| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20099422 | KORRAKANNAK (QA) | 20099422/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Resolved | In construction of overhead tank the 1st lift column above plinth beam found not in plumb. It is out 25mm.(Rectification done with the help of grinding of over concrete.) | ||||||||||||
| 2 | 8044212 | SIYADI | 8044212/01 | No | No | No | No | Yes | Yes | No | No | No | No | No | No | No | Resolved | Resolved | 1.The overlap of 12mm steel bar found only 300mm instead of 600mm which is critical and not acceptable as per norms. Pre-cast cover blocks are not found in raft foundation.(Reinforcement provided as per drawing) 2.Fasteners of ZA tank has been found damaged. Hold down bracket has been fixed by tilted fasteners.(its is instructed to TKC, replace tilted fasteners) | |||||||||||
| 3 | 20065325 | ASALPUR & SUKETI | 20065325/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | The alignment of brace and column has not been observed correctly. Take corrective action regarding this.(recommended for column to be dismantle) | |||||||||||||
| 4 | 20087377 | KALYANPUR KACHARAULI water supply scheme RO | 20087377/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Alignment of OHT column has not been observed properly vertical. Before further casting it should be rectified. | |||||||||||||
| 5 | 20099395 | Dundara Water Supply Scheme | 20099395/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Resolved | Third flight of Staircase has been found tilted towards outside.(STAIRCASE HAS BEEN DISMANTALED) | ||||||||||||
| 6 | 20099409 | Sulemabad Water Supply Scheme | 20099409/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Top Radial Reinforcement of raft foundation is not provided in staggered position with reference to bottom reinforcement.(reinforcement provided by TKC as per drawing.) | ||||||||||||
| 7 | 20099413 | Chitaura Water Supply Scheme | 20099413/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | Yes | No | Resolved | Resolved | Resolved | Column above first brace beam has been found misaligned and junction of brace and column was not found in proper shape.(After dismantling , reconstruction work has been done.) | ||||||||||
| 8 | 20099441 | Mauyara (RO) | 20099441/01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | Fastener of ZA tank has been found damaged .Hold down bracket has been fixed by tilted fastener.(zinc tank tilted fastner to bereplace ) | |||||||||||||
| 9 | 20106723 | DHAKAULI | 20106723/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Resolved | the ground brace brace not vertically aligned in distance between of one to another column of OHT. (after dismantling, reconstruction work done.) | ||||||||||||
| 10 | 20087682 | CORSAM water supply scheme | 20087682/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | the edge of 3rd brace beam of OHT has been found damaged at site. | ||||||||||||
| 11 | 20065440 | KEWAI & MAHUMUDPUR | 20065440/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Without using vibrator casting work started of second lift column above first brace beam at site. Vibrator not in functional condition also.(casting work has been done with the help of Vibrator ) | ||||||||||||
| 12 | 20099388 | Gopalpur | 20099388/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Beam shuttering size was not maintained at site as per drawing. During inspection 300mm width was found in place of 400mm.(provided as per drawing) | ||||||||||||
| 13 | 20087446 | SHAHPUR water supply scheme RO | 20087446/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | Yes | No | Resolved | Resolved | Resolved | Steel bar and Honey comb has been observed in the column of OHT. Poor casting of concrete work done. The alignment of column was not observed properly vertical. Dismantling of column has been done. | ||||||||||
| 14 | 20087462 | KANSPUR GANGAULI | 20087462/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | During Raft foundation steel binding work steel found very corrosive at site(Reinforcement has replaced.) | ||||||||||||
| 15 | 20065324 | IJURA BUJURG | 20065324/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Surface of plinth beam of OHT is not in shape(After dismantling work, reconstruction work done) | ||||||||||||