| 1 |
Bahraich |
7624357 |
Kandara PWS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
128.54 |
88.54 |
88.54 |
0.00 |
40.00 |
128.54 |
Under Construction |
70.00 |
"The project remains incomplete because the land is disputed and the High Court has ruled in favour of the farmer. Under the scheme, the tank, boring, works are finished. The Tehsil is now processing the allocation of another plot of land to the farmer in exchange." |
| 2 |
Bahraich |
8130812 |
PATHARKALA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
181.48 |
72.73 |
72.73 |
0.00 |
108.75 |
181.48 |
Under Construction |
85.00 |
The construction of the scheme's tank is in progress, and concreting of the top dome is currently completed. The target to complete the OHT work is 20th October, and the entire scheme is targeted for completion by 30th October. and the water supply will be started with in 10 days. |