S.No. |
District
|
TKC | Total NCs reported | Complainces Submitted By TKCs | % Of Compliance Submitted | No. of bills processed without compliances (J) |
Remarks(Only Critical in few words) |
||||||
Critical (A) |
Major (B) |
Minor (C ) |
Total D = A+B+C |
Critical (E ) |
Major (F) |
Minor (G) |
Total H=E+F+G |
I = H*100/D | |||||
Total | 59691 | 237085 | 14782 | 311558 | 46932 | 176451 | 11457 | 234840 | 75.38 | 11137 | |||
1 |
Jalaun |
BGCCPL-Ramky (JV) | 118 | 80 | 32 | 230 | 47 | 27 | 12 | 86 | 37.39 | 17 | Revised drawings are still awaited for approval. Approved drawings are often not available at site of work. |
GVPR | 40 | 40 | 16 | 96 | 29 | 26 | 12 | 67 | 69.79 | 18 | Revised drawings are still awaited for approval. Approved drawings are often not available at site of work. | ||
2 |
Budaun |
NCC Ltd. | 2 | 4 | 2 | 8 | 2 | 4 | 2 | 8 | 100.00 | 0 | All compliances in respect of all NCs submitted by the agency have been scrutinized and found satisfactory. |
PNC-SPML-JV | 74 | 145 | 8 | 227 | 63 | 125 | 8 | 196 | 86.34 | 0 | 1. 99 Nos compliance closed at site but not received officially in written. 2. Work done without RFI's. 3. Poor workmanship. | ||
3 |
Shravasti |
Larsen & Toubro Ltd | 13 | 18 | 13 | 44 | 11 | 15 | 13 | 39 | 88.64 | 0 | 1) Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. Many schemes HDPE Pipe distribution line is found open without providing end caps. 2. Site Order Book , Approved drawings are not available at site premise during execution. 3. As build drawing not submitted to UPJN and TPI. |
GA INFRA-VPL | 0 | 33 | 0 | 33 | 0 | 12 | 0 | 12 | 36.36 | 0 | Cube fail -2 / Honeycomb -3 / Water logged -1 / Steel cut upto GL -1 / Steel rusted -5 | ||
4 |
Bahraich |
GA INFRA-VPL | 9 | 14 | 8 | 31 | 5 | 12 | 8 | 25 | 80.65 | 0 | HDD Method is not implementing in possible site locations 2. Lack of proper road restoration works. 3. Lack of manpower, physical work progress is very slow. 4. As build drawing not submitted to UPJN office and to TPI also. |
PNC-SPML-JV | 44 | 76 | 18 | 138 | 44 | 70 | 16 | 130 | 94.20 | 0 | 1. Piling work is being done without approval of Methodology . 2. As build drawing not submitted to UPJN and TPI also | ||
5 |
Balrampur |
Larsen & Toubro Ltd | 13 | 30 | 32 | 75 | 10 | 27 | 30 | 67 | 89.33 | 0 | Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. 2) Pump house finishing work is not proper. 3) Lot of road restoration work is pending from the agency and quality of road restoration is not as per standard. 4. As build drawing not submitted to UPJN and TPI. |
Dara- Eco Protection (JV) | 14 | 25 | 22 | 61 | 11 | 22 | 21 | 54 | 88.52 | 0 | Plywood doors have been installed in 17 Gram Panchayats. 2) HDD Method is not implementing in possible site locations. 3. Hydrotesting, disinfection, and flushing of the pipeline not done before water supply. 4. As build drawing not submitted to UPJN and TPI. | ||
6 |
Lucknow |
NCC Ltd. | 202 | 1679 | 553 | 2434 | 88 | 820 | 553 | 1461 | 60.02 | 0 | |
7 |
Hardoi |
NCC Ltd. | 1329 | 1616 | 1313 | 4258 | 996 | 1279 | 1165 | 3440 | 80.79 | 0 | 1)Major cracks seen on boundary wall. 2)Pea gravel not stacked properly at site. 3)FHTC installed outside the house. 3) Disinfection of pipe not done 4) Lifting appliances, lifting gears and Compressor was not inspected by competent agency 5) Test certificate scaffolding material not submitted.6) Nonstandard scaffolding used at site.7) Non-standard DG used at site.7) Quality issues during OHT work |
8 |
Kannauj |
GVPR | 31 | 35 | 38 | 104 | 30 | 31 | 36 | 97 | 93.27 | 0 | 1. Road restoration work not done as per Specification. 2. Solar Work in progress without submitting Approved Drawing.3. Poor Workmanship. 4. Poor quality of Materials. 5. Ignorance of Safety Measures. |
VSA | 81 | 67 | 64 | 212 | 68 | 58 | 60 | 186 | 87.74 | 0 | 1. Road Reinstatement not done as per specification and against total dismantling length. 2. Availability of Quality documents during work or after work as required not provided. 3. Work done without RFI. 4. Poor workmanship. 5. Third quality of materials. | ||
9 |
Moradabad |
