Agency-wise Major/critical Ncs at OHT

S.No. Scheme ID Scheme Name OHT Code Non-Compliance Compliance(Current Status)
Description
Major Honey Comb Alignment Cube Test Exposure Deviation Tank Observation Other SBC Issue Demolish Partially Demolish Fully Under Examination Serious Observation Water Body Compliance Major Honey Comb Compliance Alignment Compliance Cube Test Compliance Exposure Compliance Deviation Compliance Tank Compliance Other Compliance SBC Issue Compliance Demolish Partially Compliance Demolish Fully Compliance Under Examination Compliance Serious Observation Compliance Water Body
1 20097218 Bhawanpur Water Supply Scheme 20097218/01 No Yes No No No No No No No No No No No The alignment of all columns has been found deviated from prior column. Kindly instruct TKC to dismantle all the columns and reconstruct again properly to ensure the structural integrity.
2 20064781 Bahorikpur Water Supply Scheme 20064781/01 Yes No No No No No No No No No No No No Severe crack has been developed at the mid of precast column of OHT. Take corrective action immediately.
3 20032577 Diyawa & Keotali Multi Gram Panchayat Water Supply Scheme 20032577/01 Yes No No No No No No No No No No No No 3rd lift vertical wall of OHT has been found damaged after casting work.
4 20052851 Praanpur Gram Panchayat Water Supply Scheme 20052851/01 No No No No No Yes No No No No No No No Leakage has been occurred from the ZA tank.
5 20067249 Shivpurkhurd Gram Panchayat Water Supply Scheme 20067249/01 No Yes No No No No No No No No No No No Alignment of column has not been observed properly and grouting work was not done properly
6 20053006 Chaukhandpureanti Gram Panchayat 20053006/01 No No No No No No Yes No No No No No No Staircase railing and stand post of the OHT has been found damaged.
7 20052870 Ramaipur Gram Panchayat Water Supply Scheme 20052870/01 No No No No No No Yes No No No No No No The 3 columns of the overhead tank are found 70 mm out from the center. Rectification should be done before casting.
8 20101405 Derhari 20101405/01 No No No No No No Yes No No No No No No Resolved Grouting work was not properly filled between two pre-cast column of OVER HEAD TANK.
9 20063143 LATTARA WATER SUPPLY SCHEME 20063143/01 No No No No No Yes No No No No No No No Resolved It has been observed steel tank Nut bolt fixing work was not found properly
10 20051922 Sekhpur Asik Gram Panchayat Water Supply Scheme 20051922/01 No No No No No Yes No No No No No No No Resolved It has been observed steel tank nut- Bolting fixing work not done properly.
11 20052983 Pure Parmeshwar Gram Panchayat Water Supply Scheme 20052983/01 Yes No No No No No No No No No No No No Resolved Crack has been observed in the staircase column at ground level.
12 20063712 Bhaedpur Water Supply Scheme 20063712/01 No No No Yes No No No No No No No No No Resolved Steel bar has been exposed in the some staircase panel.
13 20023621 BASAULI GRAM PANCHAYAT WATER SUPPLY SCHEME 20023621/01 No No No Yes No No No No No No No No No Resolved Steel has been exposed in the some steps of staircase.
14 20097121 Goi Water supply scheme 20097121/01 No No No Yes No No No No No No No No No Resolved Steel bar has been exposed at the bottom surface of precast slab panel of OVER HEAD TANK.
15 20058368 Belha Gram Panchayat Water Supply Scheme 20058368/01 No No No No No No Yes No No No No No No Resolved Spacing of shear stirrups has not been maintained as per drawing in the column.
16 20026949 PEDARIYA GRAM PANCHAYAT WATER SUPPLY SCHEME 20026949/01 No Yes No No No No Yes No No No No No No Resolved Resolved 1. Shuttering was not done properly for the concreting of OVER HEAD TANK brace beam and column. The alignment of column and brace beam has not been found properly. - 2. Steel bars of column have been getting rusted. Work has been stopped for more than 3 month.
17 20067765 Antamau Gram Panchayat Water Supply Scheme 20067765/01 Yes No No No No No Yes No No No No No No Resolved Resolved 1. Staircase column has been found damaged at the ground level - 2. It has been observed that, OVER HEAD TANK staircase grouting work was not done properly at site.
18 20067027 Lauli Pokhta Khan Water Supply Scheme 20067027/01 Yes Yes No No No No Yes No No No No No No Resolved Resolved Resolved 1 Beam of staircase has been found severely cracked and damaged. Corrective action should be taken immediately - 2. Installation of precast staircase with column has not been done properly. - 3. Staircase grouting work was not done properly between the steps.
19 20067445 Chintamanipur & Andevari Multiple Gram Panchayat Water Supply Scheme 20067445/01 Yes No No Yes No No No No No No No No No Resolved Resolved 1. structural crack observed in OVER HEAD TANK staircase step. - 2. steel bar has been exposed on the top of the precast step of OVER HEAD TANK staircase - 3. Crack has been developed in OVER HEAD TANK staircase step due to stand post installation
20 20063030 MARHA WATER SUPPLY SCHEME 20063030/01 Yes No No Yes No No No No No No No No No Resolved Resolved 1. Steel bar has been exposed at the bottom of OVER HEAD TANK slab. - 2. Crack has been observed in the OVER HEAD TANK staircase column. - 3. Poor concreting work has been observed in the Beam of staircase. Steel bars has been exposed
21 20023634 KOHRAOV GRAM PANCHAYAT WATER SUPPLY SCHEME 20023634/01 No No No No No Yes No No No No No No No Resolved OHT steel tank has been erected out of center line of OHT slab. Due to this uneven pressure distribution may be occurred.
