| 1 |
Lalitpur |
20089022 |
PURA KALAN VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
290.00 |
0.00 |
0.00 |
0.00 |
290.00 |
290.00 |
Under Construction |
60.00 |
In Poorakalan Scheme, there is 1 village with 22 habitations proposed to be covered. Out of the 17 km distribution pipeline proposed, 9 km has been laid and 8 km is still pending. Testing work is also pending. Out of the target of 1,500 FHTCs, 600 have been completed and approximately 900 FHTCs are still pending. |
| 2 |
Lalitpur |
20094881 |
MATHURADANG GOV WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
955.24 |
114.66 |
114.66 |
0.00 |
840.58 |
955.24 |
Under Construction |
60.00 |
In Mathuradang Scheme, the plant is currently operational and covers 24 villages, out of which 19 villages are presently receiving water supply. Approximately 8 km of distribution pipeline laying is still pending. Out of 8,000 proposed FHTCs, only 1,500 have been completed and around 6,500 are still pending. Under electrical works, motor installation and installation of the vertical turbine (VT) pump at the C.P. tank are pending. |
| 3 |
Lalitpur |
20094959 |
BAR REORGNAIZATION WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
923.00 |
407.82 |
407.82 |
0.00 |
515.18 |
923.00 |
Under Construction |
70.00 |
In Bar Scheme, out of the total 27 km distribution pipeline along with 5 MLD capacity, 17 km of distribution pipeline work is still pending. The 9.7 km raising main has been completed, with only interconnection work remaining. The scheme includes one tank, which has been completed 100%. Out of 2,000 proposed FHTCs, only 500 have been completed and the remaining 1,500 FHTCs are still pending. |
| 4 |
Lalitpur |
20099699 |
LAKHANGER VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
69.99 |
0.30 |
0.30 |
0.00 |
69.70 |
69.99 |
Under Construction |
30.00 |
In Lakhnjar Scheme, there are 4 solar dual-pump systems, all of which have been procured but their installation is still pending. All 4 proposed borewells have been completed. |
| 5 |
Lalitpur |
20099714 |
JAITUPURA VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
68.30 |
6.56 |
6.56 |
0.00 |
61.74 |
68.30 |
Under Construction |
70.00 |
In Jaitpura Scheme, the one proposed borewell has been completed. The pump lowering and solar installation are still pending. The pump house has been constructed. Out of the 60 proposed FHTCs, all 60 are still pending. |
| 6 |
Lalitpur |
20099746 |
BADWAR VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
89.29 |
19.24 |
19.24 |
0.00 |
70.05 |
89.29 |
Under Construction |
80.00 |
In Badwar Scheme, out of the total 4.50 km distribution pipeline, 3.00 km laying work has been completed and 1.50 km is pending. Testing work is 100% pending, and all 192 FHTCs are yet to be completed. The pump house civil work has been completed; however, motor installation and solar installation are pending. All 03 proposed borewells have been completed, while pipe lowering work has also been completed. |
| 7 |
Lalitpur |
20099749 |
KURRAT VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
135.10 |
18.40 |
18.40 |
0.00 |
116.70 |
135.10 |
Under Construction |
85.00 |
In Kurrat Scheme, the tank structure has been completed, while painting work is pending. The entire 400 m raising main is still pending. Out of two pump houses, one has been completed and is functional, while the second pump house is under progress. Out of 200 proposed FHTCs, 150 have been completed and 50 are still pending. |
| 8 |
Lalitpur |
20102391 |
PAPRO VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
21.18 |
0.00 |
0.00 |
0.00 |
21.18 |
21.18 |
Under Construction |
40.00 |
In Parpo, the single-village solar dual-pump scheme, the one proposed borewell has been completed. However, installation of the solar dual-pump system, 400 m of distribution pipeline and 22 FHTC connections is still pending, although the required material has been received at site. |
| 9 |
Lalitpur |
20103935 |
Bansi Harshpur GOV water supply Scheme(Retrofitting) |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
1335.08 |
327.10 |
327.10 |
0.00 |
1007.98 |
1335.08 |
Under Construction |
70.00 |
In Bansi Scheme, covering 19 villages, one new tank has been constructed, in which painting and flooring work is still pending. The distribution pipeline work has been completed. Approximately 2,000 FHTCs are pending across all 19 villages, out of which around 1,500 FHTCs are to be completed in Major Harshur village. At Jamalpur CWR pumping plant, installation of a 10 HP motor is the only remaining work.
|