Agency-wise Major/critical Ncs at OHT

S.No. Scheme ID Scheme Name OHT Code Non-Compliance Compliance(Current Status)
Description
Major Honey Comb Alignment Cube Test Exposure Deviation Tank Observation Other SBC Issue Demolish Partially Demolish Fully Under Examination Serious Observation Water Body Compliance Major Honey Comb Compliance Alignment Compliance Cube Test Compliance Exposure Compliance Deviation Compliance Tank Compliance Other Compliance SBC Issue Compliance Demolish Partially Compliance Demolish Fully Compliance Under Examination Compliance Serious Observation Compliance Water Body
1 20088316 SIPARI W/S SCHEME (HFCL) 20088316/01 No No No No No No Yes No No No No No No Resolved TPI Observation-"The provided development length of reinforcement was found to be insufficient and does not meet the prescribed specifications, which may compromise the structural integrity and load transfer efficiency.
2 20092034 GOVINDPUR W/S SCHEME (HFCL) 20092034/01 No No No No No No Yes No No No No No No Resolved TPI Observation- Main bars of brace beam are merged at junction box which are not fit according to drawing.
3 20097691 KHIJIRPUR W/S SCHEME (HFCL) 20097691/01 Yes No No No No No No No No No No No No Resolved TPI Observation- Honeycombing was observed in the column of OHT, indicating poor compaction or improper concrete placement, which may affect the structural integrity. Rectification Status- Rectified Observation- Honeycombing repaired by cement grouting.
4 20100544 AMABANSI W/S SCHEME (HFCL) 20100544/01 No No No No No No Yes No No No No No No Resolved TPI Observation- Rusted reinforcement bars were being used in the Overhead Tank (OHT) construction. The use of corroded steel compromises the bond with concrete and adversely affects the structural strength and durability of the structure. Immediate corrective action .
5 20091456 PATE PUR W/S SCHEME (HFCL) 20091456/01 No No No No No No Yes No No No No No No Resolved TPI Observation- The specified concrete cover of 50 mm was not maintained; only 25 mm cover was provided. This deviation from the design specification compromises durability and corrosion protection of the reinforcement, and must be rectified immediately."
6 20076123 PAREWA W/S SCHEME (HFCL) 20076123/01 No No No No No No Yes No No No No No No Resolved TPI Observation- Rusted and corroded steel bars were being used for the OHT reinforcement work, which is against standard specifications and may compromise the structural integrity and durability of the structure.
7 20086391 DHARI KHURD W/S SCHEME (HFCL) 20086391/01 No No No No No No Yes No No No No No No Resolved TPI Observation- Rusted steel reinforcement was used in the column, which may affect the bond strength with concrete and compromise the structural integrity. Rectification Status- Rectified Observation- Reinforcement is coated with cement slurry after instruction
8 20097093 NEWADAA W/S SCHEME (HFCL) 20097093/01 No Yes No No No No No No No No No No No Resolved tpi Observation- OHT column and plinth beam are not in proper alignment. Honeycomb observed in OHT Column and plinth beam area.
9 20111029 KHATIRPUR W/S SCHEME (HFCL) 20111029/01 No No No No No No Yes No No No No No No Resolved TPI Observation- Rusted reinforcement bars were used in column of OHT, which may adversely affect the bonding with concrete and the overall durability of the structure. Rectification Status- Rectified Observation- Photo of coating with anti-rust chemical provided by TKC.
10 20097769 AHLADPUR W/S SCHEME (HFCL) 20097769/01 No No No No No No Yes No No No No No No Resolved tpi Observation- Reinforcement bar overlapping has not been executed as per the specified standards. Improper lapping may compromise the structural strength and durability of the component. Rectification is necessary to ensure compliance with IS codes and design requirement
11 20088188 TODERPUR W/S SCHEME (HFCL) 20088188/01 No No No No No No Yes No No No No No No Resolved TPI Observation- 1. The cover block provided for the column reinforcement does not meet the specified thickness as per design and code requirements, which may lead to reduced durability and increased risk of reinforcement corrosion 2. Rusted steel was used in the OHT column reinforcement work works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
12 20094505 KHANPUR RAGHUBAR RAI & KRITSINGH PUR W/S SCHEME (HFCL) 20094505/01 No No No No No No Yes No No No No No No Resolved TPI Observation- Hook bending of reinforcement bars at 135 degrees, as specified in IS 2502 and IS 456:2000, was not provided. This non-compliance may lead to inadequate anchorage and compromised structural integrity, particularly in seismic or high-stress zones."
13 20091435 BELSARI W/S SCHEME (HFCL) 20091435/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT raft casting reinforcement works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
14 20074381 KANUWAN W/S SCHEME (HFCL) 20074381/01 No No No No No No Yes No No No No No No Resolved TPI Observation- The spacing of reinforcement steel bars was found to be inconsistent with the approved structural drawings. Such deviation may affect the structural performance and load distribution, and must be rectified to comply with design specifications.
