| S.No. |
District
|
TKC | Total NCs reported | Complainces Submitted By TKCs | % Of Compliance Submitted | No. of bills processed without compliances (J) |
Remarks(Only Critical in few words) |
||||||
| Critical (A) |
Major (B) |
Minor (C ) |
Total D = A+B+C |
Critical (E ) |
Major (F) |
Minor (G) |
Total H=E+F+G |
I = H*100/D | |||||
| Total | 51374 | 242590 | 15170 | 309134 | 40332 | 187431 | 11970 | 239733 | 77.55 | 10846 | |||
| 1 |
Jalaun |
BGCCPL-Ramky (JV) | 118 | 80 | 32 | 230 | 47 | 27 | 12 | 86 | 37.39 | 17 | Revised drawings are still awaited for approval. Approved drawings are often not available at site of work. |
| GVPR | 40 | 40 | 16 | 96 | 29 | 26 | 12 | 67 | 69.79 | 18 | Revised drawings are still awaited for approval. Approved drawings are often not available at site of work. | ||
| 2 |
Shravasti |
Larsen & Toubro Ltd | 13 | 18 | 13 | 44 | 11 | 15 | 13 | 39 | 88.64 | 0 | 1) Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. Many schemes HDPE Pipe distribution line is found open without providing end caps. 2. Site Order Book , Approved drawings are not available at site premise during execution. 3. As build drawing not submitted to UPJN and TPI. |
| GA INFRA-VPL | 0 | 33 | 0 | 33 | 0 | 12 | 0 | 12 | 36.36 | 0 | Cube fail -2 / Honeycomb -3 / Water logged -1 / Steel cut upto GL -1 / Steel rusted -5 | ||
| 3 |
Bahraich |
GA INFRA-VPL | 9 | 14 | 8 | 31 | 5 | 12 | 8 | 25 | 80.65 | 0 | HDD Method is not implementing in possible site locations 2. Lack of proper road restoration works. 3. Lack of manpower, physical work progress is very slow. 4. As build drawing not submitted to UPJN office and to TPI also. |
| PNC-SPML-JV | 44 | 76 | 18 | 138 | 44 | 70 | 16 | 130 | 94.20 | 0 | 1. Piling work is being done without approval of Methodology . 2. As build drawing not submitted to UPJN and TPI also | ||
| 4 |
Balrampur |
Larsen & Toubro Ltd | 13 | 30 | 32 | 75 | 10 | 27 | 30 | 67 | 89.33 | 0 | Drinking Water is supplied without performing disinfection of distribution line, hydraulic structure. 2) Pump house finishing work is not proper. 3) Lot of road restoration work is pending from the agency and quality of road restoration is not as per standard. 4. As build drawing not submitted to UPJN and TPI. |
| Dara- Eco Protection (JV) | 14 | 25 | 22 | 61 | 11 | 22 | 21 | 54 | 88.52 | 0 | Plywood doors have been installed in 17 Gram Panchayats. 2) HDD Method is not implementing in possible site locations. 3. Hydrotesting, disinfection, and flushing of the pipeline not done before water supply. 4. As build drawing not submitted to UPJN and TPI. | ||
| 5 |
Lucknow |
NCC Ltd. | 202 | 1679 | 553 | 2434 | 88 | 820 | 553 | 1461 | 60.02 | 0 | |
| 6 |
Hardoi |
NCC Ltd. | 1329 | 1616 | 1313 | 4258 | 996 | 1279 | 1165 | 3440 | 80.79 | 0 | 1)Major cracks seen on boundary wall. 2)Pea gravel not stacked properly at site. 3)FHTC installed outside the house. 3) Disinfection of pipe not done 4) Lifting appliances, lifting gears and Compressor was not inspected by competent agency 5) Test certificate scaffolding material not submitted.6) Nonstandard scaffolding used at site.7) Non-standard DG used at site.7) Quality issues during OHT work |
| 7 |
Hathras |
BGCCPL-Ramky (JV) | 28 | 67 | 152 | 247 | 10 | 21 | 81 | 112 | 45.34 | 0 | Quality of material ( sand , Brick & aggregate ) Not as per standard specification |
| ION EXCHANGE | 11 | 21 | 14 | 46 | 8 | 17 | 8 | 33 | 71.74 | 0 | Work done without RFI & Reinstatement work not as per standard specification | ||
| 8 |
Rampur |
LC INFRA | 1 | 4 | 0 | 5 | 0 | 0 | 0 | 0 | 0.00 | 0 | Brick Quality is not good 2.Poor workmanship3.Caution Tape not used 4.Safety belt not used 5.PPE kit not used. |
| NKG-PRIMUS (JV) | 11 | 22 | 4 | 37 | 9 | 13 | 0 | 22 | 59.46 | 0 | OHT construction,cube testing failure,CC road restoration ,Done work without raised RFI | ||
| SPML Infra | 16 | 28 | 8 | 52 | 10 | 17 | 3 | 30 | 57.69 | 0 | RFI was Not raised.2.Staging done without stair case 3Road restoration not done properly 4.Safety belt not used 5.PPE kit not used.6.Safety net not used. | ||
| OMIL-JWIL (JV) | 16 | 27 | 2 | 45 | 13 | 19 | 2 | 34 | 75.56 | 0 | RFI was not raised. 2.Quality of material not as per specification.3.Safety norms not followed, approved drawing not at site. | ||