LC INFRA | 40 | 20 | 169 | 229 | 32 | 17 | 126 | 175 | 76.42 | 0 | Cube Test Not Conduct Properly 07 days & 28 days , Approved Drawing Not Avaliable at site , Majorcracks seen on Boundary wall , PPE Kit Not avaliable at site & Saftey Negligence during dome casting. |
NKG-PRIMUS (JV) | 33 | 27 | 112 | 172 | 26 | 22 | 90 | 138 | 80.23 | 0 | Staging Done Without Staircase , Brick Quality is not good & Saftey negligence during dome casting. | ||
10 |
Hathras |
BGCCPL-Ramky (JV) | 28 | 67 | 152 | 247 | 10 | 21 | 81 | 112 | 45.34 | 0 | Quality of material ( sand , Brick & aggregate ) Not as per standard specification |
ION EXCHANGE | 11 | 21 | 14 | 46 | 8 | 17 | 8 | 33 | 71.74 | 0 | Work done without RFI & Reinstatement work not as per standard specification | ||
11 |
Rampur |
LC INFRA | 1 | 4 | 0 | 5 | 0 | 0 | 0 | 0 | 0.00 | 0 | Brick Quality is not good 2.Poor workmanship3.Caution Tape not used 4.Safety belt not used 5.PPE kit not used. |
NKG-PRIMUS (JV) | 11 | 22 | 4 | 37 | 9 | 13 | 0 | 22 | 59.46 | 0 | OHT construction,cube testing failure,CC road restoration ,Done work without raised RFI | ||
SPML Infra | 16 | 28 | 8 | 52 | 10 | 17 | 3 | 30 | 57.69 | 0 | RFI was Not raised.2.Staging done without stair case 3Road restoration not done properly 4.Safety belt not used 5.PPE kit not used.6.Safety net not used. | ||
OMIL-JWIL (JV) | 16 | 27 | 2 | 45 | 13 | 19 | 2 | 34 | 75.56 | 0 | RFI was not raised. 2.Quality of material not as per specification.3.Safety norms not followed, approved drawing not at site. | ||
12 |
Meerut |
Power Mech Projects Ltd | 3 | 32 | 1 | 36 | 3 | 32 | 1 | 36 | 100.00 | 0 | |
13 |
Raebareli |
NCC Ltd. | 47 | 428 | 78 | 553 | 44 | 428 | 78 | 550 | 99.46 | 0 | Honey combing found in OHT, Leakage observed in OHT |
Vindhya-GAJA (JV) | 36 | 211 | 20 | 267 | 26 | 195 | 20 | 241 | 90.26 | 0 | Poor quality of workmanship in OHT work, Leakage found in pipeline, Honey combing found in OHT. | ||
14 |
Shamli |
Gayatri Projects LTD | 2 | 3 | 2 | 7 | 1 | 0 | 0 | 1 | 14.29 | 0 | |
JMC - Lakshmi (JV) | 54 | 68 | 9 | 131 | 25 | 12 | 6 | 43 | 32.82 | 0 | |||
15 |
Etawah |
Indian Hume Pipe | 24 | 42 | 20 | 86 | 24 | 42 | 20 | 86 | 100.00 | 0 | All NC had been raised for OHT, Tubewell, Building, Safety and other issues. All work has been rectified by the agency and compliance has been provided by letter or mail. |
OMIL-JWIL (JV) | 37 | 17 | 4 | 58 | 29 | 17 | 4 | 50 | 86.21 | 0 | NC raised for column verticality, spalling of concrete and honeycomb in structure. | ||
16 |
Farrukhabad |
GVPR | 5 | 41 | 30 | 76 | 3 | 10 | 8 | 21 | 27.63 | 0 | 1.Sultanganj Khareta Raft foundation compliance pending 2.Chahcupur column misaligned above 2nd brace compliance pending |
Vindhya-GAJA (JV) | 1 | 15 | 35 | 51 | 1 | 15 | 21 | 37 | 72.55 | 0 | |||
17 |
Hamirpur |
PNC-SPML-JV | 6 | 4 | 68 | 78 | 6 | 4 | 68 | 78 | 100.00 | 0 | |
JWIL | 5 | 4 | 86 | 95 | 5 | 4 | 86 | 95 | 100.00 | 0 | |||
18 |
Mahoba |
JMC-JWIL (JV) | 13 | 27 | 24 | 64 | 13 | 27 | 24 | 64 | 100.00 | 0 | |
N.K. Gupta & K.B. Gupta Contractors | 6 | 10 | 8 | 24 | 6 | 10 | 8 | 24 | 100.00 | 0 | |||
Larsen & Toubro Ltd | 6 | 14 | 12 | 32 | 6 | 14 | 12 | 32 | 100.00 | 0 | |||
SLC-SMC (JV) | 7 | 16 | 12 | 35 | 7 | 15 | 12 | 34 | 97.14 | 0 | |||
19 |
Sitapur |
NCC Ltd. | 317 | 0 | 0 | 317 | 18 | 0 | 0 | 18 | 5.68 | 0 | |
Larsen & Toubro Ltd | 0 | 46 | 110 | 156 | 0 | 24 | 60 | 84 | 53.85 | 0 | |||
20 |
Gautam Buddha Nagar |
LC INFRA | 0 | 9 | 7 | 16 | 0 | 7 | 4 | 11 | 68.75 | 0 | |
21 |
Kasganj |
ION EXCHANGE | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 | 0 | |
PNC-SPML-JV | 52 | 165 | 91 | 308 | 45 | 131 | 78 | 254 | 82.47 | 0 | |||
22 |
Bijnor |
Vindhya-GAJA (JV) | 23 | 6 | 19 | 48 | 22 | 4 | 15 | 41 | 85.42 | 0 | un approved steel and cement,column alignment not in plumb,major honeycombs. |
LC INFRA | 7 | 3 | 4 | 14 | 7 | 2 | 4 | 13 | 92.86 | 0 | column alignment not in plumb,major honeycombs,brace beam shuttering found bulge. | ||
23 |
Lalitpur |
DARA ENGINEERING | 45 | 79 | 348 | 472 | 45 | 79 | 302 | 426 | 90.25 | 0 | |
JMC-JWIL (JV) | 48 | 66 | 413 | 527 | 48 | 66 | 344 | 458 | 86.91 | 0 | |||
Brija Banco Pvt. Ltd | 10 | 18 | 52 | 80 | 10 | 18 | 31 | 59 | 73.75 | 0 | |||
Banko Ganga | 5 | 10 | 85 | 100 | 5 | 10 | 74 | 89 | 89.00 | 0 | |||