15 20073704 SUZNI PUR W/S SCHEME (HFCL) 20073704/01 No No No No No No Yes No No No No No No Resolved TPI Observation- 1. Proper bending of OHT column ring hook at 135 degrees was not provided. 2. Cover block of OHT raft foundation not provided as per specified thickness.
16 20097015 MATH UCHORI W/S SCHEME (HFCL) 20097015/01 No No No No No No Yes No No No No No No Resolved TPI Observation- OHT Coloumn steel is found in damaged condition.
17 20073685 KATGHRA W/S SCHEME (HFCL) 20073685/01 No No No No No No Yes No No No No No No Resolved TPI Observation- Rusted steel was used in the OHT reinforcement work works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
18 20086393 UTTAMPUR W/S SCHEME (HFCL) 20086393/01 No No No No No No No No No No No No No Observation- During the inspection, reinforcement steel was observed getting rusted due to exposure to environmental conditions. This can compromise the bond with concrete and affect the structural durability if not addressed promptly.
19 20088552 M RAFI ALIAS SHIVDASPUR W/S SCHEME (HFCL) 20088552/01 No No No No No No Yes No No No No No No Observation- OHT Column steel found rusted.
20 20097737 ALAMPUR & SONA W/S SCHEME (HFCL) 20097737/01 No No No No No No Yes No No No No No No Observation- OHT Column steel found damage condition and all steel cut.
21 20088554 KARAMPUR W/S SCHEME (HFCL) 20088554/01 Yes No No No No No No No No No No No No Observation- Honeycomb visible in OHT Column area proper finishing required as per methodology.
22 20088202 HASANPUR W/S SCHEME (HFCL) 20088202/01 No No No No No No Yes No No No No No No Observation- OHT Column steel found Damage Condition and Steel Cut.
23 20086418 TOKAWA W/S SCHEME (HFCL) 20086418/01 No No No No No No Yes No No No No No No Resolved Observation- OHT Ground brace beam Shuttering alignment not in center of column.
24 20086381 MALA KHURD W/S SCHEME (HFCL) 20086381/01 No No No No No No Yes No No No No No No Observation- Torq Rench Calibration certificate not available during inspection.
25 20088583 DAULATPUR W/S SCHEME (HFCL) 20088583/01 No No No No No No Yes No No No No No No Observation- OHT Column steel found rusted.
26 20091452 MAKRSAN W/S SCHEME (HFCL) 20091452/01 No No No No No No Yes No No No No No No Observation- OHT Column steel found damage Condition
27 20097760 CIPAH W/S SCHEME (HFCL) 20097760/01 No No No No No No Yes No No No No No No Observation- Overlapping found 400mm instead 800 at 1st brace beam
28 20097687 BARAR & JANUPUR W/S SCHEME (HFCL) 20097687/01 No No No No No No Yes No No No No No No Resolved Observation- Radial bars has been not provided at inner and outer portion according to specifications
29 20086255 CHITORA W/S SCHEME (HFCL) 20086255/01 No No No No No No Yes No No No No No No Observation- OHT Column steel found rusted.
30 20086199 TARAW W/S SCHEME (HFCL) 20086199/01 No No No No No No No No No No No No No Observation- OHT Column steel found rusted.
31 20100562 PIPNAR W/S SCHEME (HFCL) 20100562/01 No No No No No No No No No No No No No Observation- Proper support with Shuttering required in OHT Column works.
32 20100531 HUSAYPUR W/S SCHEME (HFCL) 20100531/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT first brace beam of column works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
33 20087154 BIJAHARA W/S SCHEME (HFCL) 20087154/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT first brace beam of coloumn works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
34 20086449 MARDANPUR W/S SCHEME (HFCL) 20086449/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT Plinth beam . This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
35 20075253 KHETAABPUR W/S SCHEME (HFCL) 20075253/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT Plinth beam. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
36 20092082 TARKA & AMAROPUR W/S SCHEME (HFCL) 20092082/01 No No No No No No Yes No No No No No No Resolved Observation- Ring beam Steel binding is not found as per drawing. Stirrups of the beam not hold with main bar of the beam.
37 20092051 TISAURI W/S SCHEME (HFCL) 20092051/01 No No No No No No Yes No No No No No No Resolved Observation-. Rusted steel was used in the OHT Raft column works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability 2. Rusted steel was used in the OHT Raft works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
38 20086444 BHALA W/S SCHEME (HFCL) 20086444/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT Brace beam works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability.
39 20106928 USIA W/S SCHEME (HFCL) 20106928/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT column works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
40 20088383 LOHWA & HAZIPUR BARESAR & HASANPUR GAURA W/S SCHEME (HFCL) 20088383/01 No No No No No No Yes No No No No No No Resolved Observation- The beam of the OHT raft has been observed to be in an undulated shape.
41 20102083 PURAN PUR W/S SCHEME (HFCL) 20102083/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT slab casting works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability.
42 20088204 DUDHAURA W/S SCHEME (HFCL) 20088204/01 No No No No No No Yes No No No No No No Resolved Observation- Segregation was observed during concrete casting.
