S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Raebareli 20084310 RAMKHERA GROUP OF VILLEGAES NEW RETROFIT Jal Nigam YES NO NO 666.70 34.15 34.15 0.00 632.55 666.70 Under Construction 67.00 Physical progress stands at 67.0% against financial progress of 7%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1502 / W-11 / 52, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
2 Raebareli 20084337 NERTHUWA GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 1922.61 291.35 291.35 0.00 1631.26 1922.61 Under Construction 57.00 Physical progress stands at 57.0% against financial progress of 20%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1498 / W-11 / 48, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
3 Raebareli 20084389 MIRAZAPUR AIHARI G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) NEW RETROFIT Jal Nigam YES NO NO 1335.05 306.25 306.25 0.00 1028.80 1335.05 Under Construction 74.00 Physical progress stands at 74.0% against financial progress of 28%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1500 / W-11 / 50, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
4 Raebareli 20084402 Ambara Paschim G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 2077.32 355.95 355.95 0.00 1721.37 2077.32 Under Construction 57.00 Physical progress stands at 57.0% against financial progress of 20%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1499 / W-11 / 49, dated 14.07.2027). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
5 Raebareli 20084435 Neemtikar Group of Villages NEW RETROFIT Jal Nigam YES NO NO 1596.90 217.62 217.62 0.00 1379.28 1596.90 Under Construction 58.00 Physical progress stands at 58.0% against financial progress of 17%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1501 / W-11 / 51, dated 14.07.2026) and a final notice (Letter No. 1669 / W-11 / 64, dated 29/07/2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
6 Raebareli 20084452 Govindpur G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 1621.23 720.43 720.43 0.00 900.80 1621.23 Under Construction 73.00 Physical progress stands at 73% against financial progress of 56%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
7 Raebareli 20084527 THULANDI Water Supply NEW RETROFIT Jal Nigam YES NO NO 1575.16 144.23 144.23 0.00 1430.93 1575.16 Under Construction 56.00 Physical progress stands at 56.0% against financial progress of 12%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1501 / W-11 / 51, dated 14.07.2026) and a final notice (Letter No. 1668 / W-11 / 63, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1818 / W-11 / 61, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1236 / WG-05 /
8 Raebareli 20084571 SEHGON PASHCHIM Water Supply NEW RETROFIT Jal Nigam YES NO NO 784.18 151.18 151.18 0.00 633.00 784.18 Under Construction 67.00 Physical progress stands at 67.0% against financial progress of 24%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1501 / W-11 / 51, dated 14.07.2026) and a final notice (Letter No. 1669 / W-11 / 64, dated 29/07/2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
9 Raebareli 20085447 BALA GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 1577.47 109.72 109.72 0.00 1467.75 1577.47 Under Construction 58.00 Physical progress stands at 58.0% against financial progress of 9%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1501 / W-11 / 51, dated 14.07.2026) and a final notice (Letter No. 1668 / W-11 / 63, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1818 / W-11 / 61, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1236 / WG-05 / 1
10 Raebareli 20085495 Pahuri G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 746.78 155.04 155.04 0.00 591.74 746.78 Under Construction 52.00 Physical progress stands at 52.0% against financial progress of 26%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1499 / W-11 / 49, dated 14.07.2027). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
11 Raebareli 20085544 AIHAR GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 2004.50 180.84 180.84 0.00 1823.66 2004.50 Under Construction 61.00 Physical progress stands at 61.0% against financial progress of 12%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1501 / W-11 / 51, dated 14.07.2026) and a final notice (Letter No. 1667 / W-11 / 62, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1804 / W-11 / 60, dated 11/08/2026) and imposed 1% Liquidated Damages (Letter No. 1205 / WG-05 /
