16 49 76 11 16 49 76 100.00 0
PNC-SPML-JV 27 30 60 117 24 30 60 114 97.44 0
33 Gautam Buddha Nagar
LC INFRA 0 9 7 16 0 8 4 12 75.00 0
34 Muzaffarnagar
Gayatri Projects LTD 2 4 0 6 2 2 0 4 66.67 0
NKG-PRIMUS (JV) 62 26 4 92 22 1 0 23 25.00 0
JMC - Lakshmi (JV) 151 108 15 274 80 28 0 108 39.42 0
35 Banda
Larsen & Toubro Ltd 9 9 67 85 9 9 67 85 100.00 0
NCC Ltd. 9 11 29 49 9 11 29 49 100.00 0
36 Budaun
NCC Ltd. 3 4 2 9 3 4 2 9 100.00 0
PNC-SPML-JV 75 149 8 232 74 125 8 207 89.22 0 1. 99 Nos compliance closed at site but not received officially in written. 2. Work done without RFI's. 3. Poor workmanship.
37 Ambedkar Nagar
Welspun Kaveri Infraprojects JV 11 27 2 40 9 14 2 25 62.50 0
Vindhya-GAJA (JV) 56 124 4 184 56 69 2 127 69.02 0
38 Sant Kabeer Nagar
JAKSON - VISHVARAJ (JV) 22 74 61 157 20 23 13 56 35.67 0 Lapping in TB2 beam is not done as per specification whereas it should be 49D in M-25 Grade of concrete as per approved drawing. Alignment of beam is not as per drawing and design.
Megha 26 82 54 162 10 24 22 56 34.57 0 It was found at the site there is a large gap between the precast columns and the beam of OHT. Whereas gap should be 25 mm as per approved OHT Drawing. As per IS 15916 -2011, ±10 % tolerance allowed in precast components. Precast OHT Column dowel bars found 410 mm instead of 500 mm. Zinc Aluminum tank is corroded, Large gap between OHT slab and hold down bracket.
39 Ghaziabad
LC INFRA 4 12 3 19 4 7 2 13 68.42 0
40 Gonda
KLSR - RAYS (JV) 5 32 25 62 1 12 7 20 32.26 0 Road Restoration, Safety issue, Material issue, Poor workmanship
Larsen & Toubro Ltd 8 20 32 60 3 7 10 20 33.33 0 Road Restoration , Poor workmanship, Regular water supply without chlorination, Ladder issue of OHT
41 Shamli
Gayatri Projects LTD 2 4 2 8 1 0 0 1 12.50 0
JMC - Lakshmi (JV) 54 70 9 133 26 12 6 44 33.08 0
42 Baghpat
LC INFRA 4 10 17 31 4 10 13 27 87.10 0
43 Siddharth Nagar
VSA 29 85 7 121 16 12 1 29 23.97 0
Megha 57 170 15 242 23 24 3 50 20.66 0
JAKSON - VISHVARAJ (JV) 70 274 14 358 41 70 8 119 33.24 0
44 Auraiya
Indian Hume Pipe 9 13 3 25 9 13 3 25 100.00 0
GVPR 69 29 6 104 66 28 6 100 96.15 0
45 Barabanki
Gayatri Projects LTD 5 9 0 14 4 1 0 5 35.71 0
Megha 72 53 2 127 39 15 0 54 42.52 0
PNC-SPML-JV 49 50 2 101 37 19 1 57 56.44 0
Vindhya-GAJA (JV) 25 22 0 47 14 7 0 21 44.68 0
VSA 12 13 0 25 12 3 0 15 60.00 0
46 Saharanpur
Gayatri Projects LTD 10 111 2 123 5 22 0 27 21.95 0 Poor quality construction work pump house. CC road reinstatement poor workmanship.
GA INFRA - BABA (JV) 88 229 18 335 61 103 16 180 53.73 0 Poor Quality work OHT 3rd brace beam & column not plumb. Without complete staircase work & plumb of brace beam Inappropriate size of staircase Poor Quality work OHT column found honeycomb
NKG-PRIMUS (JV) 9 116 6 131 6 72 3 81 61.83 0 Poor quality construction work pump house. CC road reinstatement poor workmanship.
