| S.No. | District | Scheme ID | Scheme Name | Program Name | Department | PWS Exist | Physical Completion | Financial Completion | Work Cost | Released Cost | Expenditure Cost | Liability | Balance Fund | Final Cost | Scheme Status | Physical Progress(%) | Remark |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | 7624357 | Kandara PWS | NRDWP | Jal Nigam | YES | NO | NO | 128.54 | 88.54 | 88.54 | 0.00 | 40.00 | 128.54 | Under Construction | 60.00 | "The project remains incomplete because the land is disputed and the High Court has ruled in favour of the farmer. Under the scheme, the tank, boring, works are finished. The Tehsil is now processing the allocation of another plot of land to the farmer in exchange." |