M/s Sudhakara Infratech Pvt. Ltd | 67 | 55 | 829 | 951 | 67 | 55 | 741 | 863 | 90.75 | 0 | |||
24 |
Lakhimpur Kheri |
NCC Ltd. | 45 | 467 | 230 | 742 | 36 | 397 | 198 | 631 | 85.04 | 0 | 1- Hydrotest disinfection and flushing of pipe line not done before Supply of water. 2- Road restoration work not done as per original specification. 3- Water tightness test of OHT is not done as per IS specification 10500. |
Vindhya-GAJA (JV) | 39 | 311 | 131 | 481 | 35 | 255 | 102 | 392 | 81.50 | 0 | 1-Weigh Batcher not used for Design Mix Concreting of OHT. 2- End Cap of the HDPE pipeline not installed after completion of day work. 3- Electrical hazard safety sign board to be display at site. | ||
25 |
Jhansi |
NCC Ltd. | 26 | 93 | 295 | 414 | 26 | 93 | 269 | 388 | 93.72 | 0 | |
BGCCPL-Ramky (JV) | 29 | 140 | 303 | 472 | 29 | 102 | 120 | 251 | 53.18 | 0 | |||
Indian Hume Pipe | 16 | 40 | 65 | 121 | 16 | 40 | 56 | 112 | 92.56 | 0 | |||
DARA ENGINEERING | 19 | 31 | 62 | 112 | 19 | 31 | 58 | 108 | 96.43 | 0 | |||
Unipro | 20 | 28 | 50 | 98 | 20 | 28 | 48 | 96 | 97.96 | 0 | |||
26 |
Hapur |
LC INFRA | 4 | 4 | 19 | 27 | 3 | 2 | 0 | 5 | 18.52 | 0 | |
27 |
Shahjahanpur |
NCC Ltd. | 12 | 27 | 20 | 59 | 8 | 27 | 20 | 55 | 93.22 | 0 | |
28 |
Banda |
NCC Ltd. | 9 | 11 | 29 | 49 | 8 | 11 | 29 | 48 | 97.96 | 0 | |
Larsen & Toubro Ltd | 9 | 9 | 67 | 85 | 8 | 8 | 67 | 83 | 97.65 | 0 | |||
29 |
Ghaziabad |
LC INFRA | 4 | 10 | 3 | 17 | 4 | 5 | 2 | 11 | 64.71 | 0 | |
30 |
Muzaffarnagar |
Gayatri Projects LTD | 2 | 4 | 0 | 6 | 2 | 2 | 0 | 4 | 66.67 | 0 | |
JMC - Lakshmi (JV) | 150 | 107 | 15 | 272 | 75 | 27 | 0 | 102 | 37.50 | 0 | |||
NKG-PRIMUS (JV) | 63 | 25 | 4 | 92 | 18 | 1 | 0 | 19 | 20.65 | 0 | |||
31 |
Barabanki |
Gayatri Projects LTD | 4 | 7 | 0 | 11 | 4 | 1 | 0 | 5 | 45.45 | 0 | |
PNC-SPML-JV | 39 | 36 | 2 | 77 | 33 | 18 | 1 | 52 | 67.53 | 0 | |||
VSA | 12 | 11 | 0 | 23 | 12 | 3 | 0 | 15 | 65.22 | 0 | |||
Megha | 72 | 51 | 2 | 125 | 38 | 15 | 0 | 53 | 42.40 | 0 | |||
Vindhya-GAJA (JV) | 20 | 15 | 0 | 35 | 14 | 7 | 0 | 21 | 60.00 | 0 | |||
32 |
Sambhal |
LC INFRA | 1 | 2 | 4 | 7 | 1 | 1 | 0 | 2 | 28.57 | 0 | |
NKG-PRIMUS (JV) | 15 | 30 | 38 | 83 | 12 | 11 | 13 | 36 | 43.37 | 0 | Zinc-Alum tank, Location and position of nut bolt is not as per specification, Tampering of bolt, gap in zinc laum sheet and OHT slab is seen.honey comb,steel exposer. | ||
SPML Infra | 20 | 30 | 35 | 85 | 16 | 10 | 15 | 41 | 48.24 | 0 | Zinc-Alum tank,Location and position of nut bolt is not as per specification,Tampering of bolt, gap in zinc laum sheet and OHT slab is seen.Column beam misalignment. Honey comb | ||
33 |
Etah |
Power Mech Projects Ltd | 12 | 59 | 95 | 166 | 8 | 30 | 59 | 97 | 58.43 | 0 | |
JMC - Lakshmi (JV) | 4 | 25 | 25 | 54 | 4 | 10 | 16 | 30 | 55.56 | 0 | |||
ION EXCHANGE | 0 | 4 | 0 | 4 | 0 | 3 | 0 | 3 | 75.00 | 0 | |||
34 |
Amroha |
LC INFRA | 2 | 2 | 2 | 6 | 2 | 1 | 2 | 5 | 83.33 | 0 | 1) Poor Quality of Road Restoration 2) Poor Quality of FHTC work. |
OMIL-JWIL (JV) | 81 | 119 | 37 | 237 | 70 | 116 | 33 | 219 | 92.41 | 0 | 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT | ||
SPML Infra | 73 | 86 | 36 | 195 | 59 | 83 | 31 | 173 | 88.72 | 0 | 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT | ||
35 |
Siddharth Nagar |
VSA | 29 | 78 | 7 | 114 | 16 | 12 | 1 | 29 | 25.44 | 0 | Honey Combing is observed in the RCC of column & beam. The Cube has not attained its target strength in 28 days after testing in lab. It is suggested for NDT test or any other appropriate method. |
Megha | 55 | 165 | 15 | 235 | 22 | 20 | 3 | 45 | 19.15 | 0 | he RCC column of OHT not found as per specification. The Cube has not attained its target strength in 7 and 28 days after testing in lab. It is suggested for NDT test or any other appropriate method. | ||
JAKSON - VISHVARAJ (JV) | 55 | 247 | 11 | 313 | 33 | 56 | 1 | 90 | 28.75 | 0 | The Cube has not attained its target strength in 7 and 28 days after testing in lab. It is suggested for NDT test or any other appropriate method. | ||
36 |
Pilibhit |
PNC-SPML-JV | 27 | 30 | 60 | 117 | 22 | 30 | 60 | 112 | 95.73 | 0 | |
VISHVARAJ | 11 | 16 | 49 | 76 | 11 | 16 | 49 | 76 | 100.00 | 0 | |||
37 |
Chitrakoot |
GVPR | 5 | 5 | 27 | 37 | 4 | 1 | 15 | 20 | 54.05 | 0 | |
