S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Lalitpur 20089022 PURA KALAN VILLAGE WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 290.00 0.00 0.00 0.00 290.00 290.00 Under Construction 60.00 In Poorakalan Scheme, there is 1 village with 22 habitations proposed to be covered. Out of the 17 km distribution pipeline proposed, 9 km has been laid and 8 km is still pending. Testing work is also pending. Out of the target of 1,500 FHTCs, 600 have been completed and approximately 900 FHTCs are still pending.
2 Lalitpur 20094881 MATHURADANG GOV WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 955.24 114.66 114.66 0.00 840.58 955.24 Under Construction 60.00 In Mathuradang Scheme, the plant is currently operational and covers 24 villages, out of which 19 villages are presently receiving water supply. Approximately 8 km of distribution pipeline laying is still pending. Out of 8,000 proposed FHTCs, only 1,500 have been completed and around 6,500 are still pending. Under electrical works, motor installation and installation of the vertical turbine (VT) pump at the C.P. tank are pending.
3 Lalitpur 20094959 BAR REORGNAIZATION WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 923.00 407.82 407.82 0.00 515.18 923.00 Under Construction 70.00 In Bar Scheme, out of the total 27 km distribution pipeline along with 5 MLD capacity, 17 km of distribution pipeline work is still pending. The 9.7 km raising main has been completed, with only interconnection work remaining. The scheme includes one tank, which has been completed 100%. Out of 2,000 proposed FHTCs, only 500 have been completed and the remaining 1,500 FHTCs are still pending.
4 Lalitpur 20099699 LAKHANGER VILLAGE WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 69.99 0.30 0.30 0.00 69.70 69.99 Under Construction 30.00 In Lakhnjar Scheme, there are 4 solar dual-pump systems, all of which have been procured but their installation is still pending. All 4 proposed borewells have been completed.
5 Lalitpur 20099714 JAITUPURA VILLAGE WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 68.30 6.56 6.56 0.00 61.74 68.30 Under Construction 70.00 In Jaitpura Scheme, the one proposed borewell has been completed. The pump lowering and solar installation are still pending. The pump house has been constructed. Out of the 60 proposed FHTCs, all 60 are still pending.
6 Lalitpur 20099746 BADWAR VILLAGE WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 89.29 19.24 19.24 0.00 70.05 89.29 Under Construction 80.00 In Badwar Scheme, out of the total 4.50 km distribution pipeline, 3.00 km laying work has been completed and 1.50 km is pending. Testing work is 100% pending, and all 192 FHTCs are yet to be completed. The pump house civil work has been completed; however, motor installation and solar installation are pending. All 03 proposed borewells have been completed, while pipe lowering work has also been completed.
7 Lalitpur 20099749 KURRAT VILLAGE WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 135.10 18.40 18.40 0.00 116.70 135.10 Under Construction 85.00 In Kurrat Scheme, the tank structure has been completed, while painting work is pending. The entire 400 m raising main is still pending. Out of two pump houses, one has been completed and is functional, while the second pump house is under progress. Out of 200 proposed FHTCs, 150 have been completed and 50 are still pending.
8 Lalitpur 20102391 PAPRO VILLAGE WATER SUPPLY SCHEME NEW RETROFIT Jal Nigam YES NO NO 21.18 0.00 0.00 0.00 21.18 21.18 Under Construction 40.00 In Parpo, the single-village solar dual-pump scheme, the one proposed borewell has been completed. However, installation of the solar dual-pump system, 400 m of distribution pipeline and 22 FHTC connections is still pending, although the required material has been received at site.
9 Lalitpur 20103935 Bansi Harshpur GOV water supply Scheme(Retrofitting) NEW RETROFIT Jal Nigam YES NO NO 1335.08 327.10 327.10 0.00 1007.98 1335.08 Under Construction 70.00 In Bansi Scheme, covering 19 villages, one new tank has been constructed, in which painting and flooring work is still pending. The distribution pipeline work has been completed. Approximately 2,000 FHTCs are pending across all 19 villages, out of which around 1,500 FHTCs are to be completed in Major Harshur village. At Jamalpur CWR pumping plant, installation of a 10 HP motor is the only remaining work.