| 1 |
Ballia |
7081512 |
Jawhi |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
157.40 |
88.89 |
88.89 |
0.00 |
68.51 |
157.40 |
Under Construction |
60.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹26.62 lakh. The following works are still pending:-
15% of OHT work,
350 House Connections (FHTCs),
35 meter Rising main,
Solar System,
120 m Boundary wall and 10 percent P.H
|
| 2 |
Ballia |
7081519 |
Nwranga |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
455.51 |
168.69 |
168.69 |
0.00 |
286.82 |
455.51 |
Under Construction |
60.00 |
The Following works are pending - OHT 100% , Pipe laying 11.50 km, Pump house one 10% 2nd 100%, Rising main 445 m, House connection 400 Nos, Boundary wall 180 m and staff quarter 20% Currently work is stopped due to following reasons
Pipe Laying Work: The required pipes are to be supplied by the Department. However, Uttar Pradesh Jal Nigam (Urban) has not yet handed over/issued the required material
OHT Work: the Water Works area is presently water logged due to the ongoing rainy season. |
| 3 |
Ballia |
7081541 |
Hnuman Garh |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
226.99 |
158.75 |
158.75 |
0.00 |
68.24 |
226.99 |
Under Construction |
82.00 |
Work is in progress The following works are pending:-
259House Connections (FHTCs) and Trial-Testing of pipe line
|
| 4 |
Ballia |
7081554 |
Chai Chhpra |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
140.44 |
96.45 |
96.45 |
0.00 |
43.99 |
140.44 |
Under Construction |
66.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 14.08 lakh. The following works are pending:-
1.20 km of pipeline laying,
60 % of OHT work, 250 House Connections (FHTCs), Rising main 35 m and boundary wall 50% |
| 5 |
Ballia |
7347868 |
sisotar diyara qpv scheme 2015 16 |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
428.59 |
168.53 |
168.53 |
0.00 |
260.06 |
428.59 |
Under Construction |
35.00 |
The scheme was originally planned in two zones. However, work in Zone-I could not be commenced due to non-availability of the required land. The area is now proposed to be covered through the surface water supply scheme.
The following works are pending in the zone 2:
OHT: 20% work
Rising Main: 35 m
Boundary Wall: 20% work House Connections: 450 Nos.
At present, the work has been stopped as the required pipeline agreement has not yet been handed over by Uttar Pradesh Jal Nigam (Urban). |
| 6 |
Ballia |
7892373 |
LAKUHA EWMQ |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
118.77 |
0.62 |
0.62 |
0.00 |
118.15 |
118.77 |
Under Construction |
36.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 22.77 lakh. The following works are pending:-
8.84 km (100 %) of pipeline laying,
100% of OHT work,
127 House Connections (FHTCs),Pump house 1 No, Boundary wall 115 m, Rising main and power connection 1 No.35 m |
| 7 |
Ballia |
7894095 |
BISOULI GP WATER SUPPLY SCHEME |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
289.74 |
15.55 |
15.55 |
0.00 |
274.19 |
289.74 |
Under Construction |
42.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 21.36 lakh. The following works are pending:-
3.50 km of pipeline laying,
100% of OHT work, 822 House Connections (FHTCs), Rising main 35 m and boundary wall 70% |
| 8 |
Ballia |
7894257 |
Sahulai Hardo Patti SAGY Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
438.67 |
1.06 |
1.06 |
0.00 |
437.61 |
438.67 |
Under Construction |
25.00 |
Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹ 15.10 lakh. The following works are pending:-
28.50 km of pipeline laying,
100% of OHT work,
1221 House Connections (FHTCs),
Pump house 1 No., Laying of rising main 45 m, Power connection 1 No, boundary wall 40% and staff quarter 80% |
| 9 |
Ballia |
7913426 |
RUKUNPURA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
170.55 |
113.45 |
113.45 |
0.00 |
57.10 |
170.55 |
Under Construction |
80.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹21.76 lakh. Only 80 % of OHT work is pending
|
| 10 |
Ballia |
7913429 |