Larsen & Toubro Ltd | 9 | 31 | 109 | 149 | 9 | 16 | 104 | 129 | 86.58 | 0 | |||
38 |
Mirzapur |
NCC Ltd. | 374 | 3127 | 270 | 3771 | 374 | 3127 | 270 | 3771 | 100.00 | 62 | - |
Megha | 707 | 2703 | 81 | 3491 | 448 | 2118 | 72 | 2638 | 75.57 | 49 | Many Leakage/seepage points have been observed in the CWR tank. | ||
GA INFRA | 963 | 3192 | 125 | 4280 | 963 | 3192 | 125 | 4280 | 100.00 | 25 | - | ||
GVPR | 172 | 1350 | 49 | 1571 | 67 | 560 | 26 | 653 | 41.57 | 20 | 1- Leakage/seepage found in ESR bottom dome. 2 -The level of the stairs does not seem to be correct, the stairs appear to be tilted to one side. | ||
Ramky baba | 423 | 2037 | 153 | 2613 | 38 | 213 | 25 | 276 | 10.56 | 32 | 1 - Significant water stagnation observed around the RCC pedestal of the OHT 2 - The adjacent soil appears soft ,damp, and partially eroded. 3- Signs of algae formation and water logging persist despite multiple site visits | ||
Multiurban | 50 | 263 | 10 | 323 | 50 | 263 | 10 | 323 | 100.00 | 19 | - | ||
39 |
Kanpur Nagar |
VSA | 28 | 21 | 34 | 83 | 19 | 21 | 34 | 74 | 89.16 | 0 | |
Vindhya-GAJA (JV) | 74 | 35 | 52 | 161 | 66 | 35 | 52 | 153 | 95.03 | 0 | |||
40 |
Sonbhadra |
Jain Const. | 9 | 176 | 14 | 199 | 9 | 176 | 14 | 199 | 100.00 | 18 | - |
Larsen & Toubro Ltd | 47 | 1794 | 60 | 1901 | 47 | 1439 | 43 | 1529 | 80.43 | 76 | 1. Pipe joint is leakage from more than 4 months. 2. Flange is welded with pipe which is not acceptable at any cost. | ||
GVPR | 119 | 1233 | 34 | 1386 | 119 | 1023 | 23 | 1165 | 84.05 | 26 | 1. Pipe were not laid as per required Depth and left open. 2. Pipe laid directly on the surface. | ||
VPRPL | 165 | 2357 | 76 | 2598 | 165 | 2284 | 55 | 2504 | 96.38 | 81 | After completion of pipe laying work BT road dismantled but it has not been restored. | ||
NCC Ltd. | 106 | 1794 | 21 | 1921 | 106 | 1624 | 17 | 1747 | 90.94 | 20 | 1.Waste slab thickness not found as per drawing specifications. 2. Rise and trade not found as per drawing specifications. | ||
41 |
Azamgarh |
ECO PROTECTION ENGINEER | 181 | 396 | 3 | 580 | 166 | 374 | 0 | 540 | 93.10 | 0 | The depth of the trench was found 700 mm at many locations whereas as per IS standard it should be 1 meter+dia of pipe. |
GA INFRA - BABA (JV) | 409 | 1354 | 53 | 1816 | 141 | 464 | 13 | 618 | 34.03 | 0 | 1.) Backfilling of trenches after pipe laying is not being done layer-wise which could cause major accidents. 2.)The dia of the reinforcement bar was used 6 mm instead of 8mm in pump house slab beam. 3.)Material testing are not being done as per the norms due to which inadequate materials are used at site and could cause major failure of structure. | ||
GAJA - SGIPL (JV) | 221 | 1098 | 23 | 1342 | 140 | 790 | 5 | 935 | 69.67 | 0 | 1.) The oversized gravel was used at site for raft foundation. 2.) The spacing of the Shear stirrups were not provided properly In column and Brace Beam. | ||
LC INFRA | 1725 | 6158 | 276 | 8159 | 1608 | 4978 | 192 | 6778 | 83.07 | 0 | 1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.) Construction materials such as cement, sand, aggregate, bricks and shuttering materials were not found of satisfactory quality and standards. 3) honeycomb was observed in major area of the raft foundation. | ||
SIEPL – BRCCPL (JV) / SKYLARK | 221 | 527 | 84 | 832 | 93 | 228 | 15 | 336 | 40.38 | 0 | Proper layer wise compaction is not being performed which causes depression on road, resulting accidents | ||
M/s Sudhakara Infratech Pvt. Ltd | 1635 | 4658 | 115 | 6408 | 1175 | 3239 | 41 | 4455 | 69.52 | 0 | 1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.)Rusted steel bars were used for slab and OHT work which Is not as per IS specification's. | ||
VIKRAN-VPRPL (JV) | 380 | 863 | 120 | 1363 | 288 | 412 | 35 | 735 | 53.93 | 0 | Curing is not being done properly hence structure is not able to achieve its optimum strength. | ||
42 |
Kanpur Dehat |
Indian Hume Pipe | 5 | 5 | 10 | 20 | 5 | 5 | 10 | 20 | 100.00 | 0 | All critical NC comply through NDT and UPV test |
GVPR | 4 | 9 | 10 | 23 | 4 | 9 | 10 | 23 | 100.00 | 0 | All critical NC comply through NDT Test and rest NC rectify . | ||