47 Ayodhya
VSA 31 38 18 87 22 19 9 50 57.47 0
UNIVERSAL MEP 2 25 10 37 2 25 9 36 97.30 0
Gayatri Projects LTD 5 14 4 23 3 11 4 18 78.26 0
Vindhya-GAJA (JV) 8 15 7 30 5 12 5 22 73.33 0
48 Amroha
LC INFRA 3 2 3 8 2 2 2 6 75.00 0 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT
OMIL-JWIL (JV) 87 121 44 252 79 116 39 234 92.86 0 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT
SPML Infra 80 87 36 203 61 84 31 176 86.70 0 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT
49 Moradabad
LC INFRA 40 20 169 229 40 17 164 221 96.51 0 Cube Test Not Conduct Properly 07 days & 28 days , Approved Drawing Not Avaliable at site , Majorcracks seen on Boundary wall , PPE Kit Not avaliable at site & Saftey Negligence during dome casting.
NKG-PRIMUS (JV) 33 27 112 172 30 22 102 154 89.53 0 Staging Done Without Staircase , Brick Quality is not good & Saftey negligence during dome casting.
50 Kanpur Dehat
GVPR 4 9 10 23 4 9 10 23 100.00 0
Indian Hume Pipe 5 5 10 20 5 5 10 20 100.00 0
Vindhya-GAJA (JV) 2 5 2 9 1 5 2 8 88.89 0 For Gutaiya WSS Critical NC compliances submitted but its under observation for testing, that's why one NC is pending.
VSA 26 18 23 67 26 18 23 67 100.00 0 3 nos OHT partial dismantle
51 Farrukhabad
Vindhya-GAJA (JV) 2 32 21 55 2 28 21 51 92.73 0
GVPR 33 49 39 121 18 35 31 84 69.42 0
52 Kanpur Nagar
VSA 28 21 34 83 21 21 34 76 91.57 0
Vindhya-GAJA (JV) 74 35 52 161 70 35 52 157 97.52 0
53 Mathura
NCC-APCO JV 8 111 6 125 3 75 4 82 65.60 0
54 Agra
Megha 132 31 4 167 96 20 2 118 70.66 0
NCC-APCO JV 49 24 6 79 47 23 6 76 96.20 0
55 Basti
Megha 133 156 186 475 92 88 112 292 61.47 0
JAKSON - VISHVARAJ (JV) 9 33 22 64 4 26 20 50 78.13 0
VSA 6 11 14 31 4 9 12 25 80.65 0
56 Kannauj
GVPR 19 59 40 118 18 55 32 105 88.98 0 Road Restoration Not Done, honeycomb observed, work Without RFI
VSA 63 78 79 220 60 74 55 189 85.91 0 ZN-AL tank Fusion Not Done, Road Restoration Not Done, Column misalignment observed, honeycomb observed, work Without RFI
57 Shahjahanpur
NCC Ltd. 17 29 23 69 13 27 21 61 88.41 0
58 Varanasi
Larsen & Toubro Ltd 3514 25217 1201 29932 3176 21896 1053 26125 87.28 650 "1-Cracks observed in Boundary wall. 2-Ganga sand used at site. 3-Joints of brickwork are not filled properly 4-Width of trench found 230mm which is not as per IS code 4984:2016.It should be 600+ dia of pipe as per DPR. 5-Mortar used for the Brick work was not as per DPR and specifications. 6-Curing of the brick work was not properly done.It may result in low hydration of cement and reduce the bo
59 Jaunpur
Welspun Kaveri Infraprojects JV 2032 5658 180 7870 1880 5108 164 7152 90.88 543 Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow and Road restoration work slow
AFCONS 2793 5351 178 8322 2504 4922 150 7576 91.04 636 Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow
60 Ghazipur
HFCL- JWIL (JV) 1806 4166 100 6072 1601 3554 99 5254 86.53 0 "1-Width of the trench observed is 200mm at the top of the trench whereas as per DPR the width should be at least 600mm+ of pipe. 2-Quality of sand, 10mm, 20mm Aggregate not satisfactory 3- 75mm HDPE Pipe found laid in damage condition. 4-Depth of the trench is found 600mm at the top of the 63mm HDPE Pipe , whereas as per DPR the Depth should be at least 1000mm+ Dia of pipe. 5-MDPE pipe (20mm) f
Larsen & Toubro Ltd 2961 5635 249 8845 2219 4057 215 6491 73.39 169 "1-The DPC layer of boundary wall is damaged 2- Honeycombing is found on the coping of the boundary wall 3- Honeycombing is found on the roof of the pump house."