| 9 |
Meerut |
Power Mech Projects Ltd | 3 | 32 | 1 | 36 | 3 | 32 | 1 | 36 | 100.00 | 0 | |
| 10 |
Raebareli |
NCC Ltd. | 47 | 428 | 78 | 553 | 44 | 428 | 78 | 550 | 99.46 | 0 | Honey combing found in OHT, Leakage observed in OHT |
| Vindhya-GAJA (JV) | 36 | 211 | 20 | 267 | 26 | 195 | 20 | 241 | 90.26 | 0 | Poor quality of workmanship in OHT work, Leakage found in pipeline, Honey combing found in OHT. | ||
| 11 |
Etawah |
Indian Hume Pipe | 24 | 42 | 20 | 86 | 24 | 42 | 20 | 86 | 100.00 | 0 | All NC had been raised for OHT, Tubewell, Building, Safety and other issues. All work has been rectified by the agency and compliance has been provided by letter or mail. |
| OMIL-JWIL (JV) | 38 | 17 | 4 | 59 | 28 | 17 | 4 | 49 | 83.05 | 0 | 1. NC raised for column beam misalignment, Spalling of concrete. 2. Fixing of anchor bolt is not proper. 02 Nos. sheet has been used to fulfill the requirement of 1.6 mm thick ring in Zn Al tank without proper butt fusion welding. Slab surface finishing is also not proper dur to which a gap has been occurred between the slab and tank sheet. | ||
| 12 |
Hamirpur |
PNC-SPML-JV | 6 | 4 | 68 | 78 | 6 | 4 | 68 | 78 | 100.00 | 0 | |
| JWIL | 5 | 4 | 86 | 95 | 5 | 4 | 86 | 95 | 100.00 | 0 | |||
| 13 |
Mahoba |
JMC-JWIL (JV) | 13 | 27 | 24 | 64 | 13 | 27 | 24 | 64 | 100.00 | 0 | |
| N.K. Gupta & K.B. Gupta Contractors | 6 | 10 | 8 | 24 | 6 | 10 | 8 | 24 | 100.00 | 0 | |||
| Larsen & Toubro Ltd | 6 | 14 | 12 | 32 | 6 | 14 | 12 | 32 | 100.00 | 0 | |||
| SLC-SMC (JV) | 7 | 16 | 12 | 35 | 7 | 15 | 12 | 34 | 97.14 | 0 | |||
| 14 |
Sitapur |
NCC Ltd. | 317 | 0 | 0 | 317 | 18 | 0 | 0 | 18 | 5.68 | 0 | |
| Larsen & Toubro Ltd | 0 | 46 | 110 | 156 | 0 | 24 | 60 | 84 | 53.85 | 0 | |||
| 15 |
Kasganj |
ION EXCHANGE | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0.00 | 0 | |
| PNC-SPML-JV | 52 | 165 | 91 | 308 | 45 | 131 | 78 | 254 | 82.47 | 0 | |||
| 16 |
Bijnor |
Vindhya-GAJA (JV) | 23 | 6 | 19 | 48 | 22 | 4 | 15 | 41 | 85.42 | 0 | un approved steel and cement,column alignment not in plumb,major honeycombs. |
| LC INFRA | 7 | 3 | 4 | 14 | 7 | 2 | 4 | 13 | 92.86 | 0 | column alignment not in plumb,major honeycombs,brace beam shuttering found bulge. | ||
| 17 |
Lalitpur |
DARA ENGINEERING | 45 | 79 | 348 | 472 | 45 | 79 | 302 | 426 | 90.25 | 0 | |
| JMC-JWIL (JV) | 48 | 66 | 413 | 527 | 48 | 66 | 344 | 458 | 86.91 | 0 | |||
| Brija Banco Pvt. Ltd | 10 | 18 | 52 | 80 | 10 | 18 | 31 | 59 | 73.75 | 0 | |||
| Banko Ganga | 5 | 10 | 85 | 100 | 5 | 10 | 74 | 89 | 89.00 | 0 | |||
| M/s Sudhakara Infratech Pvt. Ltd | 67 | 55 | 829 | 951 | 67 | 55 | 741 | 863 | 90.75 | 0 | |||
| 18 |
Lakhimpur Kheri |
NCC Ltd. | 45 | 467 | 230 | 742 | 36 | 397 | 198 | 631 | 85.04 | 0 | 1- Hydrotest disinfection and flushing of pipe line not done before Supply of water. 2- Road restoration work not done as per original specification. 3- Water tightness test of OHT is not done as per IS specification 10500. |
| Vindhya-GAJA (JV) | 39 | 311 | 131 | 481 | 35 | 255 | 102 | 392 | 81.50 | 0 | 1-Weigh Batcher not used for Design Mix Concreting of OHT. 2- End Cap of the HDPE pipeline not installed after completion of day work. 3- Electrical hazard safety sign board to be display at site. | ||
| 19 |
Jhansi |
NCC Ltd. | 26 | 93 | 295 | 414 | 26 | 93 | 269 | 388 | 93.72 | 0 | |
| Indian Hume Pipe | 16 | 40 | 65 | 121 | 16 | 40 | 56 | 112 | 92.56 | 0 | |||
| DARA ENGINEERING | 19 | 31 | 62 | 112 | 19 | 31 | 58 | 108 | 96.43 | 0 | |||
| Unipro | 20 | 28 | 50 | 98 | 20 | 28 | 48 | 96 | 97.96 | 0 | |||
| BGCCPL-Ramky (JV) | 29 | 140 | 303 | 472 | 29 | 102 | 196 | 327 | 69.28 | 0 | |||
| 20 |
Hapur |
LC INFRA | 4 | 4 | 19 | 27 | 3 | 2 | 0 | 5 | 18.52 | 0 | |
| 21 |
Sambhal |
LC INFRA | 1 | 2 | 4 | 7 | 1 | 1 | 0 | 2 | 28.57 | 0 | |
| NKG-PRIMUS (JV) | 15 | 30 | 38 | 83 | 12 | 11 | 13 | 36 | 43.37 | 0 | Zinc-Alum tank, Location and position of nut bolt is not as per specification, Tampering of bolt, gap in zinc laum sheet and OHT slab is seen.honey comb,steel exposer. | ||
