S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Ballia 7081512 Jawhi NRDWP Jal Nigam YES NO NO 157.40 88.89 88.89 0.00 68.51 157.40 Under Construction 60.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹26.62 lakh. The following works are still pending:- 15% of OHT work, 350 House Connections (FHTCs), 35 meter Rising main, Solar System, 120 m Boundary wall and 10 percent P.H
2 Ballia 7081519 Nwranga NRDWP Jal Nigam YES NO NO 455.51 168.69 168.69 0.00 286.82 455.51 Under Construction 60.00 The Following works are pending - OHT 100% , Pipe laying 11.50 km, Pump house one 10% 2nd 100%, Rising main 445 m, House connection 400 Nos, Boundary wall 180 m and staff quarter 20% Currently work is stopped due to following reasons Pipe Laying Work: The required pipes are to be supplied by the Department. However, Uttar Pradesh Jal Nigam (Urban) has not yet handed over/issued the required material OHT Work: the Water Works area is presently water logged due to the ongoing rainy season.
3 Ballia 7081541 Hnuman Garh NWQSM Jal Nigam YES NO NO 226.99 158.75 158.75 0.00 68.24 226.99 Under Construction 82.00 Work is in progress The following works are pending:- 259House Connections (FHTCs) and Trial-Testing of pipe line
4 Ballia 7081554 Chai Chhpra NRDWP Jal Nigam YES NO NO 140.44 96.45 96.45 0.00 43.99 140.44 Under Construction 66.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 14.08 lakh. The following works are pending:- 1.20 km of pipeline laying, 60 % of OHT work, 250 House Connections (FHTCs), Rising main 35 m and boundary wall 50%
5 Ballia 7347868 sisotar diyara qpv scheme 2015 16 NWQSM Jal Nigam YES NO NO 428.59 168.53 168.53 0.00 260.06 428.59 Under Construction 35.00 The scheme was originally planned in two zones. However, work in Zone-I could not be commenced due to non-availability of the required land. The area is now proposed to be covered through the surface water supply scheme. The following works are pending in the zone 2: OHT: 20% work Rising Main: 35 m Boundary Wall: 20% work House Connections: 450 Nos. At present, the work has been stopped as the required pipeline agreement has not yet been handed over by Uttar Pradesh Jal Nigam (Urban).
6 Ballia 7892373 LAKUHA EWMQ NRDWP Jal Nigam YES NO NO 118.77 0.62 0.62 0.00 118.15 118.77 Under Construction 36.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 22.77 lakh. The following works are pending:- 8.84 km (100 %) of pipeline laying, 100% of OHT work, 127 House Connections (FHTCs),Pump house 1 No, Boundary wall 115 m, Rising main and power connection 1 No.35 m
7 Ballia 7894095 BISOULI GP WATER SUPPLY SCHEME NRDWP Jal Nigam YES NO NO 289.74 15.55 15.55 0.00 274.19 289.74 Under Construction 42.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 21.36 lakh. The following works are pending:- 3.50 km of pipeline laying, 100% of OHT work, 822 House Connections (FHTCs), Rising main 35 m and boundary wall 70%
8 Ballia 7894257 Sahulai Hardo Patti SAGY Scheme NRDWP Jal Nigam YES NO NO 438.67 1.06 1.06 0.00 437.61 438.67 Under Construction 25.00 Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹ 15.10 lakh. The following works are pending:- 28.50 km of pipeline laying, 100% of OHT work, 1221 House Connections (FHTCs), Pump house 1 No., Laying of rising main 45 m, Power connection 1 No, boundary wall 40% and staff quarter 80%
9 Ballia 7913426 RUKUNPURA GP WS SCHEME NWQSM Jal Nigam YES NO NO 170.55 113.45 113.45 0.00 57.10 170.55 Under Construction 80.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹21.76 lakh. Only 80 % of OHT work is pending
