SNO | District | Agency | Initiated By Agency | Finalized By Agency | Approved By TPI | Approved By EE | Integrate with SWSM Headquarters |
Total | 43 | 35 | 32 | 32 | 39 | ||
1 | Mirzapur | GVPR | 1 | 1 | 1 | 1 | 1 |
Multiurban | 0 | 0 | 0 | 0 | 0 | ||
GA INFRA | 1 | 1 | 1 | 1 | 1 | ||
Megha | 3 | 3 | 3 | 3 | 3 | ||
Ramky baba | 1 | 1 | 1 | 1 | 1 | ||
NCC Ltd. | 2 | 2 | 2 | 2 | 2 | ||
Total | 8 | 8 | 8 | 8 | 8 | ||
2 | Jhansi | Indian Hume Pipe | 1 | 1 | 1 | 1 | 1 |
DARA ENGINEERING | 1 | 1 | 1 | 1 | 1 | ||
BGCCPL-Ramky (JV) | 0 | 0 | 0 | 0 | 0 | ||
NCC Ltd. | 4 | 4 | 3 | 3 | 4 | ||
Unipro | 1 | 1 | 1 | 1 | 1 | ||
Total | 7 | 7 | 6 | 6 | 7 | ||
3 | Banda | Larsen & Toubro Ltd | 1 | 0 | 0 | 0 | 1 |
NCC Ltd. | 1 | 1 | 1 | 1 | 1 | ||
Total | 2 | 1 | 1 | 1 | 2 | ||
4 | Hamirpur | JWIL | 1 | 1 | 1 | 1 | 0 |
PNC-SPML-JV | 1 | 1 | 1 | 1 | 0 | ||
Total | 2 | 2 | 2 | 2 | 0 | ||
5 | Jalaun | BGCCPL-Ramky (JV) | 2 | 0 | 0 | 0 | 0 |
GVPR | 0 | 0 | 0 | 0 | 0 | ||
Total | 2 | 0 | 0 | 0 | 0 | ||
6 | Chitrakoot | GVPR | 0 | 0 | 0 | 0 | 0 |
Larsen & Toubro Ltd | 0 | 0 | 0 | 0 | 2 | ||
Total | 0 | 0 | 0 | 0 | 2 | ||
7 | Lalitpur | Banko Ganga | 1 | 1 | 1 | 1 | 1 |
Brija Banco Pvt. Ltd | 1 | 0 | 0 | 0 | 0 | ||
DARA ENGINEERING | 4 | 3 | 3 | 3 | 5 | ||
JMC-JWIL (JV) | 3 | 3 | 3 | 3 | 3 | ||
M/s Sudhakara Infratech Pvt. Ltd | 5 | 5 | 4 | 4 | 2 | ||
Total | 14 | 12 | 11 | 11 | 11 | ||
8 | Sonbhadra | Jain Const. | 1 | 1 | 1 | 1 | 0 |
GVPR | 0 | 0 | 0 | 0 | 0 | ||
Larsen & Toubro Ltd | 1 | 0 | 0 | 0 | 1 | ||
VPRPL | 1 | 0 | 0 | 0 | 4 | ||
NCC Ltd. | 0 | 0 | 0 | 0 | 0 | ||
Total | 3 | 1 | 1 | 1 | 5 | ||
9 | Mahoba | Larsen & Toubro Ltd | 1 | 1 | 1 | 1 | 1 |
N.K. Gupta & K.B. Gupta Contractors | 1 | 1 | 0 | 0 | 1 | ||
SLC-SMC (JV) | 1 | 0 | 0 | 0 | 0 | ||
JMC-JWIL (JV) | 2 | 2 | 2 | 2 | 2 | ||
Total | 5 | 4 | 3 | 3 | 4 |