| SPML Infra | 20 | 30 | 35 | 85 | 16 | 10 | 15 | 41 | 48.24 | 0 | Zinc-Alum tank,Location and position of nut bolt is not as per specification,Tampering of bolt, gap in zinc laum sheet and OHT slab is seen.Column beam misalignment. Honey comb | ||
| 22 |
Etah |
ION EXCHANGE | 0 | 4 | 0 | 4 | 0 | 3 | 0 | 3 | 75.00 | 0 | |
| Power Mech Projects Ltd | 12 | 78 | 95 | 185 | 12 | 47 | 65 | 124 | 67.03 | 0 | |||
| JMC - Lakshmi (JV) | 4 | 25 | 26 | 55 | 3 | 16 | 18 | 37 | 67.27 | 0 | |||
| 23 |
Chitrakoot |
GVPR | 5 | 5 | 27 | 37 | 4 | 1 | 15 | 20 | 54.05 | 0 | |
| Larsen & Toubro Ltd | 9 | 31 | 109 | 149 | 9 | 16 | 104 | 129 | 86.58 | 0 | |||
| 24 |
Mirzapur |
NCC Ltd. | 374 | 3127 | 270 | 3771 | 374 | 3127 | 270 | 3771 | 100.00 | 62 | - |
| Megha | 707 | 2703 | 81 | 3491 | 448 | 2118 | 72 | 2638 | 75.57 | 49 | Many Leakage/seepage points have been observed in the CWR tank. | ||
| GA INFRA | 963 | 3192 | 125 | 4280 | 963 | 3192 | 125 | 4280 | 100.00 | 25 | - | ||
| GVPR | 172 | 1350 | 49 | 1571 | 67 | 560 | 26 | 653 | 41.57 | 20 | 1- Leakage/seepage found in ESR bottom dome. 2 -The level of the stairs does not seem to be correct, the stairs appear to be tilted to one side. | ||
| Ramky baba | 423 | 2037 | 153 | 2613 | 38 | 213 | 25 | 276 | 10.56 | 32 | 1 - Significant water stagnation observed around the RCC pedestal of the OHT 2 - The adjacent soil appears soft ,damp, and partially eroded. 3- Signs of algae formation and water logging persist despite multiple site visits | ||
| Multiurban | 50 | 263 | 10 | 323 | 50 | 263 | 10 | 323 | 100.00 | 19 | - | ||
| 25 |
Sonbhadra |
Jain Const. | 9 | 176 | 14 | 199 | 9 | 176 | 14 | 199 | 100.00 | 18 | - |
| Larsen & Toubro Ltd | 47 | 1794 | 60 | 1901 | 47 | 1439 | 43 | 1529 | 80.43 | 76 | 1. Pipe joint is leakage from more than 4 months. 2. Flange is welded with pipe which is not acceptable at any cost. | ||
| GVPR | 119 | 1233 | 34 | 1386 | 119 | 1023 | 23 | 1165 | 84.05 | 26 | 1. Pipe were not laid as per required Depth and left open. 2. Pipe laid directly on the surface. | ||
| VPRPL | 165 | 2357 | 76 | 2598 | 165 | 2284 | 55 | 2504 | 96.38 | 81 | After completion of pipe laying work BT road dismantled but it has not been restored. | ||
| NCC Ltd. | 106 | 1794 | 21 | 1921 | 106 | 1624 | 17 | 1747 | 90.94 | 20 | 1.Waste slab thickness not found as per drawing specifications. 2. Rise and trade not found as per drawing specifications. | ||
| 26 |
Azamgarh |
ECO PROTECTION ENGINEER | 181 | 396 | 3 | 580 | 166 | 374 | 0 | 540 | 93.10 | 0 | The depth of the trench was found 700 mm at many locations whereas as per IS standard it should be 1 meter+dia of pipe. |
| GA INFRA - BABA (JV) | 409 | 1354 | 53 | 1816 | 141 | 464 | 13 | 618 | 34.03 | 0 | 1.) Backfilling of trenches after pipe laying is not being done layer-wise which could cause major accidents. 2.)The dia of the reinforcement bar was used 6 mm instead of 8mm in pump house slab beam. 3.)Material testing are not being done as per the norms due to which inadequate materials are used at site and could cause major failure of structure. | ||
| GAJA - SGIPL (JV) | 221 | 1098 | 23 | 1342 | 140 | 790 | 5 | 935 | 69.67 | 0 | 1.) The oversized gravel was used at site for raft foundation. 2.) The spacing of the Shear stirrups were not provided properly In column and Brace Beam. | ||
| LC INFRA | 1725 | 6158 | 276 | 8159 | 1608 | 4978 | 192 | 6778 | 83.07 | 0 | 1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.) Construction materials such as cement, sand, aggregate, bricks and shuttering materials were not found of satisfactory quality and standards. 3) honeycomb was observed in major area of the raft foundation. | ||
| SIEPL – BRCCPL (JV) / SKYLARK | 221 | 527 | 84 | 832 | 93 | 228 | 15 | 336 | 40.38 | 0 | Proper layer wise compaction is not being performed which causes depression on road, resulting accidents | ||
| M/s Sudhakara Infratech Pvt. Ltd | 1635 | 4658 | 115 | 6408 | 1175 | 3239 | 41 | 4455 | 69.52 | 0 | 1.) Bricks are not being used as the approved BOQ i.e of 1st class for boundary wall, pump house & staff quarter works. 2.)Rusted steel bars were used for slab and OHT work which Is not as per IS specification's. | ||