VSA 3305 6374 73 9752 1770 2130 17 3917 40.17 140 "1-Rusted steel used in ground beam work 2-Honeycombing is found in the Ring/Tie beam , Columns of the OHT. 3-Rusted bars are using in the construction of OHT foundation. 4-Cracks are found in the slab of the pump house. 5-Cracks are found in the boundary wall."
61 Chandauli
GA INFRA - BABA (JV) 258 3465 78 3801 252 3366 72 3690 97.08 184 "1-Hand concrete mixer is being used for concrete mixing instead of weightbatch concrete mixer. 2-Dirty water used for mixing of concreting, which is against clause 4.6 of IS;2250 3-Honeycomb observed in Pump house ( Chajja) 4-Rusted reinforcement use in pump house slab 5-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new brick for re
HFCL- JWIL (JV) 168 1420 23 1611 159 1358 21 1538 95.47 0 "1-Hand concrete mixer used for concrete mixing Instead of PLC based weighbatch concrete mixer. 2-Depth found 800mm found for 63mm dia HDPE Pipe laying as per DPR it should be 1000mm+Dia 3-Second class bricks are available at site , whereas per the DPR 1st class bricks should be used. 4-Curing of concrete of boundary wall coping casting work not done after de-shuttering . 5-MDPE pipe found above
ION EXCHANGE 669 5846 78 6593 635 5638 71 6344 96.22 211 "1-10mm,20mm aggregate found failed during sieve analasys test 2-Depth of 140mm dia HDPE Pipe found 570mm whereas as per the DPR ,pipe should be laid at least 1.0m+Dia 3-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new Brick should be used for restoration work 4-Hand concrete mixer used for concrete mixing Instead of PLC based weig
VSA 1029 6283 255 7567 1018 6197 251 7466 98.67 307 "1-Grouting of GI pipe not done 2-MDPE pipe found above GL level ( open condition) 3-100 percent old brick use for BOE road restoration work, As per DPR it should be 50 percent old and 50 percent new brick for BOE road restoration work 4-Depth of 63mm dia HDPE Pipe found 700mm, whereas as per the DPR depth should be 1m+dia 5-Reinstatement not done from last one month. Restoration work is being pe
East India Udhyog- Kaveri JV 17 412 1 430 16 353 1 370 86.05 0 LAYING OF HDPE PIPE IS NOT DONE PROPERLY AT SOME PLACES DEPTH IS FOUND 600 -700MM
62 Deoria
LC INFRA 1080 7674 65 8819 820 5534 46 6400 72.57 1948 1.-Cracks has been observed in wall of pump house.,2.Crack has been observed on the boundary wall.,3.Steel is visible in lintel beam of pump house.
Gayatri Projects LTD 986 6965 31 7982 905 6023 25 6953 87.11 1287 1.Crack has been observed on the boundary wall.,2.Steel is visible in coping of boundary wall.
Rithwik-Koya (JV) 201 2036 21 2258 155 1386 10 1551 68.69 101 1.3rd brace column finishing not done properly.,2.Honeycomb has been observed on the 6th lift staircase of OHT.
UNIVERSAL MEP 177 1020 8 1205 166 935 6 1107 91.87 30 1.Crack has been observed on the boundary wall.2.Crack has been observed on coping of boundary wall.
63 Gorakhpur
NCC Ltd. 956 14597 629 16182 714 10455 498 11667 72.10 2627 1. GI cashing has not been provided at Culvert crossing. 2. Crack has been observed in the boundary wall. 6. Crack has been observed in the pump house floor. 7. Paint quality is not good of boundary wall. 8. Campus approach road has been settled down. 9. Recharge pit chamber has been found damaged. 10. Honeycomb has been found in OHT TB-2.
Rithwik-Koya (JV) 345 5318 209 5872 262 4464 145 4871 82.95 320 1. Cracks has been observed in the boundary wall. 2. HDPE pipe found exposed condition end cap is not provided. 5.Boundary wall coping has been observed damage. 6. Lightning arrester has not been installed on the OHT. 7. The painting work on the OHT has not been done properly. 8. Crack has been found in the OHT apron.
