Agency-wise Major/critical Ncs at OHT

S.No. Scheme ID Scheme Name OHT Code Non-Compliance Compliance(Current Status)
Description
Major Honey Comb Alignment Cube Test Exposure Deviation Tank Observation Other SBC Issue Demolish Partially Demolish Fully Under Examination Serious Observation Water Body Compliance Major Honey Comb Compliance Alignment Compliance Cube Test Compliance Exposure Compliance Deviation Compliance Tank Compliance Other Compliance SBC Issue Compliance Demolish Partially Compliance Demolish Fully Compliance Under Examination Compliance Serious Observation Compliance Water Body
1 20101347 Bagahwa GP WSS 20101347/01 No No No No No No Yes No No No No No No Regarding OHT staircase is not as per drawing.Height of staircase riser is increased and no of flight is decreased
2 20093075 MANJHARIA GP WSS 20093075/01 No No Yes No No No No No No No No No No Concerte cube does not gain its target compressive strength on 28 days of testing.
3 20093989 NEUSA AND JIWA GP WSS 20093989/01 No No Yes No No No No No No No No No No Concrete Cube does not gain its required strength in 28 days
4 20094025 SEKHUI AND DADWAR BHATT GP WSS 20094025/01 No No Yes No No No No No No No No No No Concrete Cube does not gain its required strength in 28 days OHT Plinth Beam .
5 20096686 CHECHARAF BUJURG GP WSS 20096686/01 No No Yes No No No No No No No No No No Concrete Cube does not gain its required strength in 28 days OHT Raft
6 20101818 Jogibari GP WSS 20101818/01 No No No No No No Yes No No No No No No OHT work has not going on from last few months .OHT column steel is cut by someone at site.
7 20096827 AHADI GP WSS 20096827/01 No No No No No No Yes No No No No No No 1.Column steel is rusted, bend and cover with soil .Need cleaning before further casting. 2.OHT work has not going on from last few months .OHT column steel is cut by someone at site. It is advised to provide proper lap length by dismantling the column up to a certain length and use chemical adhesive before further concreting
8 20101921 Dhobaha mustakham GP WSS 20101921/01 No No No No No No Yes No No No No No No Regarding maximum nos of bar are curtailed from column of OHT at GL
9 20096599 MADUKAR PUR GP WSS 20096599/01 No No No Yes No No No No No No No No No OHT raft half casted still now, complete it. and Use the iron oxide before casting.
10 20096821 AMAUNA TIWARI AND BHALUKONI JAPATI GP WSS 20096821/01 No No No No No No Yes No No No No No No Resolved Rectify the OHT PCC work as per drawing & Checked the SBC report & found result satisfactory
11 20092969 BASTHA GP WSS 20092969/01 No No Yes No No No No No No No No No No Resolved OHT Raft conducted Core cutting & result found satisfied.
12 20096600 Patani Jungle 20096600/01 No No No No No No Yes No No No No No No Resolved Loose material has been removed and cube result tested at 28 day found satisfactory.
13 20096825 TILGADIYA BUJURG GP WSS 20096825/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member has been done and result found satisfactory .(OHT 3rd Brace)
14 20096339 PIPRA CHHANGAT GP WSS 20096339/01 No No Yes No No No No No No No No No No Resolved OHT 3rd Brace Done NDT test and result found satisfied.
15 20076612 FUTUKA HARBANSSHAHPUR GP WSS 20076612/01 No No Yes No No No No No No No No No No Resolved Concrete cube of OHT 1st lift column above 1st brace Done NDT test and result found satisfied.
16 20096760 CHETIA GP WSS 20096760/01 No No Yes No No No No No No No No No No Resolved Concrete cube of 3rd and 4th flight of staircase Done with NDT test and result found satisfied.
17 20094098 SIHORWA GP WSSS 20094098/01 No No No No No No Yes No No No No No No Resolved Replace the damaged steel
18 20096613 DASIA GP WSS 20096613/01 No No No No No No Yes No No No No No No Resolved Resolved Rectification has been done by increasing the depth by re excavation of OHT foundation
19 20094181 DHANDHARA 20094181/01 No No No No No No Yes No No No No No No Resolved Replace rusted steel of OHT, Raft Steel binding work
20 20097020 BHATGAWA GP WSS 20097020/01 No No No No No No Yes No No No No No No Resolved Replace rusted steel of OHT, Raft beam Steel binding work
21 20093878 LEDAWA GP WSS 20093878/01 No No Yes No No No No No No No No No No Resolved Done NDT test and result found satisfied.1st lift column above slab level
22 20076707 GOLHAURA MUSTKAM AND PARSA STATION GP WSS 20076707/01 No No Yes No No No No No No No No No No Resolved OHT cube 2nd lift column up to 1st Brace Done NDT test and result found satisfied.