VSA | 25 | 18 | 23 | 66 | 22 | 18 | 23 | 63 | 95.45 | 0 | All critical NC comply through NDT Test and rest NC rectify . 3 nos NC for Partial demolish and Partial demolished completed. | ||
Vindhya-GAJA (JV) | 1 | 5 | 2 | 8 | 1 | 5 | 2 | 8 | 100.00 | 0 | All critical NC comply through NDT Test and rest NC rectify But critical NC under observation till testing & commissioning of OHT (ZN-Al) | ||
43 |
Ballia |
Larsen & Toubro Ltd | 408 | 770 | 10 | 1188 | 394 | 657 | 8 | 1059 | 89.14 | 0 | 1 Proper finishing not found of OHT Stair .Curing not properly done 2. Trench has been found open in pakkakote, After pipe laying work compaction must be done in layer wise using compactor. |
Eagle Infra- Sudhakara Infra JV | 253 | 641 | 10 | 904 | 249 | 557 | 8 | 814 | 90.04 | 0 | Trench has been found open in pakkakote,After pipe laying work compaction must be done in layer wise using compactor. | ||
GAJA - GAIPL JV | 218 | 1338 | 0 | 1556 | 195 | 1203 | 0 | 1398 | 89.85 | 0 | 1- Compaction not done after backfilling .pipe laying work is completed, trench is backfilled haphazardly without any proper layering , watering and Compaction which is not as per clause no-8.1.2 of Indian Standard 7634:2012 (part-2) 2. Depth of the trench observed is 470mm at the top of the 63mm HDPE Pipe whereas as per DPR the Depth should be at least 1000mm+ of pipe | ||
44 |
Mau |
LC INFRA | 738 | 5179 | 149 | 6066 | 595 | 2345 | 108 | 3048 | 50.25 | 0 | 1.) Severe cracks were observed in the boundary wall due to lack of curing work 2.)Multiple lapping is provided at a single section of the beam/raft which could reduce the strength of structure at those locations. |
GA INFRA-VPL | 429 | 4328 | 17 | 4774 | 221 | 2384 | 14 | 2619 | 54.86 | 0 | 1.)End cap found open due to which insects are entering through the inlet of the pipe, it may cause various diseases in supplied water. 2.)Soil compaction of trenches after pipe laying is not being done layer-wise which could cause major accidents. | ||
KLSR - RAYS (JV) | 75 | 1792 | 16 | 1883 | 56 | 690 | 2 | 748 | 39.72 | 0 | 1.) Open trench was found, after laying HDPE pipe soil back filling was not done it's more than 3days; which may cause accidents. 2.) Dent was found over the screen pipe which may leads to collapse of assembly system. | ||
45 |
Ayodhya |
Vindhya-GAJA (JV) | 5 | 15 | 7 | 27 | 4 | 10 | 5 | 19 | 70.37 | 0 | |
Gayatri Projects LTD | 3 | 14 | 4 | 21 | 3 | 10 | 4 | 17 | 80.95 | 0 | |||
UNIVERSAL MEP | 2 | 24 | 9 | 35 | 2 | 24 | 9 | 35 | 100.00 | 0 | |||
VSA | 27 | 36 | 17 | 80 | 6 | 17 | 9 | 32 | 40.00 | 0 | |||
46 |
Sultanpur |
Gayatri Projects LTD | 17 | 16 | 16 | 49 | 7 | 9 | 14 | 30 | 61.22 | 0 | |
UNIVERSAL MEP | 13 | 11 | 13 | 37 | 11 | 10 | 13 | 34 | 91.89 | 0 | |||
Vindhya-GAJA (JV) | 67 | 124 | 129 | 320 | 46 | 41 | 57 | 144 | 45.00 | 0 | |||
47 |
Gorakhpur |
NCC Ltd. | 941 | 14222 | 571 | 15734 | 702 | 10340 | 498 | 11540 | 73.34 | 2627 | 1. Coping of boundary wall has been found damaged. 2.Cracks was found in the OHT Apron. 3. Solar Panel has been found damage. 4.MDPE pipe has been found exposed to surface. 5. Cracks was found in Staff Quarter wall. 6. Cracks has been observed in the Pump house plinth protection. |
Rithwik-Koya (JV) | 343 | 5128 | 160 | 5631 | 258 | 4262 | 111 | 4631 | 82.24 | 320 | 1.Cracks was found in the Pump House wall. 2. Cracks has been observed in the boundary wall. 3. MDPE pipe has been found exposed to surface. 4. Settlement has been observed in the DG foundation or slab. 5. Honeycombing has been observed between the brace beam and the OHT column. | ||
48 |
Deoria |
LC INFRA | 1053 | 7454 | 54 | 8561 | 718 | 4996 | 37 | 5751 | 67.18 | 1948 | 1.-Crack observed in boundary wall coping.2.-Cracked has been observed in boundary wall.3.-Honeycomb observed in pump house slab.4.Reinforcement found in exposed condition of pump house lintel chajja. |
Gayatri Projects LTD | 979 | 6788 | 25 | 7792 | 453 | 2736 | 13 | 3202 | 41.09 | 1287 | 1.-Crack has been observed on plinth protection of pump house.2.-Crack has been observed on Wall of pump house.3.-Crack has been observed on the boundary wall.4.Honeycomb has been observed on bottom portion of 1st brace beam of OHT. | ||