64 Maharajganj
JMC - Lakshmi (JV) 630 7049 15 7694 550 5756 12 6318 82.12 486 1.Rusted steel found at construction site. 2.Honeycomb found in OHT 2nd brace beam. 3. Crack has been found in Boundary wall brick work below DPC. 4. Pump House apron has been settled down. 5. Crack observed in Boundary wall. 6.HDPE pipe found in damage condition. 7.Honey combing found in 2nd Brace beam.
Rithwik-Koya (JV) 417 3547 7 3971 283 2395 3 2681 67.51 0 1. Honeycombing found in OHT 2nd flight staircase landing. 2. Steel is visible in OHT stair case cantilever beam. 3.OHT 1st lift column has been broken and extra reinforcement is not available for further casting. 4.Pump house Apron found damaged. 5. Steel is visible in OHT 1st brace beam above lift column. 6. Crack found on the wall of Pump house.
65 Kushi Nagar
NCC Ltd. 2722 17494 217 20433 2684 17279 195 20158 98.65 621 1. Leakage has been observed in the main raising pipe. 2.Lighting conductor has not been installed as per electricals norms, Its very short length from NGL,The height should be sufficient to create a protective cone covering the building or equipment. 3.It has been observed that Mild Steel (MS) earthing strips have been used at the site in place of the specified Galvanized Iron (GI) strips, which
66 Prayagraj
Larsen & Toubro Ltd 2328 13599 450 16377 1908 12311 393 14612 89.22 0 Sunshade of pump house has been found damaged.
VPRPL 303 711 11 1025 266 548 8 822 80.20 0 Steel bars have been exposed at the bottom of waist slab of staircase.
GAJA - GAIPL JV 502 634 3 1139 444 530 3 977 85.78 0 The alignment of column has been found incorrect. It has been observed tilted.
67 Kaushambi
GA INFRA - BABA (JV) 739 4365 299 5403 358 2342 200 2900 53.67 0 No cut out has been made at the slab of the oht for inlet and outlet pipe. As hammering in slab should be avoided to counter strength reduction.
JMC - Lakshmi (JV) 601 3286 201 4088 477 2738 170 3385 82.80 0 Honeycomb has been observed at the outer face of conical wall . poor work was done for the construction of conical wall.
68 Fatehpur
Gayatri Projects LTD 336 6772 292 7400 147 2360 74 2581 34.88 0 "1.Severe crack has been developed in the boundary wall. 2.Upper part of tubewell is getting rusted. And also Pea gravel feeding has not been done."
GA INFRA - BABA (JV) 160 1010 20 1190 102 456 4 562 47.23 0 "1.Pea gravel packing in chamber of Pump House has not been done. 2.Tube Well has been left without bore well cap which may cause menace in village."
Power Mech Projects Ltd 835 5275 183 6293 465 2444 65 2974 47.26 0 "1.One panel of boundary wall has been found collapsed due to soil stacked behind it. 2.boundary wall has been found collapsed. The length was aprox. 15 mtr."
69 Pratapgarh
JMC - Lakshmi (JV) 896 3942 186 5024 604 3158 155 3917 77.97 0 The painting work of the overhead tank staircase has not been carried out properly, Finishing work was not observed properly in the OHT 2nd lift column above GL brace beam.
Power Mech Projects Ltd 1443 3453 56 4952 1190 2914 8 4112 83.04 0 Washout chamber has been found severely cracked/damaged. Reconstruction required, Boundary wall has been found severely cracked
70 Bareilly
NCC Ltd. 37 60 36 133 34 59 36 129 96.99 0 1. Leakage found in Zinc-alum Tank around the jointing of bottom ring wall. 2. MDPE pipe intended for FHTCs have been laid through an existing waste water drain.
71 Mainpuri
NCC Ltd. 20 56 19 95 12 48 17 77 81.05 0
72 Sultanpur
UNIVERSAL MEP 0 0 0 0 13 11 13 37 3700.00 0
Gayatri Projects LTD 18 19 17 54 8 9 13 30 55.56 0
Vindhya-GAJA (JV) 70 125 131 326 51 43 62 156 47.85 0
73 Aligarh
ION EXCHANGE 11 51 14 76 11 47 14 72 94.74 0
JMC - Lakshmi (JV) 12 85 2 99 11 79 1 91 91.92 0
PNC-SPML-JV 15 117 9 141 15 111 9 135 95.74 0
74 Firozabad
Larsen & Toubro Ltd 5 251 7 263 5 158 7 170 64.64 0
NCC Ltd. 0 144 1 145 0 133 1 134 92.41 0