| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20096561 | RUDAULI PWS | 20096561/001 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Cube test of the top dome was found below acceptance criteria. NDT was conducted. | ||||||||||||
| 2 | 20014587 | BAKHARIYA PWS | 20014587/001 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Final staircase of the precast OHT was replaced due to crack development | ||||||||||||
| 3 | 20056125 | Nandgaon PWS | 20056125/001 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Misalignment was observed in the 4th flight staircase of the OHT. | ||||||||||||
| 4 | 20033773 | Jarhuliya PWS | 20033773/001 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Cracks were observed in the staircase portion of the OHT structure.” | ||||||||||||
| 5 | 8362627 | Niyamatpur bihari | 8362627/001 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Cube test results of the 3rd brace beam were found below the acceptance criteria; therefore, NDT was conducted | ||||||||||||
| 6 | 8361893 | SHIVPUR | 8361893/001 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | “Cube test results of column above 1st brace beam were found below the acceptance criteria; therefore, NDT was conducted | ||||||||||||
| 7 | 20055680 | Burhanpur PWS | 20055680/001 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Cube test results of 1st lift column above 2nd brace beam were found below the acceptance criteria; therefore, NDT was conducted | ||||||||||||
| 8 | 20055688 | Dhorera PWS | 20055688/001 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Minor honeycombing was observed in the Bottom Dome and Container Wall. After rectification, NDT was conducted. | ||||||||||||
| 9 | 20014865 | BASHAI PWS | 20014865/001 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Seepage was observed in the OHT structure. | ||||||||||||
| 10 | 20014533 | narttampur pws | 20014533/001 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Minor misalignment was observed in one column located above the 2nd brace beam of the OHT structure. | ||||||||||||
| 11 | 20022745 | Kaithawa Water Supply Schem | 20022745/001 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Seepage was observed in the OHT structure. | ||||||||||||