| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20100357 | LALE MAU WSS | 20100357/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Vertical columns have been found plum out at approximately 14-meter height level. | |||||||||||||
| 2 | 20090033 | RANJEET NAGAR W/S SCHEME | 20090033/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | OHT staircase cantilever beam alignment issue | |||||||||||||
| 3 | 20089980 | PIPRA PADUM W/S SCHEME | 20089980/01 | Yes | Yes | No | Yes | No | No | No | No | No | No | No | No | No | 1.Major Honeycomb observed in 2nd Beams & Columns 2.Steel is exposed 3.Misalignment in every column | |||||||||||||
| 4 | 20100614 | Maraila & BANGHUSRA WSS | 20100614/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | 1. 7th day Cube Test Fail for Raft 2. 28 day Cube Test Fail for Raft | |||||||||||||
| 5 | 20100619 | BARDAHA & BARTARA WSS | 20100619/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Honeycomb observed in tie beam 2 of the OHT | |||||||||||||
| 6 | 20100604 | DHODHUPUR WSS | 20100604/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | 1. 28 day Cube Test Fail for Tie Beam-2 | |||||||||||||
| 7 | 20090083 | DEVARIYA MADDO W/S SCHEME | 20090083/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Honeycomb observed in Column above Tie Beam-2 | |||||||||||||
| 8 | 20100598 | PARSIA BAHORIPUR & HARRYA JHUMAN | 20100598/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Lapping of column Above TB-3 is not as Per drawing | |||||||||||||
| 9 | 20099074 | ITIATHOK WSS | 20099074/01 | Yes | No | No | Yes | No | No | No | No | No | No | No | No | No | Honeycomb and Steel exposed in conical wall | |||||||||||||
| 10 | 20090408 | TENDUA CHAUKAHRIA & BIRMAPUR W/S SCHEME | 20090408/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Column Reinforcement cut at Plinth Level | |||||||||||||
| 11 | 20099098 | GADHI & KEMI WSS | 20099098/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Honeycomb observed in tie beam 2,3 and 4 of the OHT | |||||||||||||
| 12 | 20090353 | Dinkarpur & Chandpur Lakhpatrai W/S SCHEME | 20090353/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Honeycomb observed in tie beam 2 of the OHT | |||||||||||||
| 13 | 20099073 | GOHANHA WSS | 20099073/01 | Yes | No | No | Yes | No | No | No | No | No | No | No | No | No | Honeycomb and steel visible observed in 1st Flight of Staircase of OHT. | |||||||||||||
| 14 | 20099100 | MANKAPUR & MIRZAPUR RAMNATH WSS | 20099100/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Honeycomb observed in Bottom Dome of the OHT | |||||||||||||
| 15 | 20090173 | BALLIPUR W/S SCHEME | 20090173/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | Yes | Misalignment observed in Plinth Beam of the OHT. | |||||||||||||
| 16 | 20099094 | CHHITNAPUR WSS | 20099094/01 | Yes | Yes | No | No | No | No | No | No | No | No | No | No | Yes | Several honeycombs were observed on the 5th flight of the OHT staircase, and the 2nd flight staircase was found to be misaligned. | |||||||||||||