| 1 |
Bahraich |
7624357 |
Kandara PWS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
128.54 |
88.54 |
88.54 |
0.00 |
40.00 |
128.54 |
Under Construction |
60.00 |
"The project remains incomplete because the land is disputed and the High Court has ruled in favour of the farmer. Under the scheme, the tank, boring, works are finished. The Tehsil is now processing the allocation of another plot of land to the farmer in exchange." |
| 2 |
Bahraich |
8130812 |
PATHARKALA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
181.48 |
72.73 |
72.73 |
0.00 |
108.75 |
181.48 |
Under Construction |
76.00 |
The construction of the scheme's tank is in progress, and the shuttering work for the top dome is currently underway. The target to complete the OHT work is 15th October, and the entire scheme is targeted for completion by 30th October. Due to limited space in the campus, the solar installation cannot be done at the moment. After the OHT work is completed, the solar panels will be installed, and the water supply will be started. |