S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Raebareli 7201390 ITAURA BUJURG PWS NRDWP Jal Nigam YES NO NO 794.36 671.30 671.30 0.00 123.06 794.36 Under Construction 95.00 In Zone 2, the Overhead Tank (OHT) has been constructed up to the staging level. The contractor has stopped work. We have imposed 10% liquidated damages (LD) against the contract bond (CB). We have now issued a final notice via Letter No. 2044/W-3/55, dated 31/08/2026, directing the contractor to resume work; otherwise, we will be forced to forfeit the securities and terminate the contract bond (CB)
2 Raebareli 7208594 JAGATPUR PWS SCHEME(SAGY) NRDWP Jal Nigam YES NO NO 2461.16 1812.68 1812.68 0.00 648.48 2461.16 Under Construction 95.00 The contractor has not been working due to unavailability of funds since March 2024. We have also imposed a 5% liquidated damages (LD) against the contract bond (CB). If progress does not increase this week, we will impose an additional 5% LD and provide 1 more week for the contractor to resume work at the required pace. If the situation remains the same, we will proceed to forfeit the securities and terminate the contract bond (CB). For the remaining works, we will float a short-term tender.
3 Raebareli 20085243 PAKHRAULI GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 953.40 214.52 214.52 0.00 738.88 953.40 Under Construction 78.00 Physical progress stands at 78.0% against financial progress of 34%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1489 / W-11 / 39, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
4 Raebareli 20085429 BEHATA KALAN GROUP OF VILLAGES NEW RETROFIT Jal Nigam YES NO NO 1701.01 337.26 337.26 0.00 1363.75 1701.01 Under Construction 81.00 Physical progress stands at 81.0% against financial progress of 25%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1495 / W-11 / 45, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
5 Raebareli 20085473 KAMALPUR G.O.V. REORGANIZATION WATER SUPPLY SCHEME (SOLAR) NEW RETROFIT Jal Nigam YES NO NO 952.96 145.57 145.57 0.00 807.39 952.96 Under Construction 83.00 Physical progress stands at 83.0% against financial progress of 19%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1500 / W-11 / 50, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
6 Raebareli 20086724 BHojpur G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 3616.33 419.09 419.09 0.00 3197.24 3616.33 Under Construction 87.00 Physical progress stands at 87.0% against financial progress of 15%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1492 / W-11 / 42, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
7 Raebareli 20095382 Ralpur G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 1480.00 659.97 659.97 0.00 820.03 1480.00 Under Construction 81.00 Physical progress stands at 81% against financial progress of 56%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.
8 Raebareli 20095385 Sareni G.O.V Reorganisational water Supply Scheme (Solar) NEW RETROFIT Jal Nigam YES NO NO 1296.10 140.02 140.02 0.00 1156.08 1296.10 Under Construction 87.00 Physical progress stands at 87% against financial progress of 13%. Due to non-availability of funds in the scheme since October 2024, work is progressing at a significantly slower pace than planned. We have issued a warning letter (Letter No. 1502 / W-11 / 52, dated 14.07.2026). Unless significant progress is demonstrated in the coming week, further action including forfeiture of securities will be initiated.