BITHUA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
181.50 |
53.31 |
53.31 |
0.00 |
128.19 |
181.50 |
Under Construction |
73.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 11.20 lakh. The following works are pending - 500 m Pipe line, 75 % OHT works, 35 m Rising Main, 505 Nos House connection, Staff quarter 15% and Boundary wall 15% |
| 11 |
Ballia |
7913431 |
DEHRI VILLAHE WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
353.54 |
75.66 |
75.66 |
0.00 |
277.88 |
353.54 |
Under Construction |
44.00 |
Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹16.43 lakh. The following works are still pending:-
15.50 km of pipeline laying,
20% of OHT work,
1015 House Connections (FHTCs),
Pump house 2 No., Laying of rising main 645 m, Power connection 2 No, staff quarter 65%, and boundary wall 40% |
| 12 |
Ballia |
7913432 |
BUDHAU GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
184.05 |
89.62 |
89.62 |
0.00 |
94.43 |
184.05 |
Under Construction |
57.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹15.04 lakh. The following works are pending:-
1.75 km of pipeline laying,
70% of OHT work,
222 House Connections (FHTCs),
Pump house 20%, Boundary wall 50% and staff Quarter 1 No |
| 13 |
Ballia |
7913437 |
SULTANPUR GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
343.16 |
64.74 |
67.74 |
0.00 |
278.42 |
343.16 |
Under Construction |
45.00 |
Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹13.35 lakh. The following works are still pending:-
14.20 km of pipeline laying,
30% of OHT work,
749 House Connections (FHTCs),
1 No. Pump house , Laying of rising main 35 m, Power connection 1 No, boundary wall 20%, and Staff Quarter 30% |
| 14 |
Ballia |
7913438 |
MOON CHUPRA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
352.32 |
156.17 |
156.17 |
0.00 |
196.15 |
352.32 |
Under Construction |
78.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹54.57 lakh. The following works are still pending:-
409 House Connections (FHTCs), Rising Main 350 meter and power connection 2 No. |
| 15 |
Ballia |
7913453 |
GAJI PAKAD GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
147.00 |
67.25 |
67.25 |
0.00 |
79.75 |
147.00 |
Under Construction |
81.00 |
Work is in progress The following works are still pending:-
1.00 km of pipeline laying,
45% of OHT work,
51 House Connections (FHTCs),
Pump house 15%, Boundary wall 25% ,Rising main 30m ,and Staff quarter 70% |
| 16 |
Ballia |
7913456 |
KIRTUPUR GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
146.71 |
57.41 |
57.41 |
0.00 |
89.30 |
146.71 |
Under Construction |
80.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹25.50 lakh. The following works are still pending:-
10% of OHT work
214 House Connections (FHTCs), power connection 1 No, Boundary wall 125 m. |
| 17 |
Ballia |
7913459 |
KAKRI GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
153.97 |
53.66 |
53.66 |
0.00 |
100.31 |
153.97 |
Under Construction |
60.00 |
Work is in progress The following works are pending:-
3.40 km of pipeline laying,
100% of OHT work,
194 House Connections (FHTCs),
Pump house 20%, Boundary wall 30% and Staff quarter 30% |
| 18 |
Ballia |
7913460 |
MOTIRA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
142.05 |
17.20 |
17.20 |
0.00 |
124.85 |
142.05 |
Under Construction |
55.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹17.91 lakh. The following works are pending:
900 m of pipeline laying,
100% of OHT work
241 House Connections (FHTCs),Power connection 1 No, Pump House 30%, Rising main 30 m and boundary wall 40 % |
| 19 |
Ballia |
7913471 |
PACHWAR GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
153.86 |
34.11 |
34.11 |
0.00 |
119.75 |
153.86 |
Under Construction |
74.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹36.21 lakh. The following works are still pending:-
800 m of pipeline laying,
20% of OHT work,
300 House Connections (HTCs) |
| 20 |
Ballia |
7924186 |
SHIVRAMPUR |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
251.57 |
41.34 |
41.34 |
