S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Sant Kabeer Nagar 7401652 Alinagar PWS in JE/AEs affected Village NRDWP Jal Nigam YES NO NO 279.00 132.11 132.11 0.00 146.89 279.00 Under Construction 70.00 The work progress of tubewell 100 % , OHT 95 %, Pump House 95 %, Distribution Network 25% eletrification 95%, Raising mein 95% The work progress slow due to delayed payment
2 Sant Kabeer Nagar 7626726 MUKHALIS PUR NRDWP Jal Nigam YES NO NO 172.89 79.00 79.00 0.00 93.89 172.89 Under Construction 78.00 The work progress of tubewell 100 % , OHT 98%, Pump House 95 %, Distribution Network 95% and FHTC 60% . The work progress slow due to outstanding 1. Bill Amount Rs. 3336315.00 due payment on date 16.03.2024 2. Bill Amount Rs. 308716.00 due payment on date 16.10.2025 Funds for electrification have been deposited by C&DS, and efforts are underway to secure the connection from the Electricity Department.
3 Sant Kabeer Nagar 7626822 MAHULI NRDWP Jal Nigam YES NO NO 377.92 239.05 239.05 0.00 138.87 377.92 Under Construction 70.00 The work progress of tubewell 2 No. 1- 100% 2- 100%, Pump house 2 No. 1- 100%, 2- 70%, OHT 100 %, staffquater 100%, Distribution Network 80%, Raising main 2 No. 1- 100%, 2- 0%, and FHTC 45% . The work delayed due to outstanding 1. Bill Amount Rs. 673089.00 due payment on date 08.07.2023 2 Bill Amount Rs. 749507.00 due payment on date 23.07.2024 3. Bill Amount Rs. 999231.00 due payment on date 12.09.2023
4 Sant Kabeer Nagar 7628100 KONI NRDWP Jal Nigam YES NO NO 279.38 191.85 191.85 0.00 87.53 279.38 Under Construction 65.00 The work progress of tubewell 100 % , OHT 90 %, Pump House 20 %, staffquater 95%, Distribution Network 80% and FHTC 35% . The work stop due to Pump house land issue by local public. 1.Bill Amount Rs. 75206.00 due payment on date 09.09.2025
5 Sant Kabeer Nagar 7892286 Katka GOV EMWQ PWS Schemes NRDWP Jal Nigam YES NO NO 263.30 44.46 44.46 0.00 218.84 263.30 Under Construction 30.00 The work progress of tubewell 100 % , Pump House 25 %, Distribution Network 75% and FHTC 37% . The work stop due to outstanding Bill Amount Rs. 2553698.00 due payment on date 15.04.2026
6 Sant Kabeer Nagar 7892839 Mahadewa G.O.V. Water Supply Scheme NRDWP Jal Nigam YES NO NO 165.22 24.64 24.64 0.00 140.58 165.22 Under Construction 30.00 The work progress of tubewell 100 % , OHT 20 %, Pump House 80 %, Distribution Network 37% and FHTC 27% . The work stop due to outstanding 1. Bill Amount Rs. 485866.00 due payment on date 15.12.2022 2. Bill Amount Rs. 587972.00 due payment on date 24.09.2024
7 Sant Kabeer Nagar 7893500 KARAUDA GP WATER SUPPLY SCHEME NRDWP Jal Nigam YES NO NO 135.58 12.85 12.85 0.00 122.73 135.58 Under Construction 25.00 The work progress of tubewell 100 % , Pump House 80 %, Satffquater 80% . The work stop due to outstanding 1.Bill Amount Rs. 1182864.00 due payment on date 08.04.2024 2. Bill Amount Rs. 332982.00 due payment on date 24.09.2024
8 Sant Kabeer Nagar 7894072 PARASA SUKUL GP WATER SUPPLY SCHEME NRDWP Jal Nigam YES NO NO 149.66 1.33 1.33 0.00 148.33 149.66 Under Construction 60.00 The work progress of tubewell 90 % , OHT 70 %, Pump House 95 %, Distribution Network 95% and FHTC 60% . Supply of pumping plant 70%. for eletrification work Estimate demonded by UPPCL. The work delayed due to outstanding 1. Bill Amount Rs. 1065396.00 due payment on date 16.10.2025 2. Bill Amount Rs. 999797.00 due payment on date 02.01.2026
