| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20043840 | Alipur | 20043840/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Poor scaffolding work was done by using poor quality bamboo for OHT construction work. This type of work affect the quality of structure and also it may reason of collapse of structure during execution of work.(poor scaffolding removed from site) | ||||||||||||
| 2 | 20043841 | Baharoli | 20043841/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Lap length has not been maintained by TKC in vertical bars of staircase column of OHT and also its not found in alternate basis as per norms. | ||||||||||||
| 3 | 20043846 | Khadara | 20043846/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Resolved | It has been observed that during visit as per visual inspection first brace beam of staircase not vertically aligned. (dismantling has been done.) | ||||||||||||
| 4 | 20043855 | Umarghana | 20043855/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Vertical steel bars of OHT staircase column at plinth level have been found cut. It is difficult to provide steel bars with proper development length. Take corrective action regarding this issue before starting the further work on OHT staircase at site.(development length has been provided after dismantling of column) | ||||||||||||
| 5 | 20045365 | Sujawalpur & Kansahi | 20045365/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Water has been accumulated over the foundation of OHT. This may cause the uneven settlement of soil below the raft. And also work has been stopped for 3 months.(De watering completed) | ||||||||||||
| 6 | 20061345 | JINDPUR | 20061345/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Overlapping of steel bar has not been given properly. Ref. Approved drawing & IS 456:2000(Reinforcement provided as per drawing) | ||||||||||||
| 7 | 20062599 | AJMATPUR | 20062599/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | The core cutting test of the raft foundation of OHT was done by IIT Kanpur seven months ago and its strength was found to be unsatisfactory. After this, EE sir had instructed to TKC its demolition. The work of its demolition has not been done by TKC till(Old Raft dismantled and new OHT under construction) | ||||||||||||
| 8 | 20062932 | PILKHINI | 20062932/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | The size of the risers and the last flight of stairs has not been done as per the drawing.(After dismantling, reconstruction work done) | ||||||||||||
| 9 | 20067823 | BAIJANI | 20067823/01 | No | No | No | Yes | Yes | No | No | No | No | No | No | No | No | Resolved | 1.Due to clear cover not maintained, steel has clear visible in first flight staircase of OHT after casting. (dismantling has been done.) 2.Casting of Top dome was done without steel checking. RFI was not raised .(recommended for rebar scanning) | ||||||||||||
| 10 | 20067828 | DEVGAON | 20067828/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Many numbers of steel bars of column of OHT has been cut down at plinth level . It is difficult to provide steel bars with proper development length . Take corrective action regarding this .(Recommended dismantling/ Rebaring of steel/ coupling of steel bar.) | |||||||||||||
| 11 | 20068281 | HARIRAMPUR,HARIYAPUR | 20068281/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Resolved | Column has not been found in plumb and the second lift column above 3rd brace seems shifted approx 30mm.(by plumbing verticality check found ok) | ||||||||||||
| 12 | 20068380 | BAKANDHA | 20068380/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Casting starts without performing material testing. As per visual inspection poor quality of sand found at site.(material test report provided ) | ||||||||||||
| 13 | 20068406 | KHATAULI, KORARI | 20068406/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | The foundation and columns of OHT has been submerged in the water. And also work stopped for more than 3 months. Kindly take corrective action regarding this.(Dewatering done.) | ||||||||||||
| 14 | 20074518 | BHOGALPUR | 20074518/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Water logging over OHT foundation(SBC test pending) | |||||||||||||
| 15 | 20074569 | BARKATPUR | 20074569/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Construction work on the OHT has been halted by TKC for over six months following the concreting of its raft foundation; consequently, waterlogging has caused a layer of sand to accumulate over the structure, which could lead to the corrosion of the steel bars used in the OHT. | |||||||||||||
| 16 | 20074573 | MUBARAKPUR,GARIYABICHHIYAWAN | 20074573/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Rain water has been accumulated over the foundation of OHT. Water wills seepage inside the foundation and cause excessive settlement. | |||||||||||||
| 17 | 20075525 | DEVMAI | 20075525/01 | No | Yes | No | No | Yes | No | No | No | Yes | No | No | No | No | 1.Spacing between vertical bars of column are not found equal. And also steel bars are affected by corrosion.(Recommended for column dismantle) 2.Cover not maintained at the time of casting of Column due to which reinforcement of column not aligned in center. Dismantle the column and reconstruct it properly.(Recommended for column dismantle) 3.Column above the plinth beam has been misaligned relative to just below column. Dismantle the column and reconstruct it.(Recommended for column dismantle) | |||||||||||||