12 Raebareli 20085566 MAJHIGAWAN G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) NEW RETROFIT Jal Nigam YES NO NO 1140.00 72.12 72.12 0.00 1067.88 1140.00 Under Construction 53.00 Physical progress stands at 53.0% against financial progress of 8%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1501 / W-11 / 51, dated 14.07.2026) and a final notice (Letter No. 1667 / W-11 / 62, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1804 / W-11 / 60, dated 11/08/2026) and imposed 1% Liquidated Damages (Letter No. 1205 / WG-05 / 1
13 Raebareli 20085622 PASCHIM GAON GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 980.70 277.15 277.15 0.00 703.55 980.70 Under Construction 72.00 Physical progress stands at 72.0% against financial progress of 34%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1495 / W-11 / 45, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
14 Raebareli 20085997 BARAMJITPUR URF KHWATA G.O.V. NEW RETROFIT Jal Nigam YES NO NO 959.00 57.34 57.34 0.00 901.66 959.00 Under Construction 58.00 Physical progress stands at 58.0% against financial progress of 8%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1489 / W-11 / 39, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
15 Raebareli 20086021 Ichauli Water Supply NEW RETROFIT Jal Nigam YES NO NO 1065.37 185.84 185.84 0.00 879.53 1065.37 Under Construction 65.00 Physical progress stands at 65.0% against financial progress of 23%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1498 / W-11 / 48, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
16 Raebareli 20086029 RAGHOPUR Water Supply NEW RETROFIT Jal Nigam YES NO NO 740.17 67.10 67.10 0.00 673.07 740.17 Under Construction 68.00 Physical progress stands at 68.0% against financial progress of 13%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1501 / W-11 / 51, dated 14.07.2026) and a final notice (Letter No. 1669 / W-11 / 64, dated 29/07/2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
17 Raebareli 20086068 JOHWAHISAR GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 1522.06 121.21 121.21 0.00 1400.85 1522.06 Under Construction 53.00 Physical progress stands at 53.0% against financial progress of 8%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1496 / W-11 / 46, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
18 Raebareli 20086102 Meethapur G.O.V water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 261.37 50.95 50.95 0.00 210.42 261.37 Under Construction 53.00 Physical progress stands at 53.0% against financial progress of 22%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1499 / W-11 / 49, dated 14.07.2027). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
19 Raebareli 20086123 SB Kheda G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 502.01 55.94 55.94 0.00 446.07 502.01 Under Construction 55.00 Physical progress stands at 55.0% against financial progress of 14%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1502 / W-11 / 52, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
20 Raebareli 20086519 LODIPUR UTRAUWA GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 2346.99 256.39 256.39 0.00 2090.60 2346.99 Under Construction 58.00 Physical progress stands at 58.0% against financial progress of 29%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1497 / W-11 / 47, dated 14.07.2026) and a final notice (Letter No. 1663 / W-11 / 58, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1821 / W-11 / 63, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1238 / WG-05 /
21 Raebareli 20086638 BHAON GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 3679.68 921.65 921.65 0.00 2758.03 3679.68 Under Construction 58.00 Physical progress stands at 58.0% against financial progress of 29%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1491 / W-11 / 41, dated 14.07.2026) and a final notice (Letter No. 1666 / W-11 / 61, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1820 / W-11 / 62, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1241 / WG-05 /
22 Raebareli 20086653 MON WATER SUPPLY NEW RETROFIT Jal Nigam YES NO NO 3603.60 611.66 611.66 0.00 2991.94 3603.60 Under Construction 54.00 Physical progress stands at 54.0% against financial progress of 22%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1497 / W-11 / 47, dated 14.07.2026) and a final notice (Letter No. 1664 / W-11 / 59, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1822 / W-11 / 64, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1239 / WG-05 /
23 Raebareli 20086676 GHURWARA GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 2296.30 471.80 471.80 0.00 1824.50 2296.30 Under Construction 69.00 Physical progress stands at 69.0% against financial progress of 28%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1490 / W-11 / 40, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