| VIKRAN-VPRPL (JV) | 380 | 863 | 120 | 1363 | 288 | 412 | 35 | 735 | 53.93 | 0 | Curing is not being done properly hence structure is not able to achieve its optimum strength. | ||
| 27 |
Ballia |
Eagle Infra- Sudhakara Infra JV | 253 | 641 | 10 | 904 | 249 | 557 | 8 | 814 | 90.04 | 0 | Trench has been found open in pakkakote,After pipe laying work compaction must be done in layer wise using compactor. |
| GAJA - GAIPL JV | 218 | 1338 | 0 | 1556 | 195 | 1203 | 0 | 1398 | 89.85 | 0 | 1- Compaction not done after backfilling .pipe laying work is completed, trench is backfilled haphazardly without any proper layering , watering and Compaction which is not as per clause no-8.1.2 of Indian Standard 7634:2012 (part-2) 2. Depth of the trench observed is 470mm at the top of the 63mm HDPE Pipe whereas as per DPR the Depth should be at least 1000mm+ of pipe | ||
| Larsen & Toubro Ltd | 408 | 770 | 10 | 1188 | 394 | 680 | 8 | 1082 | 91.08 | 0 | Proper finishing not found of OHT Stair .Curing not properly done 2. Trench has been found open in pakkakote, After pipe laying work compaction must be done in layer wise using compactor. | ||
| 28 |
Mau |
LC INFRA | 738 | 5179 | 149 | 6066 | 595 | 2345 | 108 | 3048 | 50.25 | 0 | 1.) Severe cracks were observed in the boundary wall due to lack of curing work 2.)Multiple lapping is provided at a single section of the beam/raft which could reduce the strength of structure at those locations. |
| GA INFRA-VPL | 429 | 4328 | 17 | 4774 | 221 | 2384 | 14 | 2619 | 54.86 | 0 | 1.)End cap found open due to which insects are entering through the inlet of the pipe, it may cause various diseases in supplied water. 2.)Soil compaction of trenches after pipe laying is not being done layer-wise which could cause major accidents. | ||
| KLSR - RAYS (JV) | 75 | 1792 | 16 | 1883 | 56 | 690 | 2 | 748 | 39.72 | 0 | 1.) Open trench was found, after laying HDPE pipe soil back filling was not done it's more than 3days; which may cause accidents. 2.) Dent was found over the screen pipe which may leads to collapse of assembly system. | ||
| 29 |
Amethi |
Vindhya-GAJA (JV) | 18 | 33 | 26 | 77 | 16 | 20 | 13 | 49 | 63.64 | 0 | Size of Riser tread of staircase not found as per specifications. Landing beam bars are curtailed. |
| Gayatri Projects LTD | 12 | 26 | 24 | 62 | 10 | 10 | 6 | 26 | 41.94 | 0 | Regarding Honey combing and UPV test. | ||
| Welspun Kaveri Infraprojects JV | 9 | 13 | 19 | 41 | 9 | 10 | 16 | 35 | 85.37 | 0 | |||
| 30 |
Bulandshahr |
Welspun Kaveri Infraprojects JV | 0 | 24 | 0 | 24 | 0 | 24 | 0 | 24 | 100.00 | 0 | |
| Power Mech Projects Ltd | 2 | 10 | 1 | 13 | 2 | 10 | 1 | 13 | 100.00 | 0 | |||
| JMC - Lakshmi (JV) | 1 | 59 | 2 | 62 | 1 | 59 | 2 | 62 | 100.00 | 0 | |||
| 31 |
Sant Ravidas Nagar |
Welspun Kaveri Infraprojects JV | 1089 | 2531 | 149 | 3769 | 770 | 1899 | 139 | 2808 | 74.50 | 87 | 1. Washer and lock nut not provided in solar foundation. 2. Crack has been found in pump house wall. 3. Staircase thread & riser size is not found ok. 4. Staircase 1st landing slab size & level not found properly. 5. ESR work has been stopped for almost 5 months. 6. There is a lot of rust in the reinforcement used in ESR, due to which the upper layer of the steel is slowly getting destroyed. |
| GA INFRA - BABA (JV) | 980 | 1882 | 166 | 3028 | 531 | 1442 | 153 | 2126 | 70.21 | 36 | 1. The cement placed in rampur ESR location has completely set. 2. The soil of the foundation of the boundary wall of Rampur ESR has been washed away by rain, due to which the boundary wall can collapse any time. 3. Crack has been found in boundary wall at many places. 4. Boundary wall plumb & alignment is not found properly. 5. Honeycombing has been found in ESR column and beam at many places. 6 | ||
| 32 |
Pilibhit |
VISHVARAJ | 11 | 16 | 49 | 76 | 11 | 16 | 49 | 76 | 100.00 | 0 | |
| PNC-SPML-JV | 27 | 30 | 60 | 117 | 24 | 30 | 60 | 114 | 97.44 | 0 | |||
| 33 |
Gautam Buddha Nagar |
LC INFRA | 0 | 9 | 7 | 16 | 0 | 8 | 4 | 12 | 75.00 | 0 | |
| 34 |
Muzaffarnagar |
Gayatri Projects LTD | 2 | 4 | 0 | 6 | 2 | 2 | 0 | 4 | 66.67 | 0 | |
| NKG-PRIMUS (JV) | 62 | 26 | 4 | 92 | 22 | 1 | 0 | 23 | 25.00 | 0 | |||
| JMC - Lakshmi (JV) | 151 | 108 | 15 | 274 | 80 | 28 | 0 | 108 | 39.42 | 0 | |||