| 18 | 20075581 | Souh &Chintapur | 20075581/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Raft of OHT has been constructed without raising/verification of RFI and also material testing was not done.(material test was performed and report provided.) | ||||||||||||
| 19 | 20079007 | IRADATPUR CHATURBHUJPUR | 20079007/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | Yes | No | As per visual inspection it has come to our notice that the Verticality of Over Head Tank does not look in plumb. | |||||||||||||
| 20 | 20079059 | MAWAIYA GUNEER GRAM PANCHAYAT WATER SUPPLY SCHEME | 20079059/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | Yes | No | Horizontal alignment of beams of OHT have not been found properly at site.(Instruction given to change pre cast elements) | |||||||||||||
| 21 | 20079106 | BARHAT | 20079106/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Curing of OHT is not being done properly during inspection.(Curing is going on at the time of OHT under construction) | ||||||||||||
| 22 | 20079137 | BHIKAMPUR AND TENDULI LAKHIPUR GP | 20079137/01 | No | No | No | No | No | Yes | No | No | No | No | No | No | No | Anchor fastener of ZA tank has been exposed after installation due to slab broken by Hilti machine. During water loading condition ZA tank may collapse due to this negligence.(zinc part (Fastener) to be replaced) | |||||||||||||
| 23 | 20081170 | MOHMMDIPUR | 20081170/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | Yes | No | Column above second brace beam was not found in proper vertical alignment.(Instruction given to TKC to dismantle) | |||||||||||||
| 24 | 20081191 | CHHEWKA | 20081191/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | It has been observed that honeycomb has been found in 3rd brace beam of OHT at site. | |||||||||||||
| 25 | 20089204 | SARAYDHARAMPUR | 20089204/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | After binding the bars, the OHT work has stopped for the last one month and due to the OHT trench being filled with water, it is in contact with water, which will affect its quality. (reinforcement replaced before casting work) | ||||||||||||
| 26 | 20089216 | BIJURI | 20089216/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Water logged over the foundation of OHT. Work has been stopped for more than 15 days.(Dewatering has been done ) | ||||||||||||
| 27 | 20089367 | JONIHA | 20089367/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | it has been found that Overlaps are provided in consecutive order in raft foundation of OHT. TKC is requested to provide it in alternate order as per the standard.(Reinforcement provided as per drawing) | ||||||||||||
| 28 | 20095897 | Rasoolpur & Jagatpur | 20095897/01 | No | Yes | No | No | Yes | No | Yes | No | No | No | No | No | No | Resolved | Resolved | Resolved | 1.Tread and riser of OHT has not been made as per drawing and finishing is also not done properly.(After dismantling ,re-constructed of Riser and trade as per drawing specification.) 2.Alignment of 3rd flight of staircase has not been found properly. Dismantle it and reconstruct again in proper alignment.(After dismantling ,re-constructed 3rd flight of staircase as per drawing specification.) 3.Crack has been developed in the 2nd landing of staircase.(After dismantling ,re-constructed 2nd landing of staircase. as per drawing specification.) | ||||||||||
| 29 | 20095909 | SANGRAMPUR,BHAKRANA | 20095909/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Spacing between columns to 1st stirrup has been found 250 mm instead of 100 in foundation ring beam of OHT at site.(Spacing between columns to 1st stirrup has been provided as per drawing) | ||||||||||||
| 30 | 20097251 | SHIVARI | 20097251/01 | No | No | No | No | No | No | Yes | No | Yes | No | No | Yes | No | Crack has been observed in junction point of raft footing and three way column of OHT.(Instruction given to TKC to replace of pre cast elements) | |||||||||||||
| 31 | 20097485 | UMARA | 20097485/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | 4th flight staircase of OHT was not constructed properly as per drawing. | ||||||||||||
| 32 | 20097515 | HASWA | 20097515/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | seepage has been observed at near ring beam bottom dome of over head tank.(epoxy/ water proofing done and hydrotest also perfomed) | ||||||||||||
| 33 | 20097849 | OTI | 20097849/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | The width of tread of OHT staircase has been found 230 mm instead of 250 mm as per approved drawing.(With help motar chipping work) | ||||||||||||
| 34 | 20097920 | TRILOCHANPUR | 20097920/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | Raft foundation cube test result of 7&28 days are not fulfilling the acceptance criteria as per IS 456:2000(NDT test performed. result found satisfactory) | ||||||||||||
