| 1 |
Kushi Nagar |
7892835 |
Ahladpur EMWQ Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
287.37 |
106.88 |
106.88 |
0.00 |
180.49 |
287.37 |
Under Construction |
64.00 |
OHT column pipe, Staircase, Railing, SV and SV chamber, OHT finishing pending, Pumphouse at Sill level, boundrywall pending, Staff quarter finishing pending , approx 7 km Distribution system and approx 670 FHTC pending. |
| 2 |
Kushi Nagar |
7894059 |
Lachhia Deoria GOV AES JE Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
439.29 |
206.33 |
206.33 |
0.00 |
232.96 |
439.29 |
Under Construction |
65.00 |
OHT top dome, column pipe, Staircase, Railing, SV and SV chamber, finishing pending, Rising main pending , approx 7.5 km Distribution system and approx 880 FHTC pending. |
| 3 |
Kushi Nagar |
7894075 |
Gagalwa EMWQ |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
332.01 |
256.32 |
256.32 |
0.00 |
75.69 |
332.01 |
Under Construction |
62.00 |
Pumping plant and Electrification is pending, Rising main pending, Pumphouse, boundrywall and staff quarter fining work pending, Approx 8.5 km distribution system and approx 300 FHTC pending |
| 4 |
Kushi Nagar |
7913441 |
PACH PHERA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
204.54 |
110.92 |
110.92 |
0.00 |
93.62 |
204.54 |
Under Construction |
87.00 |
Electric connection from transformer to Pump house is pending. approx 150 m Distribution system and approx 300 FHTC pending, |
| 5 |
Kushi Nagar |
7924199 |
PARSAUNI GP WSS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
214.31 |
168.14 |
168.14 |
0.00 |
46.17 |
214.31 |
Under Construction |
65.00 |
Pumping plant and Electrification is pending, Rising main pending, OHT column pipe, Staircase, Railing, SV and SV chamber, Apron, finishing pending, boundrywall finishing pending, Staff quarter finishing pending , approx 5 km Distribution system and approx 500 FHTC pending. |
| 6 |
Kushi Nagar |
8039028 |
BADARAHA GRAM PANCHAYAT WS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
105.16 |
79.94 |
79.94 |
0.00 |
25.22 |
105.16 |
Under Construction |
38.00 |
OHT not started, Waterlogged in Current time. Contractor is agree for start work once the waterlogging has been cleared. Electrification, boundrywall, Rising main pending, Some Distribution system and FHTC pending. |
| 7 |
Kushi Nagar |
8127407 |
MAILA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
156.41 |
102.16 |
102.16 |
0.00 |
54.25 |
156.41 |
Under Construction |
5.00 |
Land not aviliable in this village which is informed by Revenue Department in written. And we are trying/Approach for land in other nearby village. |
| 8 |
Kushi Nagar |
8132396 |
HATHIYA |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
133.55 |
126.96 |
126.96 |
0.00 |
6.59 |
133.55 |
Under Construction |
60.00 |
OHT work pending, only excavation done, boundrywall finishing, pumphouse and staff quarter finishing and some FHTC pending, Direct pumping is going on. Contractor is not intrested in remaining work completion. |