10 Ballia 7913429 BITHUA GP WS SCHEME NWQSM Jal Nigam YES NO NO 181.50 53.31 53.31 0.00 128.19 181.50 Under Construction 73.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 11.20 lakh. The following works are pending - 500 m Pipe line, 75 % OHT works, 35 m Rising Main, 505 Nos House connection, Staff quarter 15% and Boundary wall 15%
11 Ballia 7913431 DEHRI VILLAHE WS SCHEME NWQSM Jal Nigam YES NO NO 353.54 75.66 75.66 0.00 277.88 353.54 Under Construction 44.00 Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹16.43 lakh. The following works are still pending:- 15.50 km of pipeline laying, 20% of OHT work, 1015 House Connections (FHTCs), Pump house 2 No., Laying of rising main 645 m, Power connection 2 No, staff quarter 65%, and boundary wall 40%
12 Ballia 7913432 BUDHAU GP WS SCHEME NWQSM Jal Nigam YES NO NO 184.05 89.62 89.62 0.00 94.43 184.05 Under Construction 57.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹15.04 lakh. The following works are pending:- 1.75 km of pipeline laying, 70% of OHT work, 222 House Connections (FHTCs), Pump house 20%, Boundary wall 50% and staff Quarter 1 No
13 Ballia 7913437 SULTANPUR GP WS SCHEME NWQSM Jal Nigam YES NO NO 343.16 64.74 67.74 0.00 278.42 343.16 Under Construction 45.00 Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹13.35 lakh. The following works are still pending:- 14.20 km of pipeline laying, 30% of OHT work, 749 House Connections (FHTCs), 1 No. Pump house , Laying of rising main 35 m, Power connection 1 No, boundary wall 20%, and Staff Quarter 30%
14 Ballia 7913438 MOON CHUPRA GP WS SCHEME NWQSM Jal Nigam YES NO NO 352.32 156.17 156.17 0.00 196.15 352.32 Under Construction 78.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹54.57 lakh. The following works are still pending:- 409 House Connections (FHTCs), Rising Main 350 meter and power connection 2 No.
15 Ballia 7913453 GAJI PAKAD GP WS SCHEME NWQSM Jal Nigam YES NO NO 147.00 67.25 67.25 0.00 79.75 147.00 Under Construction 81.00 Work is in progress The following works are still pending:- 1.00 km of pipeline laying, 45% of OHT work, 51 House Connections (FHTCs), Pump house 15%, Boundary wall 25% ,Rising main 30m ,and Staff quarter 70%
16 Ballia 7913456 KIRTUPUR GP WS SCHEME NWQSM Jal Nigam YES NO NO 146.71 57.41 57.41 0.00 89.30 146.71 Under Construction 80.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹25.50 lakh. The following works are still pending:- 10% of OHT work 214 House Connections (FHTCs), power connection 1 No, Boundary wall 125 m.
17 Ballia 7913459 KAKRI GP WS SCHEME NWQSM Jal Nigam YES NO NO 153.97 53.66 53.66 0.00 100.31 153.97 Under Construction 60.00 Work is in progress The following works are pending:- 3.40 km of pipeline laying, 100% of OHT work, 194 House Connections (FHTCs), Pump house 20%, Boundary wall 30% and Staff quarter 30%
18 Ballia 7913460 MOTIRA GP WS SCHEME NWQSM Jal Nigam YES NO NO 142.05 17.20 17.20 0.00 124.85 142.05 Under Construction 55.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹17.91 lakh. The following works are pending: 900 m of pipeline laying, 100% of OHT work 241 House Connections (FHTCs),Power connection 1 No, Pump House 30%, Rising main 30 m and boundary wall 40 %
19 Ballia 7913471 PACHWAR GP WS SCHEME NWQSM Jal Nigam YES NO NO 153.86 34.11 34.11 0.00 119.75 153.86 Under Construction 74.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹36.21 lakh. The following works are still pending:- 800 m of pipeline laying, 20% of OHT work, 300 House Connections (HTCs)
