S.No. District Agency Scheme ID Scheme Name OHT Code Village ID Village Name Issue Type Remark Issue Date
1 Lucknow NCC Ltd. 20018625 Raitha 20018625/01 415778 Raitha Land Dispute / Litigation ROW Issue 200 mt. Local villageres are stopped due to given land belongs to them. 05-03-2026
2 Lucknow NCC Ltd. 20091318 Pashchim Gaon 20091318/01 415756 Pashchim Gaon Land Dispute / Litigation We have completed construction activity Boundary wall & Pump House as given land by Lekhpal & garam Pradhan. While Alloting land lekhpal & Gram Pradhan said that approach road will be provided by gram Pradhan, but approach road is passing through a private land. Land Lords are not allowing us to move our resources to our campus area. 04-03-2026
3 Lucknow NCC Ltd. 20014490 Gaureyakala 20014490/01 415977 Gaureyakala Land Dispute / Litigation ROW Issue 200 Mt. Pipe Laying Passing Through private land. 07-02-2026
4 Lucknow NCC Ltd. 20069216 Faridpur 20069216/01 416062 Faridpur Land Dispute / Litigation ROW Issue 100 Mt. Pipe Laying Passing Through private land. 29-01-2026
5 Lucknow NCC Ltd. 20069225 Kazee Khera Sekhanapur & Sadarpur karora 20069225/01 416038 Sadarpur Karora Land Dispute / Litigation In front campus a shop situated and obstrution our counstruction work 14-01-2026
6 Lucknow NCC Ltd. 8360592 Fatehganj 8360592/01 415821 Fatehganj Land Dispute / Litigation After installation of Tube well pumping Plant, a local ladies stopped our work from last 02 years 7 month. 05-01-2024