| 35 |
Banda |
Larsen & Toubro Ltd | 9 | 9 | 67 | 85 | 9 | 9 | 67 | 85 | 100.00 | 0 | |
| NCC Ltd. | 9 | 11 | 29 | 49 | 9 | 11 | 29 | 49 | 100.00 | 0 | |||
| 36 |
Budaun |
NCC Ltd. | 3 | 4 | 2 | 9 | 3 | 4 | 2 | 9 | 100.00 | 0 | |
| PNC-SPML-JV | 75 | 149 | 8 | 232 | 74 | 125 | 8 | 207 | 89.22 | 0 | 1. 99 Nos compliance closed at site but not received officially in written. 2. Work done without RFI's. 3. Poor workmanship. | ||
| 37 |
Ambedkar Nagar |
Welspun Kaveri Infraprojects JV | 11 | 27 | 2 | 40 | 9 | 14 | 2 | 25 | 62.50 | 0 | |
| Vindhya-GAJA (JV) | 56 | 124 | 4 | 184 | 56 | 69 | 2 | 127 | 69.02 | 0 | |||
| 38 |
Sant Kabeer Nagar |
JAKSON - VISHVARAJ (JV) | 22 | 74 | 61 | 157 | 20 | 23 | 13 | 56 | 35.67 | 0 | Lapping in TB2 beam is not done as per specification whereas it should be 49D in M-25 Grade of concrete as per approved drawing. Alignment of beam is not as per drawing and design. |
| Megha | 26 | 82 | 54 | 162 | 10 | 24 | 22 | 56 | 34.57 | 0 | It was found at the site there is a large gap between the precast columns and the beam of OHT. Whereas gap should be 25 mm as per approved OHT Drawing. As per IS 15916 -2011, ±10 % tolerance allowed in precast components. Precast OHT Column dowel bars found 410 mm instead of 500 mm. Zinc Aluminum tank is corroded, Large gap between OHT slab and hold down bracket. | ||
| 39 |
Ghaziabad |
LC INFRA | 4 | 12 | 3 | 19 | 4 | 7 | 2 | 13 | 68.42 | 0 | |
| 40 |
Gonda |
KLSR - RAYS (JV) | 5 | 32 | 25 | 62 | 1 | 12 | 7 | 20 | 32.26 | 0 | Road Restoration, Safety issue, Material issue, Poor workmanship |
| Larsen & Toubro Ltd | 8 | 20 | 32 | 60 | 3 | 7 | 10 | 20 | 33.33 | 0 | Road Restoration , Poor workmanship, Regular water supply without chlorination, Ladder issue of OHT | ||
| 41 |
Shamli |
Gayatri Projects LTD | 2 | 4 | 2 | 8 | 1 | 0 | 0 | 1 | 12.50 | 0 | |
| JMC - Lakshmi (JV) | 54 | 70 | 9 | 133 | 26 | 12 | 6 | 44 | 33.08 | 0 | |||
| 42 |
Baghpat |
LC INFRA | 4 | 10 | 17 | 31 | 4 | 10 | 13 | 27 | 87.10 | 0 | |
| 43 |
Siddharth Nagar |
VSA | 29 | 85 | 7 | 121 | 16 | 12 | 1 | 29 | 23.97 | 0 | |
| Megha | 57 | 170 | 15 | 242 | 23 | 24 | 3 | 50 | 20.66 | 0 | |||
| JAKSON - VISHVARAJ (JV) | 70 | 274 | 14 | 358 | 41 | 70 | 8 | 119 | 33.24 | 0 | |||
| 44 |
Auraiya |
Indian Hume Pipe | 9 | 13 | 3 | 25 | 9 | 13 | 3 | 25 | 100.00 | 0 | |
| GVPR | 69 | 29 | 6 | 104 | 66 | 28 | 6 | 100 | 96.15 | 0 | |||
| 45 |
Barabanki |
Gayatri Projects LTD | 5 | 9 | 0 | 14 | 4 | 1 | 0 | 5 | 35.71 | 0 | |
| Megha | 72 | 53 | 2 | 127 | 39 | 15 | 0 | 54 | 42.52 | 0 | |||
| PNC-SPML-JV | 49 | 50 | 2 | 101 | 37 | 19 | 1 | 57 | 56.44 | 0 | |||
| Vindhya-GAJA (JV) | 25 | 22 | 0 | 47 | 14 | 7 | 0 | 21 | 44.68 | 0 | |||
| VSA | 12 | 13 | 0 | 25 | 12 | 3 | 0 | 15 | 60.00 | 0 | |||
| 46 |
Saharanpur |
Gayatri Projects LTD | 10 | 111 | 2 | 123 | 5 | 22 | 0 | 27 | 21.95 | 0 | Poor quality construction work pump house. CC road reinstatement poor workmanship. |
| GA INFRA - BABA (JV) | 88 | 229 | 18 | 335 | 61 | 103 | 16 | 180 | 53.73 | 0 | Poor Quality work OHT 3rd brace beam & column not plumb. Without complete staircase work & plumb of brace beam Inappropriate size of staircase Poor Quality work OHT column found honeycomb | ||
| NKG-PRIMUS (JV) | 9 | 116 | 6 | 131 | 6 | 72 | 3 | 81 | 61.83 | 0 | Poor quality construction work pump house. CC road reinstatement poor workmanship. | ||
| 47 |
Ayodhya |
VSA | 31 | 38 | 18 | 87 | 22 | 19 | 9 | 50 | 57.47 | 0 | |
| UNIVERSAL MEP | 2 | 25 | 10 | 37 | 2 | 25 | 9 | 36 | 97.30 | 0 | |||
| Gayatri Projects LTD | 5 | 14 | 4 | 23 | 3 | 11 | 4 | 18 | 78.26 | 0 | |||
| Vindhya-GAJA (JV) | 8 | 15 | 7 | 30 | 5 | 12 | 5 | 22 | 73.33 | 0 | |||
| 48 |
Amroha |
LC INFRA | 3 | 2 | 3 | 8 | 2 | 2 | 2 | 6 | 75.00 | 0 | 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT |
| OMIL-JWIL (JV) | 87 | 121 | 44 | 252 | 79 | 116 | 39 | 234 | 92.86 | 0 | 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT | ||
| SPML Infra | 80 | 87 | 36 | 203 | 61 | 84 | 31 | 176 | 86.70 | 0 | 1) Poor Quality of Road Restoration 2) Corrosive steel is being used for OHT Construction 3) Poor Quality of Materials used for OHT Construction 4) PPE kit not available at site. 5) RFI was Not raised and Technical staff not present at site 6) Poor Quality of Materials like sand and aggregate are being used for Construction of OHT | ||
