| 1 |
Lalitpur |
20099746 |
BADWAR VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
89.29 |
19.24 |
19.24 |
0.00 |
70.05 |
89.29 |
Under Construction |
80.00 |
In Badwar Scheme, out of the total 4.50 km distribution pipeline, 3.00 km laying work has been completed and 1.50 km is pending. Testing work is 100% pending, and all 192 FHTCs are yet to be completed. The pump house civil work has been completed; however, motor installation and solar installation are pending. All 03 proposed borewells have been completed, while pipe lowering work has also been completed. |
| 2 |
Lalitpur |
20099749 |
KURRAT VILLAGE WATER SUPPLY SCHEME |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
135.10 |
18.40 |
18.40 |
0.00 |
116.70 |
135.10 |
Under Construction |
85.00 |
In Kurrat Scheme, the tank structure has been completed, while painting work is pending. The entire 400 m raising main is still pending. Out of two pump houses, one has been completed and is functional, while the second pump house is under progress. Out of 200 proposed FHTCs, 150 have been completed and 50 are still pending. |