Rithwik-Koya (JV) | 201 | 1978 | 14 | 2193 | 155 | 1329 | 9 | 1493 | 68.08 | 101 | 1.-Crack has been observed on plinth protection of pump house.2.-Crack has been observed on Wall of pump house.3.-Crack has been observed on the boundary wall.4.Honeycomb has been observed on bottom portion of 1st brace beam of OHT. | ||
UNIVERSAL MEP | 178 | 969 | 6 | 1153 | 146 | 751 | 4 | 901 | 78.14 | 30 | 1.Crack has been observed in the Pump house plinth protection.2.A thrust block has not been constructed beneath the DI pipe installation. 3.Cover block not used properly in Beam. 4. Cracks has been observed in the boundary wall. | ||
49 |
Kushi Nagar |
NCC Ltd. | 2682 | 17125 | 170 | 19977 | 2693 | 16830 | 103 | 19626 | 98.24 | 621 | 1 .A vertical crack is observed on the corner joint of the boundary wall. 2. Crack has been observed in the boundary wall coping. 3. Interlocking pavement below solar panel has not constructed. |
50 |
Maharajganj |
JMC - Lakshmi (JV) | 612 | 6827 | 10 | 7449 | 534 | 5499 | 10 | 6043 | 81.12 | 486 | 1. Thickness of mortar is more than 10mm in pump house brick work. 2.Pea gravel not fill tube well chamber. 3. columns & tie Beam junction finishing has not done Properly. 4. Honeycomb has found at OHT columns Juction. 5. Crack observed in Boundary wall. |
Rithwik-Koya (JV) | 401 | 3361 | 7 | 3769 | 244 | 2254 | 3 | 2501 | 66.36 | 0 | 1. Crack has been observed in boundary wall. 2. Crack has been observed in boundary wall coping. 3. OHT column and tie beam Junction is not Properly casted due to improper shuttering. 4.Steel are visible in pump house lintel beam. 5. Pump House lintel beam found in broken condition. | ||
51 |
Varanasi |
Larsen & Toubro Ltd | 3486 | 24608 | 1155 | 29249 | 3106 | 21670 | 1042 | 25818 | 88.27 | 941 | "1-Cracks observed in Boundary wall. 2-Ganga sand used at site. 3-Joints of brickwork are not filled properly 4-Width of trench found 230mm which is not as per IS code 4984:2016.It should be 600+ dia of pipe as per DPR. 5-Mortar used for the Brick work was not as per DPR and specifications. 6-Curing of the brick work was not properly done.It may result in low hydration of cement and reduce the bo |
52 |
Jaunpur |
Welspun Kaveri Infraprojects JV | 1956 | 5551 | 174 | 7681 | 1821 | 4886 | 158 | 6865 | 89.38 | 543 | Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow and Road restoration work slow |
AFCONS | 2713 | 5212 | 172 | 8097 | 2444 | 4824 | 140 | 7408 | 91.49 | 636 | Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow | ||
53 |
Ghazipur |
HFCL- JWIL (JV) | 1735 | 3995 | 100 | 5830 | 1502 | 2919 | 91 | 4512 | 77.39 | 0 | "1-Width of the trench observed is 200mm at the top of the trench whereas as per DPR the width should be at least 600mm+ of pipe. 2-Quality of sand, 10mm, 20mm Aggregate not satisfactory 3- 75mm HDPE Pipe found laid in damage condition. 4-Depth of the trench is found 600mm at the top of the 63mm HDPE Pipe , whereas as per DPR the Depth should be at least 1000mm+ Dia of pipe. 5-MDPE pipe (20mm) f |
Larsen & Toubro Ltd | 2937 | 5462 | 248 | 8647 | 1599 | 2374 | 108 | 4081 | 47.20 | 169 | "1-The DPC layer of boundary wall is damaged 2- Honeycombing is found on the coping of the boundary wall 3- Honeycombing is found on the roof of the pump house." | ||
VSA | 3239 | 5985 | 69 | 9293 | 1640 | 1669 | 17 | 3326 | 35.79 | 140 | "1-Rusted steel used in ground beam work 2-Honeycombing is found in the Ring/Tie beam , Columns of the OHT. 3-Rusted bars are using in the construction of OHT foundation. 4-Cracks are found in the slab of the pump house. 5-Cracks are found in the boundary wall." | ||
54 |
Chandauli |
GA INFRA - BABA (JV) | 258 | 3442 | 78 | 3778 | 252 | 3366 | 72 | 3690 | 97.67 | 184 | "1-Hand concrete mixer is being used for concrete mixing instead of weightbatch concrete mixer. 2-Dirty water used for mixing of concreting, which is against clause 4.6 of IS;2250 3-Honeycomb observed in Pump house ( Chajja) 4-Rusted reinforcement use in pump house slab 5-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new brick for re |
