| 1 |
Basti |
7893806 |
Dewami GOV AES JE Schemes |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
277.32 |
125.72 |
125.72 |
0.00 |
151.60 |
277.32 |
Under Construction |
76.00 |
1. Work started by firm, after notice for tender cancellation. 2. Rising Main Work In Progress. 3. Firm is trying to arrange 200 mm Dia DI-K-7 200 pipe.
|
| 2 |
Basti |
8126991 |
Unji Mustakam PWS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
285.57 |
53.84 |
53.84 |
0.00 |
231.73 |
285.57 |
Under Construction |
76.00 |
1. Work started by firm, after notice for tender cancellation. 2. Pipe laying work In Progress. 3. Power connection is work in progress.
4. 34.52 Lacs bill uploaded on portal |
| 3 |
Basti |
8178790 |
MAHADEWA GOV W/S (RETROFITTING) |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
111.82 |
24.16 |
24.16 |
0.00 |
87.66 |
111.82 |
Under Construction |
76.00 |
1. Due to land issue (Court Case) OHT work could not be started. 2. OHT construction in progress on 2nd Land.
3. 30.6 Lacs bill uploaded on portal |
| 4 |
Basti |
8180316 |
Gotwa G.P. w/s Scheme (Retrofitting) |
OLD RETROFIT |
Jal Nigam |
YES |
NO |
NO |
69.11 |
3.31 |
3.31 |
0.00 |
65.80 |
69.11 |
Under Construction |
80.00 |
1. Due to outer ring-road construction in district distribution system has been affected. 3. Pump House construction in progress .
4. 30.96 Lacs bill uploaded on portal |
| 5 |
Basti |
20126168 |
Baisiya Kala G.P. w/s Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
177.21 |
29.84 |
29.84 |
0.00 |
147.37 |
177.21 |
Under Construction |
90.00 |
1. OHT work in progress. 2. Supervision Charge Submitted to UPPCL.
3. Power Connection Is in Progress.
4. 44.12 Lacs bill uploaded on portal |
| 6 |
Basti |
20126185 |
Amorah Khas G.P. w/s Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
384.20 |
94.39 |
94.39 |
0.00 |
289.81 |
384.20 |
Under Construction |
90.00 |
1. OHT work in progress. 2. Supervision Charge Submitted to UPPCL
3. Power Connection Is in Progress.
4. 64.71 Lacs bill uploaded on portal
|
| 7 |
Basti |
20126187 |
Ashokpur G.P. w/s Scheme |
NEW RETROFIT |
Jal Nigam |
YES |
NO |
NO |
341.59 |
57.23 |
57.23 |
0.00 |
284.36 |
341.59 |
Under Construction |
90.00 |
1. OHT work in progress. 2. Supervision Charge Submitted to UPPCL.
3. Transformer not energised Power Connection Is in Progress.
4. 61.67 Lacs bill uploaded on portal
|