| S.No. | District | Scheme ID | Scheme Name | Program Name | Department | PWS Exist | Physical Completion | Financial Completion | Work Cost | Released Cost | Expenditure Cost | Liability | Balance Fund | Final Cost | Scheme Status | Physical Progress(%) | Remark |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lalitpur | 20099699 | LAKHANGER VILLAGE WATER SUPPLY SCHEME | NEW RETROFIT | Jal Nigam | YES | NO | NO | 69.99 | 0.30 | 0.30 | 0.00 | 69.70 | 69.99 | Under Construction | 30.00 | |
| 2 | Lalitpur | 20099707 | THANGANA BANDWA VILLAGE WATER SUPLLY SHEME | NEW RETROFIT | Jal Nigam | YES | NO | NO | 95.00 | 3.68 | 3.68 | 0.00 | 91.32 | 95.00 | Under Construction | 30.00 | |
| 3 | Lalitpur | 20102391 | PAPRO VILLAGE WATER SUPPLY SCHEME | NEW RETROFIT | Jal Nigam | YES | NO | NO | 21.18 | 0.00 | 0.00 | 0.00 | 21.18 | 21.18 | Under Construction | 40.00 |