Agency-wise Major/critical Ncs at OHT

S.No. Scheme ID Scheme Name OHT Code Non-Compliance Compliance(Current Status)
Description
Major Honey Comb Alignment Cube Test Exposure Deviation Tank Observation Other SBC Issue Demolish Partially Demolish Fully Under Examination Serious Observation Water Body Compliance Major Honey Comb Compliance Alignment Compliance Cube Test Compliance Exposure Compliance Deviation Compliance Tank Compliance Other Compliance SBC Issue Compliance Demolish Partially Compliance Demolish Fully Compliance Under Examination Compliance Serious Observation Compliance Water Body
1 20099003 HUSENIPURWA RISIA (VPL) PWS 20099003/01 No Yes No No No No No No No No No No No *The columns are vertically not aligned, deviating from the specified standards
2 20099016 NAWAPATTI CHITAURA (VPL) MVS PWS 20099016/01 No Yes No No No No No No No No No No No The improper shuttering has led to alignment issues between the columns and brace beams.
3 20093234 UDHARANA SARAHDI VISHESWARGANJ (VPL) PWS 20093234/01 No No No No No No Yes No No No No No No *Certain vertical reinforcement bars of the column have been cut and appear to have been stolen.
4 20101738 MOTIPUR MIHIPURWA (VPL) PWS 20101738/01 Yes Yes No No No No No No No No No No No *Honeycomb is observed in column and brace beam. *Column is not vertically aligned and section is not properly casted. *Center to center distance between two columns has 30-40 mm variation from drawing.
5 20092859 MOHANAPUR GANGAPUR MIHIPURWA (VPL) PWS 20092859/01 No No No Yes No No No No No No No No No *Due to prolonged suspension of work, all reinforcement steel in the column of the OHT structure has become rusted from continuous exposure without any protective covering.
6 20098992 JHALA MIHIPURWA (VPL) PWS 20098992/01 No No No No Yes No No No No No No No No *Dimensional error in one of Brace beam not as per approved drawing.
7 20093179 PIPARI MAFI SHIVPUR (VPL) PWS 20093179/01 No Yes No No No No No No No No No No No *All column is not vertically aligned.
8 20099013 TIKUAPARA SHIVPUR (VPL) PWS 20099013/01 No No No No Yes No Yes No No No No No No *Concrete pouring is being caried out directly on the ground. *Slump of concrete is not as desired and even slump cone is also not provided at site.
9 20099005 KARNIYA RISIA (VPL) PWS 20099005/01 No No No No No No Yes No No No No No No *Few vertical columns steel is chopped at GL level.
10 20098948 NIBIYASHAH MOHAMMADPUR BALAHA (VPL) PWS 20098948/01 No No No No No No Yes No No No No No No *Few vertical columns steel chopped at GL level .
11 20098950 TULSIPUR BALAHA (VPL) PWS 20098950/01 No No No No No No Yes No No No No No No *Few vertical columns steel chopped at GL level .
12 20092705 MADHUBAN BALAHA (VPL) PWS 20092705/01 No No No No Yes No No No No No No No No *staircase waist slab thickness not as per approved drawing.
13 20101733 NAGAR CHITTAURA (VPL) PWS 20101733/01 No No No No No No Yes No No No No No No *1st staircase cantilever beam reinforcement cut from column.
14 20093332 BARAI BILASA CHITAURA (VPL) MVS PWS 20093332/01 Yes No Yes No No No No No No No No No No *Cube failed of 28 days of 1st lift column above 2nd brace.
15 20099788 PARSA RAMPUR PHAKARPUR (VPL) PWS 20099788/01 No No No No Yes No No No No No No No No *Ring beam alignment not as per approved drawing, ring beam found in zig zig manner.
16 20092931 BAMIYARI PAKHARPUR (VPL) PWS 20092931/01 No No No No Yes No No No No No No No No *Dimensional error in OHT staircase.
17 20099780 TAJA KHODAI CHITTAURA (VPL) PWS 20099780/01 Yes Yes No No No No No No No No No No No *Misalignment of column above 3rd brace and honeycomb in columns. *Honeycomb is OHT column.
18 20093315 JAMNUHA NAUBASTA NAWABGANJ (VPL) MVS PWS 20093315/01 No No No No Yes No No No No No No No No *Deviation in brace beam, not constructed as per approved drawing.
19 20093320 AMWA TETARPUR PHAKHARPUR (VPL) MVS PWS 20093320/01 No No No No Yes No No No No No No No No *Regarding poor surface finishing of OHT air voids seams at few places.
20 20093190 MANIKPUR BAGHAULI SHIVPUR (VPL) PWS 20093190/01 No No No Yes No No No No No No No No No *Regarding rusting of Beam steel at GL level beam .
21 20093210 GANIYAPUR TEJWAPUR (VPL) PWS 20093210/01 No No No No Yes No No No No No No No No *Regarding top ring beam has executed in deviation from the approved drawing.
22 20093285 KAHARAI KAISARGANJ (VPL) MVS PWS 20093285/01 No Yes No Yes Yes No No No No No No No No *Columns are not vertically aligned. *Rusting in exposed steel from column.
23 20098995 SEMRAHANA MIHIPURWA (VPL) PWS 20098995/01 No No No No No Yes No No No No No No No *Regarding improper finishing work and finishing of Zinc alum tank erection work.
24 20092866 AYODHYA GAON MIHIPURWA (VPL) PWS 20092866/01 Yes No No Yes Yes No Yes No No No No No No *Dimensional error in all Brace beam not as per approved drawing. *Rusted reinforcement steel found at full stagging possible due to long delay in casting. *Minor honeycomb is brace column junction due to poor compaction due to concreting.
25 20098996 PEERNASARUDDIN NAWABGANJ (VPL) PWS 20098996/01 No Yes No No No No No No No No No No No *Regarding misalignment in GL brace and minor honeycomb in column brace junctions.
26 20099010 UCHWA PURAINA CHITTAURA (VPL) PWS 20099010/01 Yes No No No No No No No No No No No No *HONEYCOMB IS OBSERVED IN STAIRCASE SLAB .
27 20099007 MAJHAUBWA VISHESWARGANJ (VPL) PWS 20099007/01 No No No No Yes No No No No No No No No Resolved Brace steel lapping length is not as per IS standard