Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in
S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Raebareli 20086508 KAND RAWAN G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) NEW RETROFIT Jal Nigam YES NO NO 3160.70 171.46 171.46 0.00 2989.24 3160.70 Under Construction 50.00 Physical progress stands at 50.0% against financial progress of 7%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1501 / W-11 / 51, dated 14.07.2026) and a final notice (Letter No. 1670 / W-11 / 65, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1825 / W-11 / 66, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1237 / WG-05 / 1