| 1 |
Sultanpur |
8132007 |
LAUHAR DAXIN W/S SCHEME |
JJM (JAL NIGAM SCHEMES) |
Jal Nigam |
YES |
NO |
NO |
452.75 |
166.18 |
166.18 |
0.00 |
286.57 |
452.75 |
Under Construction |
88.00 |
Tubewells: 2 Nos. – Completed.
Pumping Plants: 1 No. – Installation completed. However, the servo stabilizer is not functioning properly. The stabilizer needs to be inspected and properly configured by the Servocon engineer. After successful setting and testing of the stabilizer,1 No. pumping plant will be commissioned.
Pump Houses: 2 Nos.
Pump House 1: Civil work completed; painting is pending.
Pump House 2: Civil structure completed; door and window installation, electrification, and painting |