| S.No. | District | Agency | Scheme ID | Scheme Name | OHT Code | Village ID | Village Name | Issue Type | Remark | Issue Date |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jhansi | BGCCPL-Ramky (JV) | 8135947 | Teharka GOV | OHT-4 | 423972 | Parsuwa | Road Widening | <p>Rising Main DI 200mm dia pipe line damage by PWD</p> | 24-10-2026 |
| 2 | Jhansi | NCC Ltd. | 8009992 | Gulara GOV | OHT0006 | 423894 | Bakuwn Bujur | Road Widening | <p>The pipeline has been damaged, disrupting the water supply to two villages.</p> | 13-10-2026 |
| 3 | Jhansi | Indian Hume Pipe | 8010037 | Kuraicha GOV | 009 | 424227 | Rampura | Road Widening | <p>The PWD damaged the pipeline during road-widening work in 2024. Despite resuming repairs on 01.09.2026 following the DM’s intervention and assuring completion by 15.10.2026, work was stopped again on 20.09.2026. Three critical interconnections remain pending, and full water supply has not been restored. No work is currently in progress.</p> | 16-01-2024 |
| 4 | Jhansi | Indian Hume Pipe | 8010037 | Kuraicha GOV | 009 | 424226 | Arjar | Road Widening | <p>PWD damaged the pipeline during road widening in 2024. Despite work commencing on 01.05.2026 and the DM, Jhansi’s direction dated 23.09.2026 to complete it by 15.10.2026, the work remains incomplete and has stopped again. Approximately 600 m of 150 mm DI pipeline, 2,000 m of 50 mm GI pipeline, and interconnections are pending</p> | 12-01-2024 |
| 5 | Jhansi | Indian Hume Pipe | 8010037 | Kuraicha GOV | 009 | 424230 | Ninaura | Road Widening | <p>The pipeline was damaged by the PWD during road-widening work in <strong>2024</strong>. Despite repair work commencing on 01.05.2026 and the DM, Jhansi’s directions dated 23.09.2026 to complete the work by 15.10.2026, the 150 mm dia. pipeline gap-closing work between Rampura and Arjar remains incomplete. Work has been stopped since 20.09.2026, and the full water supply to Village Ninaura has not been restored.</p> | 10-01-2024 |