HFCL- JWIL (JV) | 168 | 1409 | 23 | 1600 | 159 | 1358 | 21 | 1538 | 96.13 | 0 | "1-Hand concrete mixer used for concrete mixing Instead of PLC based weighbatch concrete mixer. 2-Depth found 800mm found for 63mm dia HDPE Pipe laying as per DPR it should be 1000mm+Dia 3-Second class bricks are available at site , whereas per the DPR 1st class bricks should be used. 4-Curing of concrete of boundary wall coping casting work not done after de-shuttering . 5-MDPE pipe found above | ||
ION EXCHANGE | 669 | 5678 | 78 | 6425 | 635 | 5638 | 71 | 6344 | 98.74 | 211 | "1-10mm,20mm aggregate found failed during sieve analasys test 2-Depth of 140mm dia HDPE Pipe found 570mm whereas as per the DPR ,pipe should be laid at least 1.0m+Dia 3-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new Brick should be used for restoration work 4-Hand concrete mixer used for concrete mixing Instead of PLC based weigh | ||
VSA | 10129 | 6243 | 255 | 16627 | 10118 | 6197 | 251 | 16566 | 99.63 | 307 | "1-Grouting of GI pipe not done 2-MDPE pipe found above GL level ( open condition) 3-100 percent old brick use for BOE road restoration work, As per DPR it should be 50 percent old and 50 percent new brick for BOE road restoration work 4-Depth of 63mm dia HDPE Pipe found 700mm, whereas as per the DPR depth should be 1m+dia 5-Reinstatement not done from last one month. Restoration work is being pen | ||
East India Udhyog- Kaveri JV | 17 | 390 | 1 | 408 | 16 | 353 | 1 | 370 | 90.69 | 0 | Laying Of Hdpe Pipe Is Not Done Properly At Some Places Depth Is Found 600 -700mm. | ||
55 |
Auraiya |
Indian Hume Pipe | 10 | 12 | 3 | 25 | 10 | 10 | 3 | 23 | 92.00 | 0 | |
GVPR | 70 | 25 | 6 | 101 | 67 | 21 | 6 | 94 | 93.07 | 0 | |||
56 |
Prayagraj |
Larsen & Toubro Ltd | 2259 | 13216 | 432 | 15907 | 1570 | 11573 | 365 | 13508 | 84.92 | 0 | Grouting base of GI pipe has been given above the ground level. Whereas it should be under the ground at 300 mm depth to support GI pipe properly. This type issues has been observed in the some connections. |
VPRPL | 299 | 630 | 11 | 940 | 260 | 526 | 8 | 794 | 84.47 | 0 | Depth of trench of DI pipe has been found 400 mm from the crown of pipe instead of 1000 mm. | ||
GAJA - GAIPL JV | 478 | 577 | 3 | 1058 | 423 | 502 | 2 | 927 | 87.62 | 0 | HDPE pipe has been crossed the culvert without encasing the pipe. | ||
57 |
Kaushambi |
GA INFRA - BABA (JV) | 735 | 4257 | 289 | 5281 | 268 | 2123 | 190 | 2581 | 48.87 | 0 | No cut out has been made at the slab of the oht for inlet and outlet pipe. As hammering in slab should be avoided to counter strength reduction. |
JMC - Lakshmi (JV) | 569 | 3086 | 191 | 3846 | 389 | 2418 | 153 | 2960 | 76.96 | 0 | Honeycomb has been observed at the outer face of conical wall . poor work was done for the construction of conical wall. | ||
58 |
Fatehpur |
Gayatri Projects LTD | 324 | 6640 | 279 | 7243 | 125 | 2161 | 68 | 2354 | 32.50 | 0 | NIL |
GA INFRA - BABA (JV) | 157 | 943 | 17 | 1117 | 86 | 406 | 3 | 495 | 44.32 | 0 | NIL | ||
Power Mech Projects Ltd | 821 | 4971 | 161 | 5953 | 339 | 1882 | 39 | 2260 | 37.96 | 0 | NIL | ||
59 |
Pratapgarh |
JMC - Lakshmi (JV) | 846 | 3803 | 174 | 4823 | 581 | 3158 | 155 | 3894 | 80.74 | 0 | Water logging has been occurred around the pump house. Crack has been developed in the boundary wall. |
Power Mech Projects Ltd | 1409 | 3323 | 42 | 4774 | 1175 | 2914 | 8 | 4097 | 85.82 | 0 | Clamp has not been used to support DI pipes of OHT. Water logging has been occurred at the ground level of OHT. Due to this bamboo scaffolding may get settled and consequently members may got damaged/collapsed. | ||
60 |
Gonda |
KLSR - RAYS (JV) | 15 | 53 | 35 | 103 | 10 | 25 | 18 | 53 | 51.46 | 0 | Column misalignment, cube Test Failure, Honeycombing on structure, Road restoration, poor Quality material |
Larsen & Toubro Ltd | 17 | 39 | 25 | 81 | 10 | 27 | 13 | 50 | 61.73 | 0 | Road restoration work, Poor Quality material, Zinc Tank leakage, | ||
61 |
Saharanpur |
GA INFRA - BABA (JV) | 88 | 223 | 18 | 329 | 60 | 98 | 2 | 160 | 48.63 | 0 | Poor Quality work OHT 3rd brace beam & column not plumb. Without complete staircase work & plumb of brace beam Inappropriate size of staircase Poor Quality work OHT column found honeycomb |
NKG-PRIMUS (JV) | 9 | 116 | 6 | 131 | 6 | 72 | 3 | 81 | 61.83 | 0 | Poor quality construction work pump house. CC road reinstatement poor workmanship. | ||