23 20101845 Gaya Ghat GP WSS 20101845/01 No No Yes No No No No No No No No No No Resolved stair case 5th landing cube test Done NDT test and result found satisfied.
24 20096688 PARSA GP WSS 20096688/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that mamber has been done and result found satisfactory
25 20096740 HARI JOT GP WSS 20096740/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member has been done and result found satisfactory
26 20096703 AKOLHIYA GP WSS 20096703/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member has been done and result found satisfactory
27 20094406 KARAHIA SAGHAN GP WSS 20094406/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member has been done and result found satisfactory
28 20101843 Rudrauliya Bujurg GP WSS 20101843/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member has been done and result found satisfactory
29 20102124 BALUA GP WSS 20102124/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member(2nd 4th and 5th lift stair) has been done and result found satisfactory.
30 20101822 Pipra Ramlal GP WSS 20101822/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member(Pump House slab) has been done and result found satisfactory
31 20076474 MANIKAURA FIRST AND PIPRA PANDET GP WSS 20076474/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member(1st Brace) has been done and result found satisfactory
32 20096571 RASOOLPUR GP WSS 20096571/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member has been done and result found satisfactory
33 20096605 KANWAR GP WSS 20096605/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member(1st Brace)has been done and result found satisfactory
34 20076416 CHAURASI AND JAGMOHANI GP WSS 20076416/01 No No No No No Yes No No No No No No No Resolved Rechecking and repair leakage of Zinc Alum tank .
35 20076751 KAPIYA SHUKLA GP WSS 20076751/01 No No No No No No Yes No No No No No No Resolved Rectified the reinforcement lap work as per drawing and use foam to close gap
36 20076667 MAHADEWA LALA GP WSS 20076667/01 No No No No No No Yes No No No No No No Resolved dismantling the column and provided lap length
37 20094389 MAHADEWA KURMI AND BUZURG GP WSS 20094389/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member(6th Flight Stair) has been done and result found satisfactory
38 20096642 Badurgahna GP WSS 20096642/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member(OHT1st lift column above 2nd brace) has been done and result found satisfactory
39 20076714 BARDAHI NANKAR GP WSS 20076714/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member(OHT 5th landing staircase) has been done and result found satisfactory
40 20096756 SUPA RAJA AND BHAGAUTA PUR NORTH GP WSS 20096756/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member (1't lift column above 1st brace beam) has been done and result found satisfactory
41 20076643 TIGHARA GP WSS 20076643/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member has been done and result found satisfactory
42 20093980 TENUA GP WSS 20093980/01 No No Yes No No No No No No No No No No Resolved Done NDT test and result found satisfied.
43 20096566 AURAHWA GP WSS 20096566/01 No No No No No No Yes No No No No No No Resolved Replace the reinforcement as per drawing
44 20093971 NAGWA GP WSS 20093971/01 No No Yes No No No No No No No No No No Resolved NDT (Rebound hammer and Ultrasonic pulse velocity test ) on that member has been done and result found satisfactory
45 20094058 KAT BANDH GP WSS 20094058/01 No No No No No No Yes No No No No No No Regarding OHT column steel cutting and provide proper lap before casting.
46 20093066 SEHUDA GP WSS 20093066/01 No No No No No Yes No No No No No No No 1. During inspection found that zinc alum tank Nut and bolt not properly tightened, leading to a loose connection at the bracket. 2. It is also observed grouting has not done.
47 20094261 BARAGO GP WSS 20094261/01 No No No No No No Yes No No No No No No 1. During site visit it is found that staircase dowel bar is cut by unknown person. 2. Site is situated at low land area.
48 20097023 BANKATA SECOND GP WSS 20097023/01 No No Yes No No No No No No No No No No Resolved OHT 1st brace above 1st lift column Done NDT test and result found satisfied. and Honeycombing Use GP2 material for repairing