| 35 | 20097927 | KHASMAU & BRAMANPUR | 20097927/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Without using 10mm of aggregate 1st lift casting work done of cylindrical wall of OHT. 10mm aggregate not available at site during casting.(performed NDT test ( Report number-RTHPL/2025/6391) | ||||||||||||
| 36 | 20100818 | YOHAN | 20100818/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | As per IS Code- 456:2000, the result of cube samples of 28 days were found to be unsatisfactory. TKC is instructed to do the needful to ascertain the quality of Over Head Tank, so that quality of the same can be maintained.(IIT BHU letter no. CE/PRM/2025-26/1517 DATED-08.07.2025 report result found satisfactory.) | ||||||||||||
| 37 | 20043845 | Kalana | 20043845/01 | No | Yes | No | No | No | No | No | No | Yes | No | No | Yes | No | Resolved | Resolved | Resolved | It has been observed that during site visit column above Ground brace beam of OHT not in proper alignment.( Dismantling has been done) | ||||||||||
| 38 | 20097538 | VIJAYEPUR | 20097538/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Sub standard coarse aggregates have been used for concreting work of top dome of OHT.(provided material test report ) | ||||||||||||
| 39 | 20106717 | DATTAULI GRAM PANCHAYAT WATER SUPPLY SCHEME | 20106717/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | seepage has been observed in bottom dome and conical wall of OHT at site. | |||||||||||||
| 40 | 20099435 | PAHARPUR | 20099435/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | Resolved | 4th lift column of OHT has not been done in proper alignment (dismantling has been done.) | ||||||||||||
| 41 | 20092360 | Gopalpur & Hasanapur | 20092360/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | ||||||||||||||
| 42 | 20079117 | KEWAI | 20079117/01 | No | No | No | No | No | No | No | No | No | No | No | No | No | ||||||||||||||
| 43 | 20067827 | KURUSTI KALA | 20067827/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Steel bars of column have been found cut at the face of column. Steel bar should be left of development length size at the face of column. Dismantle the column and splice the bars as per drawing.(Dismantle the column and splice the bars as per drawing.) | ||||||||||||
| 44 | 20068375 | KESURWA | 20068375/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | Steel bar has been exposed after casting and also it has been observed that honeycomb has been found in 1st brace beam of OHT at site.which is not acceptable as per IS code 456:(2000)clause- 13.3.1(NDT test conducted on dated 16.08.2025. found satisfactory) | ||||||||||||
| 45 | 20075493 | SAMASPUR | 20075493/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Without reinforcement checking and material testing of raft foundation of OHT casting work done at site.(Recommended for Rebar scanning test) | |||||||||||||
| 46 | 20075544 | BAGBADSHAHI | 20075544/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Concrete work of raft foundation of OHT starts without material testing(Material test performed found ok) | ||||||||||||
| 47 | 20089220 | DANDA AMAULI | 20089220/01 | No | No | No | Yes | No | No | No | No | No | No | No | No | No | Resolved | steel bar has been exposed at the junction of beam and column. OHT does not look in plumb. | ||||||||||||
| 48 | 20089230 | SARAKANDI | 20089230/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Bottom dowel bar of OHT staircase at plinth level has been cut. It is difficult to provided steel bar with proper development length. Take corrective action regarding this issue.(rectified with help of electric welding) | ||||||||||||
| 49 | 20095164 | ALLIPUR | 20095164/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Rusted sheet is used in shuttering of bottom slab of OHT. Shuttering oil has not applied over the sheet.(reinforcement is replaced) | ||||||||||||
| 50 | 20095789 | KISHUNPUR KAPILI | 20095789/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | After binding of steel bars the work has been stopped for long time and due to which trench of OHT filled with water. Steel bars have been rusted and also settlement of soil may be occurred.(re inforcement to be replaced ) | ||||||||||||
| 51 | 20097495 | ALAMPUR GAURIYA | 20097495/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Rusted steel bars have been used for the reinforcement of bottom dome of OHT. And also shuttering plate has been observed rusted, Shuttering oil was not applied.(reinforcement replaced) | ||||||||||||
| 52 | 20097520 | KISHUNPUR | 20097520/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | It has been observed that the distribution bars of conical wall and bottom dome of OHT have not been found as per approved drawing. | |||||||||||||
| 53 | 20097544 | RAIPUR BHASRAULI | 20097544/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Rusted steel bars have been used for the reinforcement of OHT raft.(reinforcement of OHT raft bas been replaced) | ||||||||||||
| 54 | 20097720 | AJDUPUR | 20097720/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Rusted steel bar has been used at site.(reinforcement is replaced) | ||||||||||||
| 55 | 20099434 | BARAGAON | 20099434/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Steel bars have been found severely rusted which was left for column above raft.(recommended for reinforcement to be replace) | |||||||||||||