22 20023523 BHADAUSI & RAMPUR PRAAN GRAM PANCHAYAT WATER SUPPLY SCHEME 20023523/01 No Yes No No No No Yes No No No No No No Resolved 1. Precast panels of staircase have not been fixed properly. The alignment of the column after panels fixing has been observed misaligned - 2. Poor concrete casting work was done in the construction of the precast staircase steps. Remove these members from site.
23 20027060 Sangrampur Gram Panchayat Water Supply Scheme 20027060/01 No No No No No No Yes No No No No No No Resolved Expired date cement has been used for construction of OHT column. Cement has been found set also. Kindly dismantle the column as reconstruct it properly.
24 20032389 Pithanapur Gram Panchayat Water Supply Scheme 20032389/01 No No No No No No Yes No No No No No No Resolved Water logging has been occurred inside the OHT Foundation trench.
25 20032443 Jayachandrapur Gram Panchayat Water Supply Scheme 20032443/01 Yes No No No No No No No No No No No No Resolved There is a major crack in the slab beam of the pre-cast overhead tank.
26 20057765 JHINGUR GRAM PANCHYAT WATER SUPPLY SCHEME 20057765/01 No No No No No No Yes No No No No No No Resolved The height of the bottom of the balcony from the top of the bottom ring beam has found 1660 mm. whereas as per drawing it should be 1750 mm.
27 20058077 Dharahra & Dhanepur Mutliple Gram Panchayat Water Supply Scheme 20058077/01 Yes No No No No No No No No No No No No Resolved Precast staircase step has been found cracked.
28 20062726 RAMPUR BELA 20062726/01 Yes No No Yes No No Yes No No No No No No Resolved Resolved Resolved 1. Poor workmanship has been observed in the construction of OVER HEAD TANK staircase. Steel bars have been exposed and severe honeycomb developed. - 2. Steel bars have been exposed at the bottom of staircase and honeycomb developed - 3. Cover was not maintained properly in the precast steps construction as per given in the drawing. Steel bars have been found exposed.
29 20062983 BADSHAHPUR WATER SUPPLY SCHEME 20062983/01 No No Yes No No No No No No No No No No Resolved Cubes has not been sent to the lab for testing, it was found at the site
30 20063003 HARIKHPURA WATER SUPPLY SCHEME 20063003/01 No No No No No No Yes No No No No No No Resolved Grouting work was not carried out properly between the precast members of OHT
31 20067159 Amarpur Gram Panchayat Water Supply Scheme 20067159/01 Yes No No No No No Yes No No No No No No Resolved Resolved 1. cracks have been observed in OVER HEAD TANK column. - 2. The lap length of column steel bar has been found 450 mm. Where as it should have been 600 mm. - 3. Precast steps have not been casted properly in the precast yard. Cover was not provided to the steel bar.
32 20063185 DAFRA WATER SUPPLY SCHEME 20063185/01 No No No No No Yes No No No No No No No Resolved Leakage has been occurred from ZA tank
33 20064076 Ragauli Water Supply Scheme 20064076/01 No No No No No No Yes No No No No No No Resolved Grouting has not been done between the precast steps. Gaps are seen clearly between steps.
34 20064748 Purebhika & raigarh water supply svheme 20064748/01 No No No No No No Yes No No No No No No Resolved Grouting work was not done between two precast column of OHT. Gap has been clearly seen after erection.
35 20066808 Raiypur Gram Panchayat Water Supply Scheme 20066808/01 No No No No No No Yes No No No No No No Resolved The landing beam of the 5th flight staircase of the overhead tank is coming out of column. And the landing beam was not casted during concrete pouring. This is significantly affecting the supporting strength of the staircase. Please fix this.
36 20066939 Rajapur Kala Gram Panchayat Water Supply Scheme 20066939/01 No No No Yes No Yes No No No No No No No Resolved Resolved 1. Steel bars have been exposed at the bottom surface of OHT Slab. It has been cleared that cover block was not provided during placement of steel bars. - 2. Leakage has been found due to some screws not being properly fitted in the ZA cylindrical wall.
37 20067016 Ramgarh Banohi Gram Panchayat Water Supply Scheme 20067016/01 No No No No No Yes No No No No No No No Resolved Leakage has been occurred from the ZA tank
38 20067020 Bhudiyaur Gram Panchayat Water Supply Scheme 20067020/01 Yes No No No No No No No No No No No No Resolved Cracks have been developed at the joint of precast column.
39 20074057 Sarkhailpur water supply scheme 20074057/01 No Yes No No No No No No No No No No No Resolved 1. The formwork of plinth beam has not been found in proper alignment - 2. The horizontal alignment of brace beam has been observed bulged/misaligned.
40 20087376 Kamoliveer Bhanpur Water Supply Scheme 20087376/01 No No No No No No Yes No No No No No No Resolved Water logging has been occurred over the foundation of a pre-cast overhead tank.
41 20089695 Kabirpur Water Supply Scheme 20089695/01 No No No No No Yes No No No No No No No Resolved Leakage has been occurred from the ZA tank.
42 20096957 Dharaulimufrid & Chanduadih Water Supply Scheme 20096957/01 No No No No No No No No No No No No No Water logging has been found at the ground level of OHT. Bamboo scaffolding may be collapsed due to water logging.
43 20096960 Hosiyapur Water Supply Scheme 20096960/01 No No No Yes No No No No No No No No No Resolved Steel bar has been exposed at the bottom surface of OVER HEAD TANK precast slab.
44 20101463 Raigarh Gram Panchayat Water Supply Scheme 20101463/01 No No No No No No Yes No No No No No No Resolved Grouting has not been done properly between the joint of precast columns.