9 Sant Kabeer Nagar 7894134 Dudhara EMWQ NRDWP Jal Nigam YES NO NO 246.62 119.91 119.91 0.00 126.71 246.62 Under Construction 75.00 The work progress of tubewell 100 % , OHT 95%, Pump House 70 %, Distribution Network 95% and FHTC 33% , electrification 90 %. The work progress slow due to delayed payment
10 Sant Kabeer Nagar 8027214 NANDAUR NRDWP Jal Nigam YES NO NO 365.92 120.32 120.32 0.00 245.60 365.92 Under Construction 65.00 The work progress of tubewell 2 No. 1- 90% 2- 0%, Pump house 2 No. 1- 90%, 2- 0%, OHT 90 %, Distribution Network 68% and FHTC 33% . The work delayed due to outstanding Bill Amount Rs. 697216.00 due payment on date 20.03.2025
11 Sant Kabeer Nagar 8127436 GHOORAPALI NRDWP Jal Nigam YES NO NO 182.60 90.46 90.46 0.00 92.14 182.60 Under Construction 72.00 The work progress of tubewell 100 % , OHT 95 %, Pump House 95 %, Staffquater 95%, Distribution Network 66% The estimate for more than enough revaised estimate demand by UPPCL dept. The work delayed due to payment
12 Sant Kabeer Nagar 8130009 TARYAPAR NRDWP Jal Nigam YES NO NO 182.00 66.58 66.58 0.00 115.42 182.00 Under Construction 82.00 The work progress of tubewell 100 % , OHT 95 %, Pump House 98 %, staffquater 98%, Distribution Network 95% and FHTC 55% . Supply of pumping plant 70% and fund Deposited of eletification work against Estimate Rs. 251536.00 . The work delayed due to outstanding bill Rs. 2283803.00 Since 09.09.2024
13 Sant Kabeer Nagar 8130863 ON BILAIO NRDWP Jal Nigam YES NO NO 146.81 17.63 17.63 0.00 129.18 146.81 Under Construction 35.00 The work progress of tubewell 100 % , Pump House 75 %, Staffquater 75%, Distribution Network 75% and FHTC 30% . The work delayed due to payment
14 Sant Kabeer Nagar 8130880 GAYGHAT NRDWP Jal Nigam YES NO NO 151.85 11.98 11.98 0.00 139.87 151.85 Under Construction 15.00 The work progress of tubewell 100 % , Pump House 90 %, Distribution Network 85% and FHTC 50% . Distribution work in progress. The wok slow progress due to delayed payment
15 Sant Kabeer Nagar 8131643 BHAGAWATIPUR NRDWP Jal Nigam YES NO NO 184.87 37.63 37.63 0.00 147.24 184.87 Under Construction 51.00 The work progress of tubewell 100 % , OHT 95 %, Pump House 95 %, Staffquarter 90%, suppy of pumping plant 70% and fund Deposited of eletification work against Estimate Rs.219371.00 . The work delayed due to outstanding 1. Bill Amount Rs. 256226.00 due payment on date 04.03.2024 2. Bill Amount Rs. 428842.00 due payment on date 19.04.2023 3. Bill Amount Rs. 458286.00 due payment on date 05.09.2024
16 Sant Kabeer Nagar 20094676 KUSAUNA KALAN GP WSS NEW RETROFIT Jal Nigam YES NO NO 181.30 3.60 3.60 0.00 177.70 181.30 Under Construction 5.00 Land Alloted on Date 06.08.2026 work stoped by local person during start of construction of boundry wall
17 Sant Kabeer Nagar 20094685 BARPARWA GP WSS NEW RETROFIT Jal Nigam YES NO NO 172.50 28.00 28.00 0.00 144.50 172.50 Under Construction 20.00 The work progress of tubewell 100 % and OHT 30 % . The work delayed due to payment of Rs. 619614.00 Since 07.08.2025
18 Sant Kabeer Nagar 20094694 GIRDHARPUR GP WSS NEW RETROFIT Jal Nigam YES NO NO 228.20 16.24 16.24 0.00 211.96 228.20 Under Construction 17.00 The work progress of tubewell 100 % , OHT 30 %. The work stop due to outstanding bill Rs. 927147.00 Since 26.08.2026
19 Sant Kabeer Nagar 20094795 BARHYA THATHAR GP WSS NEW RETROFIT Jal Nigam YES NO NO 451.42 97.90 97.90 0.00 353.52 451.42 Under Construction 62.00 The work progress of tubewell 100 % , OHT 50 %, Pump House 90 %, Distribution Network 90% and FHTC 51% . The work delayed due to Bill Amount Rs. 3590755.00