24 Raebareli 20086769 Bannamau G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 2826.62 362.36 362.36 0.00 2464.26 2826.62 Under Construction 54.00 Physical progress stands at 54.0% against financial progress of 17%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1493 / W-11 / 43, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
25 Raebareli 20094863 HARCHANDPUR GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 1158.50 61.06 61.06 0.00 1097.44 1158.50 Under Construction 61.00 Physical progress stands at 61.0% against financial progress of 7%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1496 / W-11 / 46, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
26 Raebareli 20095086 FIROJPUR G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) NEW RETROFIT Jal Nigam YES NO NO 612.00 35.66 35.66 0.00 576.34 612.00 Under Construction 52.00 Physical progress stands at 52.0% against financial progress of 08%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1502 / W-11 / 52, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
27 Raebareli 20095087 Itaura Bujurg Retrofitting water supply scheme OLD RETROFIT Jal Nigam YES NO NO 195.69 73.83 73.83 0.00 121.86 195.69 Under Construction 55.00 We will complete this scheme in this month
28 Raebareli 20095091 Jagatpur retrofitting water supply scheme OLD RETROFIT Jal Nigam YES NO NO 234.22 58.78 58.78 0.00 175.44 234.22 Under Construction 51.00 We had imposed Ld on main scheme CB. Contractor is same for retrofitting scheme.
29 Raebareli 20095094 DEEH (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 3529.83 815.09 815.09 0.00 2714.74 3529.83 Under Construction 57.00 Physical progress stands at 57.0% against financial progress of 28%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1491 / W-11 / 41, dated 14.07.2026) and a final notice (Letter No. 1665 / W-11 / 60, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1826 / W-11 / 67, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1242 / WG-05 /
30 Raebareli 20095120 ASRAFPUR (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 1909.90 234.57 234.57 0.00 1675.33 1909.90 Under Construction 54.00 Physical progress stands at 54.0% against financial progress of 15%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1499 / W-11 / 49, dated 14.07.2026). We have recommended 1% Liquidated Damages (Letter No. 1855 / W-11 / 70, dated 14/08/2026) and imposed 1% Liquidated Damages (Letter No. 1235 / WG-05 / 163, dated 20/08/2026). Unless significant progress is demonstrated
31 Raebareli 20095128 KUNWAR MAU (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 1016.91 66.75 66.75 0.00 950.16 1016.91 Under Construction 57.00 Physical progress stands at 57.0% against financial progress of 9%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1497 / W-11 / 47, dated 14.07.2026) and a final notice (Letter No. 1662 / W-11 / 57, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1824 / W-11 / 65, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1240 / WG-05 / 1
32 Raebareli 20095374 SANDAHA (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 648.09 206.19 206.19 0.00 441.90 648.09 Under Construction 53.00 Physical progress stands at 53.0% against financial progress of 38%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1500 / W-11 / 50, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
33 Raebareli 20095377 NINAWAN (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 882.16 117.99 117.99 0.00 764.17 882.16 Under Construction 53.00 Physical progress stands at 53.0% against financial progress of 16%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1499 / W-11 / 49, dated 14.07.2026). We have recommended 1% Liquidated Damages (Letter No. 1855 / W-11 / 70, dated 14/08/2026) and imposed 1% Liquidated Damages (Letter No. 1235 / WG-05 / 163, dated 20/08/2026). Unless significant progress is demonstrated
34 Raebareli 20095392 ASHA RASIDPUR (REORGANIZATION) GROUP OF GRAM PANCHAYATS WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 1926.67 123.95 123.95 0.00 1802.72 1926.67 Under Construction 54.00 Physical progress stands at 54.0% against financial progress of 9%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1497 / W-11 / 47, dated 14.07.2026) and a final notice (Letter No. 1662 / W-11 / 57, dated 29/07/2026). We have recommended 1% Liquidated Damages (Letter No. 1824 / W-11 / 65, dated 12/08/2026) and imposed 1% Liquidated Damages (Letter No. 1240 / WG-05 / 1