| 49 |
Moradabad |
LC INFRA | 40 | 20 | 169 | 229 | 40 | 17 | 164 | 221 | 96.51 | 0 | Cube Test Not Conduct Properly 07 days & 28 days , Approved Drawing Not Avaliable at site , Majorcracks seen on Boundary wall , PPE Kit Not avaliable at site & Saftey Negligence during dome casting. |
| NKG-PRIMUS (JV) | 33 | 27 | 112 | 172 | 30 | 22 | 102 | 154 | 89.53 | 0 | Staging Done Without Staircase , Brick Quality is not good & Saftey negligence during dome casting. | ||
| 50 |
Kanpur Dehat |
GVPR | 4 | 9 | 10 | 23 | 4 | 9 | 10 | 23 | 100.00 | 0 | |
| Indian Hume Pipe | 5 | 5 | 10 | 20 | 5 | 5 | 10 | 20 | 100.00 | 0 | |||
| Vindhya-GAJA (JV) | 2 | 5 | 2 | 9 | 1 | 5 | 2 | 8 | 88.89 | 0 | For Gutaiya WSS Critical NC compliances submitted but its under observation for testing, that's why one NC is pending. | ||
| VSA | 26 | 18 | 23 | 67 | 26 | 18 | 23 | 67 | 100.00 | 0 | 3 nos OHT partial dismantle | ||
| 51 |
Farrukhabad |
Vindhya-GAJA (JV) | 2 | 32 | 21 | 55 | 2 | 28 | 21 | 51 | 92.73 | 0 | |
| GVPR | 33 | 49 | 39 | 121 | 18 | 35 | 31 | 84 | 69.42 | 0 | |||
| 52 |
Kanpur Nagar |
VSA | 28 | 21 | 34 | 83 | 21 | 21 | 34 | 76 | 91.57 | 0 | |
| Vindhya-GAJA (JV) | 74 | 35 | 52 | 161 | 70 | 35 | 52 | 157 | 97.52 | 0 | |||
| 53 |
Mathura |
NCC-APCO JV | 8 | 111 | 6 | 125 | 3 | 75 | 4 | 82 | 65.60 | 0 | |
| 54 |
Agra |
Megha | 132 | 31 | 4 | 167 | 96 | 20 | 2 | 118 | 70.66 | 0 | |
| NCC-APCO JV | 49 | 24 | 6 | 79 | 47 | 23 | 6 | 76 | 96.20 | 0 | |||
| 55 |
Basti |
Megha | 133 | 156 | 186 | 475 | 92 | 88 | 112 | 292 | 61.47 | 0 | |
| JAKSON - VISHVARAJ (JV) | 9 | 33 | 22 | 64 | 4 | 26 | 20 | 50 | 78.13 | 0 | |||
| VSA | 6 | 11 | 14 | 31 | 4 | 9 | 12 | 25 | 80.65 | 0 | |||
| 56 |
Kannauj |
GVPR | 19 | 59 | 40 | 118 | 18 | 55 | 32 | 105 | 88.98 | 0 | Road Restoration Not Done, honeycomb observed, work Without RFI |
| VSA | 63 | 78 | 79 | 220 | 60 | 74 | 55 | 189 | 85.91 | 0 | ZN-AL tank Fusion Not Done, Road Restoration Not Done, Column misalignment observed, honeycomb observed, work Without RFI | ||
| 57 |
Shahjahanpur |
NCC Ltd. | 17 | 29 | 23 | 69 | 13 | 27 | 21 | 61 | 88.41 | 0 | |
| 58 |
Varanasi |
Larsen & Toubro Ltd | 3514 | 25217 | 1201 | 29932 | 3176 | 21896 | 1053 | 26125 | 87.28 | 650 | "1-Cracks observed in Boundary wall. 2-Ganga sand used at site. 3-Joints of brickwork are not filled properly 4-Width of trench found 230mm which is not as per IS code 4984:2016.It should be 600+ dia of pipe as per DPR. 5-Mortar used for the Brick work was not as per DPR and specifications. 6-Curing of the brick work was not properly done.It may result in low hydration of cement and reduce the bo |
| 59 |
Jaunpur |
Welspun Kaveri Infraprojects JV | 2032 | 5658 | 180 | 7870 | 1880 | 5108 | 164 | 7152 | 90.88 | 543 | Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow and Road restoration work slow |
| AFCONS | 2793 | 5351 | 178 | 8322 | 2504 | 4922 | 150 | 7576 | 91.04 | 636 | Honeycomb found in columns of OHT and Crack observed in Boundary wall, Har ghar Jal certification slow | ||
| 60 |
Ghazipur |
HFCL- JWIL (JV) | 1806 | 4166 | 100 | 6072 | 1601 | 3554 | 99 | 5254 | 86.53 | 0 | "1-Width of the trench observed is 200mm at the top of the trench whereas as per DPR the width should be at least 600mm+ of pipe. 2-Quality of sand, 10mm, 20mm Aggregate not satisfactory 3- 75mm HDPE Pipe found laid in damage condition. 4-Depth of the trench is found 600mm at the top of the 63mm HDPE Pipe , whereas as per DPR the Depth should be at least 1000mm+ Dia of pipe. 5-MDPE pipe (20mm) f |
| Larsen & Toubro Ltd | 2961 | 5635 | 249 | 8845 | 2219 | 4057 | 215 | 6491 | 73.39 | 169 | "1-The DPC layer of boundary wall is damaged 2- Honeycombing is found on the coping of the boundary wall 3- Honeycombing is found on the roof of the pump house." | ||
| VSA | 3305 | 6374 | 73 | 9752 | 1770 | 2130 | 17 | 3917 | 40.17 | 140 | "1-Rusted steel used in ground beam work 2-Honeycombing is found in the Ring/Tie beam , Columns of the OHT. 3-Rusted bars are using in the construction of OHT foundation. 4-Cracks are found in the slab of the pump house. 5-Cracks are found in the boundary wall." | ||
