| S.No. | Scheme ID | Scheme Name | OHT Code | Non-Compliance | Compliance(Current Status) | Description
|
||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Major Honey Comb | Alignment | Cube Test | Exposure | Deviation | Tank Observation | Other | SBC Issue | Demolish Partially | Demolish Fully | Under Examination | Serious Observation | Water Body | Compliance Major Honey Comb | Compliance Alignment | Compliance Cube Test | Compliance Exposure | Compliance Deviation | Compliance Tank | Compliance Other | Compliance SBC Issue | Compliance Demolish Partially | Compliance Demolish Fully | Compliance Under Examination | Compliance Serious Observation | Compliance Water Body | |||||
| 1 | 8152383 | Dhawarra GOV | OHT / 023 /DHUDHAIYA | Yes | Yes | No | No | No | No | Yes | No | No | No | No | No | No | 1. Major honeycombing has been observed in 1st ,2nd and 3rd , lift landing and their tie beam of staircase at Overhead Tank (OHT), indicating poor compaction and workmanship. 2. Deviation in Verticality of column alignment has been observed. 3. Reinforcement is exposed at 5th, 6th & 7 th landing of staircase and between the conical wall and bottom ring beam. 4. Minor leakages occurring from Mechanical installations and Bottom dome. | |||||||||||||
| 2 | 8152383 | Dhawarra GOV | OHT / 008 / DIKWAHA | Yes | No | No | Yes | No | No | Yes | No | No | No | No | No | No | Resolved | 1. Major honeycombing has been observed in 1st ,2nd and 3rd , lift landing and their tie beam of staircase at Overhead Tank (OHT), indicating poor compaction and workmanship. 2. Reinforcement is exposed at 2nd tie beam of staircase and Bottom dome. 3. All DI pipes have been installed without proper clamping/support arrangement also the alignment of DI pipes is not as per the drawings. (Closed Sr. No. 3). | ||||||||||||
| 3 | 8152383 | Dhawarra GOV | OHT / 027 / CHITTARWARA | Yes | No | No | No | No | No | Yes | No | No | No | No | No | No | 1. Major honeycombing and exposed steel has been observed in the ring beam, columns and slab of Overhead Tank (OHT). 2. Leakage has been observed from the bottom dome of tank. (Closed) 3. Voids and exposed steel is observed in the junction point of beam and column of OHT. 4. Crack has been observed in the OHT columns. | |||||||||||||
| 4 | 8152383 | Dhawarra GOV | OHT / 011 / MAHUA BANDH | Yes | Yes | No | Yes | No | No | Yes | No | No | No | No | No | No | 1. Major honeycombing has been observed in certain parts of Overhead Tank (OHT). 2. Misalignment has been observed in the OHT columns. 3. Reinforcement is exposed from the certain parts of OHT. 4. Cracks observed at junction point of column and beam. | |||||||||||||
| 5 | 8152383 | Dhawarra GOV | OHT / 004 / NAGARA DANG | Yes | Yes | No | No | No | No | No | No | No | No | No | No | No | 1. Major honeycomb and reinforcement is exposed in Tie beam, ring beam & bottom dome. 2. Deviation in Verticality of column alignment has been observed. | |||||||||||||
| 6 | 8152383 | Dhawarra GOV | OHT / 030 / SAITHWARA | Yes | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | Resolved | 1. Major honeycomb and reinforcement are exposed in cylindrical wall, ring beam of bottom dome and top dome. 2. Leakage is observed from the container wall and bottom dome of OHT. | |||||||||||
| 7 | 8152383 | Dhawarra GOV | OHT / 005 / BUDHWARA | Yes | Yes | No | No | No | No | Yes | No | No | No | No | No | No | 1. Major honeycombing and exposed steel has been observed in most of the OHT concrete work including ring beam and bottom dome. 2. Verticality of column alignment is observed which is indicating poor compaction and workmanship. 3. Voids has been observed between the conical wall and ring beam of tank. | |||||||||||||
