| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 20013485 | Rajamau Water Supply Scheme | 20013485/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | For Violation of safety | ||||||||||||
| 2 | 20099421 | GUWAWAN WATER SUPPLY SCHEME | 20099421/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | |||||||||||||
| 3 | 20033484 | Baghaiya | 20033484/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | NDT test conducted for raft foundation. | ||||||||||||
| 4 | 20013003 | RastaMau Water Supply Scheme | 20013003/01 | No | No | Yes | No | No | No | No | No | No | No | No | No | No | Resolved | NDT test conducted for cylindrical wall. | ||||||||||||
| 5 | 20063093 | Mawai Water Supply Scheme | 20063093/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Raft reinforcement not as per drawing and specifications rectification done in presence of TPIA and UPJN. | ||||||||||||
| 6 | 20013653 | GogaMau Water Supply Scheme | 20013653/01 | No | No | No | No | Yes | No | No | No | No | No | No | No | No | Resolved | Raft reinforcement not as per drawing and specifications reinforcement rectified as per drawing and specifications in presence of TPIA & UPJN. | ||||||||||||
| 7 | 8362201 | PAHAR GANJ | 8362201/01 | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Resolved | |||||||||||||
| 8 | 20099792 | PALIYA WATER SUPPLY SCHEME | 20099792/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | coarse aggregate (10mm & 20mm) not as per specification. Rectification:- Material replaced from the site. | ||||||||||||
| 9 | 8360868 | Naudand | 8360868/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Riser & Tread of staircase not as per drawing & specifications. | ||||||||||||
| 10 | 20095527 | Tulsipur water supply scheme | 20095527/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Alignment of 6th flight of staircase not as per specifications. | ||||||||||||
| 11 | 20066184 | DADRA GP WATER SUPPLY SCHEME | 20066184/01 | No | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | For misalignment of 4th flight of staircase. | ||||||||||||
| 12 | 20076555 | NIYAVA WATER SUPPLY SCHEME | 20076555/01 | No | Yes | No | No | No | No | No | No | No | No | No | No | No | During inspection of the reinforced concrete cylindrical wall of the Overhead Tank (OHT), it was observed that the wall alignment is not as per the approved drawings and specified tolerances. The cylindrical wall was found to be out of plumb/misaligned beyond the permissible limits specified in the relevant codes and project specifications. | |||||||||||||