| 61 |
Chandauli |
GA INFRA - BABA (JV) | 258 | 3465 | 78 | 3801 | 252 | 3366 | 72 | 3690 | 97.08 | 184 | "1-Hand concrete mixer is being used for concrete mixing instead of weightbatch concrete mixer. 2-Dirty water used for mixing of concreting, which is against clause 4.6 of IS;2250 3-Honeycomb observed in Pump house ( Chajja) 4-Rusted reinforcement use in pump house slab 5-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new brick for re |
| HFCL- JWIL (JV) | 168 | 1420 | 23 | 1611 | 159 | 1358 | 21 | 1538 | 95.47 | 0 | "1-Hand concrete mixer used for concrete mixing Instead of PLC based weighbatch concrete mixer. 2-Depth found 800mm found for 63mm dia HDPE Pipe laying as per DPR it should be 1000mm+Dia 3-Second class bricks are available at site , whereas per the DPR 1st class bricks should be used. 4-Curing of concrete of boundary wall coping casting work not done after de-shuttering . 5-MDPE pipe found above | ||
| ION EXCHANGE | 669 | 5846 | 78 | 6593 | 635 | 5638 | 71 | 6344 | 96.22 | 211 | "1-10mm,20mm aggregate found failed during sieve analasys test 2-Depth of 140mm dia HDPE Pipe found 570mm whereas as per the DPR ,pipe should be laid at least 1.0m+Dia 3-100 percent old brick used for BOE road restoration work as per DPR it should be 50 percent old and 50 percent new Brick should be used for restoration work 4-Hand concrete mixer used for concrete mixing Instead of PLC based weig | ||
| VSA | 1029 | 6283 | 255 | 7567 | 1018 | 6197 | 251 | 7466 | 98.67 | 307 | "1-Grouting of GI pipe not done 2-MDPE pipe found above GL level ( open condition) 3-100 percent old brick use for BOE road restoration work, As per DPR it should be 50 percent old and 50 percent new brick for BOE road restoration work 4-Depth of 63mm dia HDPE Pipe found 700mm, whereas as per the DPR depth should be 1m+dia 5-Reinstatement not done from last one month. Restoration work is being pe | ||
| East India Udhyog- Kaveri JV | 17 | 412 | 1 | 430 | 16 | 353 | 1 | 370 | 86.05 | 0 | LAYING OF HDPE PIPE IS NOT DONE PROPERLY AT SOME PLACES DEPTH IS FOUND 600 -700MM | ||
| 62 |
Deoria |
LC INFRA | 1080 | 7674 | 65 | 8819 | 820 | 5534 | 46 | 6400 | 72.57 | 1948 | 1.-Cracks has been observed in wall of pump house.,2.Crack has been observed on the boundary wall.,3.Steel is visible in lintel beam of pump house. |
| Gayatri Projects LTD | 986 | 6965 | 31 | 7982 | 905 | 6023 | 25 | 6953 | 87.11 | 1287 | 1.Crack has been observed on the boundary wall.,2.Steel is visible in coping of boundary wall. | ||
| Rithwik-Koya (JV) | 201 | 2036 | 21 | 2258 | 155 | 1386 | 10 | 1551 | 68.69 | 101 | 1.3rd brace column finishing not done properly.,2.Honeycomb has been observed on the 6th lift staircase of OHT. | ||
| UNIVERSAL MEP | 177 | 1020 | 8 | 1205 | 166 | 935 | 6 | 1107 | 91.87 | 30 | 1.Crack has been observed on the boundary wall.2.Crack has been observed on coping of boundary wall. | ||
| 63 |
Gorakhpur |
NCC Ltd. | 956 | 14597 | 629 | 16182 | 714 | 10455 | 498 | 11667 | 72.10 | 2627 | 1. GI cashing has not been provided at Culvert crossing. 2. Crack has been observed in the boundary wall. 6. Crack has been observed in the pump house floor. 7. Paint quality is not good of boundary wall. 8. Campus approach road has been settled down. 9. Recharge pit chamber has been found damaged. 10. Honeycomb has been found in OHT TB-2. |
| Rithwik-Koya (JV) | 345 | 5318 | 209 | 5872 | 262 | 4464 | 145 | 4871 | 82.95 | 320 | 1. Cracks has been observed in the boundary wall. 2. HDPE pipe found exposed condition end cap is not provided. 5.Boundary wall coping has been observed damage. 6. Lightning arrester has not been installed on the OHT. 7. The painting work on the OHT has not been done properly. 8. Crack has been found in the OHT apron. | ||
| 64 |
Maharajganj |
JMC - Lakshmi (JV) | 630 | 7049 | 15 | 7694 | 550 | 5756 | 12 | 6318 | 82.12 | 486 | 1.Rusted steel found at construction site. 2.Honeycomb found in OHT 2nd brace beam. 3. Crack has been found in Boundary wall brick work below DPC. 4. Pump House apron has been settled down. 5. Crack observed in Boundary wall. 6.HDPE pipe found in damage condition. 7.Honey combing found in 2nd Brace beam. |