| 8 | 8152383 | Dhawarra GOV | OHT / 017 / ARI | Yes | Yes | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1. Major honeycombing and reinforcement are exposed from the bottom dome & ring beam of OHT. 2. Misalignment has been observed in the OHT columns. 3. Leakage is observed from cylindrical wall and bottom dome of OHT. (Sr. No. 3 Closed) | ||||||||||||
| 9 | 8152383 | Dhawarra GOV | OHT / 025 / NARWARA | Yes | No | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1. Major honeycombing and exposed steel has been observed in most of the OHT concrete work including OHT columns and bottom dome. 2. Continues leakage and seepage is observed at the bottom dome. (Closed Sr. No. 2) | ||||||||||||
| 10 | 8152383 | Dhawarra GOV | ESR-01 | Yes | Yes | No | No | No | No | Yes | No | No | No | No | No | No | 1. Major honeycombing and exposed steel has been observed in balcony near staircase, 5th outer brace and on main ring beam Overhead Tank (OHT). 2. Verticality of column alignment is observed which is indicating poor compaction and workmanship. 3. Cracks has been observed in the junction point of beam and column. 4. Voids has been observed in the conical wall of tank. 5. Leakages spotted has been found in the container wall & bottom dome. | |||||||||||||
| 11 | 8152383 | Dhawarra GOV | OHT / 019 / SWASA MAF | No | Yes | No | No | No | No | Yes | No | No | No | No | No | No | Resolved | 1. Deviation in verticality of columns indicating poor compaction and workmanship. 2. The Leakage has been observed from OHT container. (Closed Sr. No. 2) | ||||||||||||
| 12 | 8152383 | Dhawarra GOV | OHT / 018 / KAITHUARA | Yes | Yes | No | Yes | No | No | No | No | No | No | No | No | No | Major honeycombing & reinforcement is exposed from the OHT slab. | |||||||||||||
| 13 | 8152383 | Dhawarra GOV | OHT / 010 / DHAWARRA | Yes | Yes | No | No | No | No | Yes | No | No | No | No | No | No | 1. Major honeycombing and exposed steel has been observed in most of the OHT concrete work including OHT beams and bottom dome. 2. Leakage has been observed in the OHT. 3. Deviation in verticality of columns indicating poor compaction and workmanship. | |||||||||||||
| 14 | 8152383 | Dhawarra GOV | OHT / 013 / BHANDARA | Yes | No | No | No | No | No | No | No | No | No | No | No | No | Major honeycombing and exposed steel has been observed in certain parts of Overhead Tank (OHT). | |||||||||||||
| 15 | 8152383 | Dhawarra GOV | OHT / 022 / PACH PAHARA | Yes | No | No | No | No | No | Yes | No | No | No | No | No | No | 1.Major Honeycombs has been observed in the certain parts of OHT. 2.Gaps has bene observed at the junction points of beams and column. 3.The tank was found empty during the visit, Live seepage found between junction of RCC tank and Connecting Pipe. | |||||||||||||
| 16 | 8152383 | Dhawarra GOV | OHT / 009 / BILKHI | Yes | Yes | No | Yes | No | No | No | No | No | No | No | No | No | 1.Major honeycombing has been observed in 7th flight and 4th tie beam of staircase at Overhead Tank (OHT), indicating poor compaction and workmanship. 2.Reinforcement is exposed at column above 4th brace and 3rd & 4th brace. 3.Misalignment in verticality of Upper Column lifts for Staircase and OHT. | |||||||||||||
| 17 | 8152383 | Dhawarra GOV | OHT / 014 / ATRAR MAF | Yes | Yes | No | Yes | No | No | Yes | No | No | No | No | No | No | 1.• Honeycomb and Reinforcement is exposed in OHT ring beam, walkway and stairs. 2• Misalignment has been observed in the columns of OHT. 3• Leakage and Seepage is observed at the bottom dome of the OHT. | |||||||||||||