20 Ballia 7924186 SHIVRAMPUR NWQSM Jal Nigam YES NO NO 251.57 41.34 41.34 0.00 210.23 251.57 Under Construction 46.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹8.14 lakh. The following works are pending: 8.84 km(100%) of pipeline laying, 40% of OHT work 729 House Connections (FHTCs),Power connection 2 No, Pump House 1 No.40%, Rising main 545 m and boundary wall 20 %
21 Ballia 7924187 MUDERA NWQSM Jal Nigam YES NO NO 312.75 107.46 107.46 0.00 205.29 312.75 Under Construction 60.00 Work is in progress The following works are pending:- 5.30 km of pipeline laying, 10% of OHT work, 435 House Connections (FHTCs), Pump house 10%, Boundary wall 50% , Power connection 1 No, Rising main 45 m and Staff quarter 40%
22 Ballia 7924188 NAGHAR NWQSM Jal Nigam YES NO NO 162.00 40.62 40.62 0.00 121.38 162.00 Under Construction 40.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹15.16 lakh. The following works are pending: 3.50 km of pipeline laying, 100% of OHT work, 376 House Connections (FHTCs),Power connection 1 No, Pump House 10%, Rising main 35 m, Staff Quarter 40% and boundary wall 20 %
23 Ballia 7924189 AMHAR PATTI NWQSM Jal Nigam YES NO NO 309.62 53.11 53.11 0.00 256.51 309.62 Under Construction 69.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 53.10 lakh. The following works are pending: 11.20 km of pipeline laying, 732 House Connections (FHTCs), Pump House 10%
24 Ballia 7924209 SIGHI NWQSM Jal Nigam YES NO NO 359.40 47.69 47.69 0.00 311.71 359.40 Under Construction 42.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 23.87 lakh. The following works are pending: 8.50 km of pipeline laying, OHT 80%, 862 House Connections (FHTCs), Pump House 60%, Boundary wall 110 m and Rising main 35 m
25 Ballia 8127588 KARNAI NRDWP Jal Nigam YES NO NO 442.94 173.84 173.84 0.00 269.10 442.94 Under Construction 81.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 36.58 lakh. The following works are pending:- 10 % of OHT work 627 House Connections (FHTCs), 10% Pump house, 10% boundary wall and 10% staff quarter
26 Ballia 8132371 Bigahi NRDWP Jal Nigam YES NO NO 354.00 146.68 146.68 0.00 207.32 354.00 Under Construction 87.00 Work is in progress The following works are pending:- House connection 150 Nos and Boundary wall 75%
27 Ballia 8132384 Kushha Rasidpur NRDWP Jal Nigam YES NO NO 190.58 98.55 98.55 0.00 92.03 190.58 Under Construction 78.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 5.58 lakh. The following works are pending:- 500 m of pipeline laying, 20% of OHT work, 138 House Connections (FHTCs),Pump house 30%, Boundary wall 20%, Rising main 35 m and Staff Quarter 50%
28 Ballia 8132388 Nikasi NRDWP Jal Nigam YES NO NO 323.60 70.34 70.34 0.00 253.26 323.60 Under Construction 71.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 72.68 lakh. The following works are pending:- 9.5 km of pipeline laying, 65% of OHT work, 641 House Connections (FHTCs),Pump house 20%, Boundary wall 50% and Rising main 35 m
29 Ballia 20094368 Khatanga Math Ramgiri Gram Panchayat Water Supply Scheme NWQSM Jal Nigam YES NO NO 142.59 72.09 72.09 0.00 70.50 142.59 Under Construction 90.00 The work is currently stopped due to the unfortunate demise of the contractor. Re-tendering is presently in progress for the following pending works: OHT: 20% work pending Rising Main: 30 m pending House Connections: 60 Nos. pending
30 Ballia 20126188 ARU/FRU Ballia NWQSM Jal Nigam YES NO NO 4351.16 843.48 843.48 0.00 3507.68 4351.16 Under Construction 33.00 ARU/FRU work status detail are as below: 1) schemes Civil works not completed due to fund issue - 15 Nos. 2) ARU/FRU commissioned and in O&M - 15 Nos. 3) Not required due to no contamination- 7 Nos. 4) Civil work completed but due to fund issue work not started - 8 Nos.