Gayatri Projects LTD | 10 | 110 | 2 | 122 | 5 | 19 | 0 | 24 | 19.67 | 0 | Poor quality construction work pump house. CC road reinstatement poor workmanship. | ||
62 |
Firozabad |
Larsen & Toubro Ltd | 5 | 242 | 7 | 254 | 5 | 147 | 7 | 159 | 62.60 | 0 | |
NCC Ltd. | 0 | 131 | 1 | 132 | 0 | 121 | 1 | 122 | 92.42 | 0 | |||
63 |
Bareilly |
NCC Ltd. | 36 | 60 | 36 | 132 | 34 | 58 | 36 | 128 | 96.97 | 0 | Regarding Deviation from Approved Design/Drawing in the construction of OHT staircase and MDPE pipe intended for FHTCs have been laid through an existing waste water drain |
64 |
Amethi |
Vindhya-GAJA (JV) | 18 | 33 | 26 | 77 | 16 | 20 | 13 | 49 | 63.64 | 0 | Size of Riser tread of staircase not found as per specifications. Landing beam bars are curtailed. |
Gayatri Projects LTD | 12 | 26 | 24 | 62 | 10 | 10 | 6 | 26 | 41.94 | 0 | Regarding Honey combing and UPV test. | ||
Welspun Kaveri Infraprojects JV | 9 | 13 | 19 | 41 | 9 | 10 | 16 | 35 | 85.37 | 0 | |||
65 |
Bulandshahr |
JMC - Lakshmi (JV) | 1 | 59 | 2 | 62 | 1 | 57 | 2 | 60 | 96.77 | 0 | |
Welspun Kaveri Infraprojects JV | 0 | 24 | 0 | 24 | 0 | 24 | 0 | 24 | 100.00 | 0 | |||
Power Mech Projects Ltd | 2 | 10 | 1 | 13 | 2 | 10 | 1 | 13 | 100.00 | 0 | |||
66 |
Ambedkar Nagar |
Welspun Kaveri Infraprojects JV | 11 | 29 | 2 | 42 | 9 | 5 | 2 | 16 | 38.10 | 0 | |
Vindhya-GAJA (JV) | 56 | 126 | 3 | 185 | 52 | 58 | 2 | 112 | 60.54 | 0 | |||
67 |
Sant Kabeer Nagar |
Megha | 24 | 66 | 62 | 152 | 7 | 20 | 21 | 48 | 31.58 | 0 | 1. It was found that at site there are large gap between precast columns & at beam of OHT. Whereas gap should be 25mm as per approved OHT drawing As per IS 15916-2011 ±10% tolerance allowed in precast components. Honeycomb found in concrete due to failure of the mortar to effectively fill the spaces among coarse aggregate particles .Column dowel bars found 450 mm instead of 500 mm |
JAKSON - VISHVARAJ (JV) | 22 | 71 | 58 | 151 | 18 | 23 | 10 | 51 | 33.77 | 0 | Coarse aggregate is over size whereas for construction activity Coarse aggregate (20 mm) should be As per IS 383 Table 2 .Lapping in TB2 beam is not done as per specification whereas it should be 49D in M-25 Grade of concrete as per approved drawing. Not proper finishing work of OHT column and brace , patching found at many places . Column not in an alignment. At joints of column and brace lots o | ||
68 |
Basti |
JAKSON - VISHVARAJ (JV) | 5 | 29 | 21 | 55 | 4 | 20 | 15 | 39 | 70.91 | 0 | |
Megha | 123 | 155 | 182 | 460 | 88 | 86 | 112 | 286 | 62.17 | 0 | |||
VSA | 4 | 11 | 14 | 29 | 4 | 9 | 12 | 25 | 86.21 | 0 | |||
69 |
Agra |
NCC-APCO JV | 49 | 24 | 6 | 79 | 42 | 20 | 6 | 68 | 86.08 | 0 | |
Megha | 130 | 30 | 2 | 162 | 87 | 18 | 1 | 106 | 65.43 | 0 | |||
70 |
Aligarh |
ION EXCHANGE | 11 | 51 | 14 | 76 | 11 | 43 | 13 | 67 | 88.16 | 0 | |
JMC - Lakshmi (JV) | 11 | 83 | 1 | 95 | 10 | 70 | 1 | 81 | 85.26 | 0 | |||
PNC-SPML-JV | 15 | 114 | 9 | 138 | 13 | 94 | 7 | 114 | 82.61 | 0 | |||
71 |
Mathura |
NCC-APCO JV | 6 | 101 | 6 | 113 | 4 | 67 | 3 | 74 | 65.49 | 0 | |
72 |
Sant Ravidas Nagar |
Welspun Kaveri Infraprojects JV | 1089 | 2531 | 149 | 3769 | 770 | 1899 | 139 | 2808 | 74.50 | 87 | 1. Washer and lock nut not provided in solar foundation. 2. Crack has been found in pump house wall. 3. Staircase thread & riser size is not found ok. 4. Staircase 1st landing slab size & level not found properly. 5. ESR work has been stopped for almost 5 months. 6. There is a lot of rust in the reinforcement used in ESR, due to which the upper layer of the steel is slowly getting destroyed. |
GA INFRA - BABA (JV) | 980 | 1882 | 166 | 3028 | 531 | 1442 | 153 | 2126 | 70.21 | 36 | 1. The cement placed in rampur ESR location has completely set. 2. The soil of the foundation of the boundary wall of Rampur ESR has been washed away by rain, due to which the boundary wall can collapse any time. 3. Crack has been found in boundary wall at many places. 4. Boundary wall plumb & alignment is not found properly. 5. Honeycombing has been found in ESR column and beam at many places. 6 | ||
73 |
Mainpuri |
NCC Ltd. | 15 | 49 | 18 | 82 | 48 | 16 | 76 | 140 | 170.73 | 0 | |
74 |
Baghpat |
LC INFRA | 0 | 0 | 0 | 0 | 0 | 0 | 4 | 4 | 400.00 | 0 |