| 1 |
Prayagraj |
8130884 |
Vitthalpur Village Water Supply Scheme |
QPV |
Jal Nigam |
YES |
NO |
NO |
153.00 |
0.00 |
0.00 |
0.00 |
153.00 |
153.00 |
Under Construction |
70.00 |
Work progress in this Scheme. The following works are pending :- 10% Pump House Work, 0.5 KM distribution Line, 1 New OHT, 13 House Connection and 1 New Electricity Connection. This Scheme Will be Functional from Oct,26 but Due to OHT work scheme will be Complete in Dec,26. |
| 2 |
Prayagraj |
8130887 |
Kumbhauna Village Water Supply Scheme |
QPV |
Jal Nigam |
YES |
NO |
NO |
136.90 |
0.00 |
0.00 |
0.00 |
136.90 |
136.90 |
Under Construction |
65.00 |
Work progress in this Scheme. The following works are pending :- 10% Pump House Work, 4.35 KM distribution Line, 1 New OHT, 177 House Connection and 1 New Electricity Connection. This Scheme Will be Functional from Oct,26 but Due to OHT work scheme will be Complete in Dec,26. |