| 18 | 8152383 | Dhawarra GOV | OHT / 015 / DIGARIYA | Yes | Yes | No | Yes | No | No | No | No | No | No | No | No | No | 1• Major honeycombing has been observed in 2nd, 5th ,7th tie beam and Midlanding of staircase at Overhead Tank (OHT), indicating poor compaction and workmanship. 2• Misalignment has been observed in the OHT columns. 3.• Reinforcement is exposed at bottom dome near inlet pipe, balcony near staircase and on main ring beam near inlet pipe. | |||||||||||||
| 19 | 8152383 | Dhawarra GOV | OHT / 007 / BASORA | Yes | Yes | No | Yes | No | No | No | No | No | No | No | No | No | 1• Major honeycombing has been observed in 3rd, 4th brace, Main ring beam, significant Exposed steel and honeycomb conical wall and balcony of Overhead Tank (OHT), indicating poor compaction and workmanship, with significant leakages at bottom dome. 2• Misalignment in columns of tanks and staircase has been observed in the OHT. 3• Reinforcement is exposed at 4th tie beam of staircase and 3rd and 4th Landing of staircase bottom dome near inlet pipe, main ring beam. | |||||||||||||
| 20 | 8152383 | Dhawarra GOV | OHT / 021 / RAHELIA | Yes | Yes | No | No | No | No | Yes | No | No | No | No | No | No | 1.• Major honeycombing has been observed in 1st, 2nd, 3rd ,4th tie beam of staircase at Overhead Tank (OHT). 2• Deviation in verticality of columns indicating poor compaction and workmanship. 3• Voids has been observed in the junctions points of beam and column of OHT. | |||||||||||||
| 21 | 8152383 | Dhawarra GOV | OHT / 006 / TOLA SOYAM | Yes | Yes | No | No | Yes | No | Yes | No | No | No | No | No | No | Resolved | 1.• Major honeycombing has been observed in certain parts of Overhead Tank (OHT). 2• The diameter of columns in the OHT is not uniform across the OHT. 3• Deviation in verticality of columns indicating poor compaction and workmanship.- Closed Drawing submitted. 4• Concrete quality in the OHT is not proper as per the visual inspection carried out. 5• Voids has been observed in the junctions points of beam and column of OHT. | ||||||||||||
| 22 | 8152383 | Dhawarra GOV | OHT / 029 / KAR PAHARIYA | Yes | No | No | Yes | No | No | Yes | No | No | No | No | No | No | 1.Major honeycombing has been observed in certain parts of Overhead Tank (OHT). 2• Reinforcement is exposed at staircase landing of Overhead Tank (OHT). 3• Cracks observed where staircase landing. 4• The Leakage has been observed from OHT container. | |||||||||||||
| 23 | 8152383 | Dhawarra GOV | OHT / 012 / LEVA | Yes | Yes | No | No | No | No | Yes | No | No | No | No | No | No | 1• Major honeycombing has been observed in certain parts of Overhead Tank (OHT). 2• Misalignment has been observed in the OHT columns. 3• Cracks observed at junction point of column and beam. 4• The Leakage has been observed from OHT. | |||||||||||||
| 24 | 8152383 | Dhawarra GOV | OHT / 016 /MUDHARI | Yes | Yes | No | Yes | No | No | No | No | No | No | No | No | No | 1• Major honeycombing has been observed in certain parts of Overhead Tank (OHT). 2• Misalignment has been observed in the OHT columns. 3• Reinforcement is exposed from the certain parts of OHT. | |||||||||||||
| 25 | 8152383 | Dhawarra GOV | OHT / 026 / TIKARIYA PANWARI | Yes | Yes | No | Yes | No | No | No | No | No | No | No | No | No | 1• Major honeycombing has been observed in certain parts of Overhead Tank (OHT). 2• Misalignment has been observed in the OHT columns. 3• Reinforcement is exposed from the certain parts of OHT. | |||||||||||||
| 26 | 8152383 | Dhawarra GOV | OHT / 003 / LUHEDI | No | No | No | No | No | No | No | No | No | No | No | No | No | ||||||||||||||