| 1 |
Sant Kabeer Nagar |
7626726 |
MUKHALIS PUR |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
172.89 |
79.00 |
79.00 |
0.00 |
93.89 |
172.89 |
Under Construction |
78.00 |
The work progress of tubewell 100 % , OHT 98%, Pump House 95 %, Distribution Network 95% and FHTC 60% . The work progress slow due to outstanding
1. Bill Amount Rs. 3336315.00 due payment on date 16.03.2024
2. Bill Amount Rs. 308716.00 due payment on date 16.10.2025
Funds for electrification have been deposited by C&DS, and efforts are underway to secure the connection from the Electricity Department. |
| 2 |
Sant Kabeer Nagar |
8130009 |
TARYAPAR |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
182.00 |
66.58 |
66.58 |
0.00 |
115.42 |
182.00 |
Under Construction |
82.00 |
The work progress of tubewell 100 % , OHT 95 %, Pump House 98 %, staffquater 98%, Distribution Network 95% and FHTC 55% . Supply of pumping plant 70% and fund Deposited of eletification work against Estimate Rs. 251536.00 . The work delayed due to outstanding bill Rs. 2283803.00 Since 09.09.2024 |