43 20093397 CHAITHO BANDH W/S SCHEME (HFCL) 20093397/01 No No No No No No Yes No No No No No No Resolved Observation- Segregation was observed during concrete casting
44 20074355 BAHRAMPUR W/S SCHEME (HFCL) 20074355/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT column works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
45 20086359 ENDRAPUR CHHIRI W/S SCHEME (HFCL) 20086359/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT plinth beam. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability. 2. OHT plinth beam shuttering is not aligned. 3. Rusted steel was used in the OHT column works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
46 20086345 OTANA W/S SCHEME (HFCL) 20086345/01 No No No No No No Yes No No No No No No Resolved Observation- During the inspection of the OHT (Overhead Tank) column ring reinforcement work, it was observed that proper binding of ring hooks at 135 degrees was not provided as per standard detailing requirements.
47 20073711 CHOKARI_W/S_SCHEME 20073711/01 No No No No No No Yes No No No No No No Resolved Observation- During the inspection of the OHT (Overhead Tank) column ring reinforcement work, it was observed that proper binding of ring hooks at 135 degrees was not provided as per standard detailing requirements.
48 20088191 POOTA W/S SCHEME (HFCL) 20088191/01 No No No No No No Yes No No No No No No Resolved Observation- Staggered bars were not used for lapping, which is against standard reinforcement practices. Spacing of Slab Steel Bars Not as per Approved Drawing
49 20086196 VASILA & JAGMAL ZOT W/S SCHEME (HFCL) 20086196/01 No No No No No No No No No No No No No Observation- Rusted steel was used in the OHT coloumn reinforcement works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
50 20097732 PAHARPUR TAUFIR W/S SCHEME (HFCL) 20097732/01 No No No No No No Yes No No No No No No Resolved Observation- Alignment of the brace beam has not been executed as per design specifications. This misalignment can lead to structural inefficiency and potential stability concerns in the OHT framework.
51 20088558 UCHORI W/S SCHEME (HFCL) 20088558/01 Yes No No No No No No No No No No No No Resolved Observation- Honeycomb visible in OHT Column area, proper finishing is required.
52 20086408 SARAI BAHADUR W/S SCHEME (HFCL) 20086408/01 No No No No No No Yes No No No No No No Resolved Observation- Rusted steel was used in the OHT raft column reinforcement works. This compromises the bonding between concrete and steel and poses a serious risk to structural integrity and durability
53 20100532 CHAK MUKURI BAREJPUR W/S SCHEME (HFCL) 20100532/01 No No No No No No Yes No No No No No No Resolved Observation- A visible crack has been observed on the OHT column.
54 20086425 BURANPUR W/S SCHEME (HFCL) 20086425/01 No No No No No No No No No No No No No
55 20086281 ODASAN W/S SCHEME (HFCL) 20086281/01 No No No No No No No No No No No No No
56 20100536 SALEMPUR BAGHAI W/S SCHEME (HFCL) 20100536/01 No No No No No No No No No No No No No
57 20074299 DEVAPAR W/S SCHEME (HFCL) 20074299/01 No No No No No No No No No No No No No
58 20100552 CHAK PAHAR M.MURTAJPUR W/S SCHEME (HFCL) 20100552/01 No No No No No No No No No No No No No
59 20097674 CHAK JAINAB W/S SCHEME (HFCL) 20097674/01 No No No No No No No No No No No No No
60 20075421 JAHNI W/S SCHEME (HFCL) 20075421/01 No No No No No No No No No No No No No
61 20088257 GOPALPUR W/S SCHEME (HFCL) 20088257/01 No No No No No No No No No No No No No
62 20076400 SHAHPUR & MURERA BUZURG W/S SCHEME (HFCL) 20076400/01 No No No No No No No No No No No No No
63 20073819 AARIPUR W/S SCHEME (HFCL) 20073819/01 No No No No No No No No No No No No No
64 20088430 JAIRAMPUR MANGWAL W/S SCHEME (HFCL) 20088430/01 No No No No No No No No No No No No No
65 20088221 SARDARPUR W/S SCHEME (HFCL) 20088221/01 No No No No No No No No No No No No No
66 20088470 KANERI W/S SCHEME (HFCL) 20088470/01 No No No No No No No No No No No No No
67 20075942 BARAULI SULTAN SINGH W/S SCHEME (HFCL) 20075942/01 No No No No No No No No No No No No No
68 20086207 MOUDIHA & BARWA KHURD W/S SCHEME (HFCL) 20086207/01 No No No No No No No No No No No No No
69 20088408 MALIKPURA W/S SCHEME (HFCL) 20088408/01 No No No No No No No No No No No No No
70 20100557 BURANPUR W/S SCHEME (HFCL) 20100557/01 No No No No No No No No No No No No No
71 20086446 SONBARSA W/S SCHEME (HFCL) 20086446/01 No No No No No No No No No No No No No
72 20092091 SARAI DHANESH W/S SCHEME (HFCL) 20092091/01 No No No No No No No No No No No No No
73 20074377 JALALPUR DHANI W/S SCHEME (HFCL) 20074377/01 No No No No No No No No No No No No No
74 20092007 KISHUN PUR W/S SCHEME (HFCL) 20092007/01 No No No No No No No No No No No No No