| 1 |
Bahraich |
8130812 |
PATHARKALA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
181.48 |
72.73 |
72.73 |
0.00 |
108.75 |
181.48 |
Under Construction |
76.00 |
The construction of the scheme's tank is in progress, and the shuttering work for the top dome is currently underway. The target to complete the OHT work is 15th October, and the entire scheme is targeted for completion by 30th October. Due to limited space in the campus, the solar installation cannot be done at the moment. After the OHT work is completed, the solar panels will be installed, and the water supply will be started. |