| Rithwik-Koya (JV) | 417 | 3547 | 7 | 3971 | 283 | 2395 | 3 | 2681 | 67.51 | 0 | 1. Honeycombing found in OHT 2nd flight staircase landing. 2. Steel is visible in OHT stair case cantilever beam. 3.OHT 1st lift column has been broken and extra reinforcement is not available for further casting. 4.Pump house Apron found damaged. 5. Steel is visible in OHT 1st brace beam above lift column. 6. Crack found on the wall of Pump house. | ||
| 65 |
Kushi Nagar |
NCC Ltd. | 2722 | 17494 | 217 | 20433 | 2684 | 17279 | 195 | 20158 | 98.65 | 621 | 1. Leakage has been observed in the main raising pipe. 2.Lighting conductor has not been installed as per electricals norms, Its very short length from NGL,The height should be sufficient to create a protective cone covering the building or equipment. 3.It has been observed that Mild Steel (MS) earthing strips have been used at the site in place of the specified Galvanized Iron (GI) strips, which |
| 66 |
Prayagraj |
Larsen & Toubro Ltd | 2328 | 13599 | 450 | 16377 | 1908 | 12311 | 393 | 14612 | 89.22 | 0 | Sunshade of pump house has been found damaged. |
| VPRPL | 303 | 711 | 11 | 1025 | 266 | 548 | 8 | 822 | 80.20 | 0 | Steel bars have been exposed at the bottom of waist slab of staircase. | ||
| GAJA - GAIPL JV | 502 | 634 | 3 | 1139 | 444 | 530 | 3 | 977 | 85.78 | 0 | The alignment of column has been found incorrect. It has been observed tilted. | ||
| 67 |
Kaushambi |
GA INFRA - BABA (JV) | 739 | 4365 | 299 | 5403 | 358 | 2342 | 200 | 2900 | 53.67 | 0 | No cut out has been made at the slab of the oht for inlet and outlet pipe. As hammering in slab should be avoided to counter strength reduction. |
| JMC - Lakshmi (JV) | 601 | 3286 | 201 | 4088 | 477 | 2738 | 170 | 3385 | 82.80 | 0 | Honeycomb has been observed at the outer face of conical wall . poor work was done for the construction of conical wall. | ||
| 68 |
Fatehpur |
Gayatri Projects LTD | 336 | 6772 | 292 | 7400 | 147 | 2360 | 74 | 2581 | 34.88 | 0 | "1.Severe crack has been developed in the boundary wall. 2.Upper part of tubewell is getting rusted. And also Pea gravel feeding has not been done." |
| GA INFRA - BABA (JV) | 160 | 1010 | 20 | 1190 | 102 | 456 | 4 | 562 | 47.23 | 0 | "1.Pea gravel packing in chamber of Pump House has not been done. 2.Tube Well has been left without bore well cap which may cause menace in village." | ||
| Power Mech Projects Ltd | 835 | 5275 | 183 | 6293 | 465 | 2444 | 65 | 2974 | 47.26 | 0 | "1.One panel of boundary wall has been found collapsed due to soil stacked behind it. 2.boundary wall has been found collapsed. The length was aprox. 15 mtr." | ||
| 69 |
Pratapgarh |
JMC - Lakshmi (JV) | 896 | 3942 | 186 | 5024 | 604 | 3158 | 155 | 3917 | 77.97 | 0 | The painting work of the overhead tank staircase has not been carried out properly, Finishing work was not observed properly in the OHT 2nd lift column above GL brace beam. |
| Power Mech Projects Ltd | 1443 | 3453 | 56 | 4952 | 1190 | 2914 | 8 | 4112 | 83.04 | 0 | Washout chamber has been found severely cracked/damaged. Reconstruction required, Boundary wall has been found severely cracked | ||
| 70 |
Bareilly |
NCC Ltd. | 37 | 60 | 36 | 133 | 34 | 59 | 36 | 129 | 96.99 | 0 | 1. Leakage found in Zinc-alum Tank around the jointing of bottom ring wall. 2. MDPE pipe intended for FHTCs have been laid through an existing waste water drain. |
| 71 |
Mainpuri |
NCC Ltd. | 20 | 56 | 19 | 95 | 12 | 48 | 17 | 77 | 81.05 | 0 | |
| 72 |
Sultanpur |
UNIVERSAL MEP | 0 | 0 | 0 | 0 | 13 | 11 | 13 | 37 | 3700.00 | 0 | |
| Gayatri Projects LTD | 18 | 19 | 17 | 54 | 8 | 9 | 13 | 30 | 55.56 | 0 | |||
| Vindhya-GAJA (JV) | 70 | 125 | 131 | 326 | 51 | 43 | 62 | 156 | 47.85 | 0 | |||
| 73 |
Aligarh |
ION EXCHANGE | 11 | 51 | 14 | 76 | 11 | 47 | 14 | 72 | 94.74 | 0 | |
| JMC - Lakshmi (JV) | 12 | 85 | 2 | 99 | 11 | 79 | 1 | 91 | 91.92 | 0 | |||
| PNC-SPML-JV | 15 | 117 | 9 | 141 | 15 | 111 | 9 | 135 | 95.74 | 0 | |||
| 74 |
Firozabad |
Larsen & Toubro Ltd | 5 | 251 | 7 | 263 | 5 | 158 | 7 | 170 | 64.64 | 0 | |
| NCC Ltd. | 0 | 144 | 1 | 145 | 0 | 133 | 1 | 134 | 92.41 | 0 | |||