| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20015063 | ALI AKABARPUR URF NAVADA W/s | 20015063/01 | No | No | No | No | No | No | Yes | No | Yes | No | No | Yes | No | Cracks have been observed at multiple locations in the OHT slab and at the slab-ring beam junction. Further, the Rebound Hammer test results of the column are also found to be unsatisfactory. it is recommended that the affected component be dismantled and that necessary rectification/reconstruction work be carried out as per standard specifications. | |||||||||||||
| 2 | 20073477 | BUJHIYA & JHUJHARPUR WSS | 20073477/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | No | No | The OHT column found misaligned above second Tie beam. It is recommended to dismantle the OHT column upto second Tie beam. | |||||||||||||
| 3 | 20014893 | MURCHA Sindhauli W/s | 20014893/01 | No | No | No | No | No | No | Yes | No | Yes | No | No | No | No | Resolved | Resolved | Regarding Quality issue in OHT stair case work | |||||||||||
| 4 | 20024959 | Aurangabad Wss | 20024959/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | Resolved | Regarding Column/beam misalignment below TB-2 | |||||||||||
| 5 | 20057420 | DHULLIYA & JINDPURA WSS | 20057420/01 | No | No | No | No | No | No | Yes | No | Yes | No | No | No | No | Resolved | Resolved | Horizontal creck was found in column no.3 below 2nd tie beam | |||||||||||
| 6 | 20014807 | ISMAILPUR URF NAWADA | 20014807/01 | Yes | No | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | Resolved | Regarding major honeycomb was found in 1st tie beam | |||||||||||
| 7 | 20023928 | Bhagwantpur Wss | 20023928/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | Resolved | Regarding Column/beam misalignment below TB-2 | |||||||||||
| 8 | 20014822 | CHANIURA | 20014822/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | Resolved | Regarding Column/beam misalignment below TB-3 | |||||||||||
| 9 | 20088870 | BARI PRASIDHPUR GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | 20088870/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Regarding OHT raft construction work was done without information. UPV test has been conducted by the TKC in the presence of TPIA. and test was found satisfactory. | ||||||||||||
| 10 | 20056926 | DHAKA & KHAKHRA BUJURG WSS | 20056926/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | Yes | No | Resolved | Resolved | Resolved | Regarding OHT column/beam misalignment above TB-2 | ||||||||||
| 11 | 20026240 | UDAIAPUR | 20026240/01 | Yes | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Resolved | Regarding OHT gallery platform and RB-1 the Bars can be clearly seen i.e. directly exposed to atmosphere. Rectification done as per the SWSM guideline. | |||||||||||
| 12 | 20057091 | JAMUNIA KHANPUR & MUDIGAON & SABALPUR WSS | 20057091/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | No | No | Resolved | Resolved | Regarding column/beam misalignment below OHT slab. | |||||||||||
| 13 | 20097922 | MOHANPUR MAMREJPUR GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | 20097922/01 | No | No | No | No | No | No | Yes | No | Yes | No | No | No | No | Resolved | Resolved | Regarding poor strength is found in OHT structure From GL to Above TB-1 columns as per rebound hammer test. | |||||||||||
| 14 | 20089038 | NARDARA, RAJPOOT URF CHITI GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME | 20089038/01 | No | No | No | No | No | No | Yes | No | Yes | No | No | No | No | Resolved | Resolved | Regarding poor strength is found in OHT structure TB-3 as per rebound hammer test. | |||||||||||
| 15 | 20015828 | KUNIYA NAUABAD | 20015828/01 | No | No | No | No | No | No | Yes | No | Yes | No | No | No | No | Resolved | Resolved | Regarding poor strength is found in OHT structure From GL to TB-1 columns as per rebound hammer test. | |||||||||||
| 16 | 20015539 | Mathana sww | 20015539/01 | No | No | No | Yes | No | No | No | No | Yes | No | No | No | No | Resolved | Resolved | Regarding reinforcement is exposed due to insufficient concrete cover in OHT TB- 1 in between C5 to C6 & C6 to C1 | |||||||||||
| 17 | 20101876 | BINAURA GRAM PANCHAYAT VILLAGE WATER SUPPLY | 20101876/01 | No | No | No | Yes | No | No | No | No | Yes | No | No | No | No | Resolved | Resolved | Regarding reinforcement is exposed due to insufficient concrete cover in OHT columns C1 & C3 below TB-1. | |||||||||||
| 18 | 20084135 | BADSHAHNAGER GRAM PANCHAYAT WATER SUPPLY SCHEME | 20084135/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Regarding casting of staircase flight 1st & 2nd without raised the RFI and OHТ TB-2 & column above tb-2 casting was done without primary Inspection, | ||||||||||||
| 19 | 8361712 | ANWAS DUGAIYA GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME | 8361712/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Regarding major honeycomb was found in OHT raft casting work. | ||||||||||||
| 20 | 20071250 | BHATAURA PRATHVIPUR & TIKMAPUR & VAZEERPUR WSS | 20071250/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | Regarding major honeycomb was found in OHT raft casting work. | ||||||||||||