S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Bahraich 8130812 PATHARKALA NRDWP Jal Nigam YES NO NO 181.48 72.73 72.73 0.00 108.75 181.48 Under Construction 76.00 The construction of the scheme's tank is in progress, and the shuttering work for the top dome is currently underway. The target to complete the OHT work is 15th October, and the entire scheme is targeted for completion by 30th October. Due to limited space in the campus, the solar installation cannot be done at the moment. After the OHT work is completed, the solar panels will be installed, and the water supply will be started.