0.00 |
210.23 |
251.57 |
Under Construction |
46.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹8.14 lakh. The following works are pending:
8.84 km(100%) of pipeline laying,
40% of OHT work
729 House Connections (FHTCs),Power connection 2 No, Pump House 1 No.40%, Rising main 545 m and boundary wall 20 % |
| 21 |
Ballia |
7924187 |
MUDERA |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
312.75 |
107.46 |
107.46 |
0.00 |
205.29 |
312.75 |
Under Construction |
60.00 |
Work is in progress The following works are pending:-
5.30 km of pipeline laying,
10% of OHT work,
435 House Connections (FHTCs),
Pump house 10%, Boundary wall 50% , Power connection 1 No, Rising main 45 m and Staff quarter 40% |
| 22 |
Ballia |
7924188 |
NAGHAR |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
162.00 |
40.62 |
40.62 |
0.00 |
121.38 |
162.00 |
Under Construction |
40.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹15.16 lakh. The following works are pending:
3.50 km of pipeline laying,
100% of OHT work,
376 House Connections (FHTCs),Power connection 1 No, Pump House 10%, Rising main 35 m, Staff Quarter 40% and boundary wall 20 % |
| 23 |
Ballia |
7924189 |
AMHAR PATTI |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
309.62 |
53.11 |
53.11 |
0.00 |
256.51 |
309.62 |
Under Construction |
69.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 53.10 lakh. The following works are pending:
11.20 km of pipeline laying,
732 House Connections (FHTCs), Pump House 10% |
| 24 |
Ballia |
7924209 |
SIGHI |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
359.40 |
47.69 |
47.69 |
0.00 |
311.71 |
359.40 |
Under Construction |
42.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 23.87 lakh. The following works are pending:
8.50 km of pipeline laying, OHT 80%,
862 House Connections (FHTCs), Pump House 60%, Boundary wall 110 m and Rising main 35 m |
| 25 |
Ballia |
8127588 |
KARNAI |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
442.94 |
173.84 |
173.84 |
0.00 |
269.10 |
442.94 |
Under Construction |
81.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 36.58 lakh. The following works are pending:-
10 % of OHT work
627 House Connections (FHTCs), 10% Pump house, 10% boundary wall and 10% staff quarter |
| 26 |
Ballia |
8132371 |
Bigahi |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
354.00 |
146.68 |
146.68 |
0.00 |
207.32 |
354.00 |
Under Construction |
87.00 |
Work is in progress The following works are pending:-
House connection 150 Nos and Boundary wall 75% |
| 27 |
Ballia |
8132384 |
Kushha Rasidpur |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
190.58 |
98.55 |
98.55 |
0.00 |
92.03 |
190.58 |
Under Construction |
78.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 5.58 lakh. The following works are pending:-
500 m of pipeline laying,
20% of OHT work,
138 House Connections (FHTCs),Pump house 30%, Boundary wall 20%, Rising main 35 m and Staff Quarter 50% |
| 28 |
Ballia |
8132388 |
Nikasi |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
323.60 |
70.34 |
70.34 |
0.00 |
253.26 |
323.60 |
Under Construction |
71.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 72.68 lakh. The following works are pending:-
9.5 km of pipeline laying,
65% of OHT work,
641 House Connections (FHTCs),Pump house 20%, Boundary wall 50% and Rising main 35 m |
| 29 |
Ballia |
20094368 |
Khatanga Math Ramgiri Gram Panchayat Water Supply Scheme |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
142.59 |
72.09 |
72.09 |
0.00 |
70.50 |
142.59 |
Under Construction |
90.00 |
The work is currently stopped due to the unfortunate demise of the contractor. Re-tendering is presently in progress for the following pending works:
OHT: 20% work pending
Rising Main: 30 m pending
House Connections: 60 Nos. pending |
| 30 |
Ballia |
20126188 |
ARU/FRU Ballia |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
4351.16 |
843.48 |
843.48 |
0.00 |
3507.68 |
4351.16 |
Under Construction |
33.00 |
ARU/FRU work status detail are as below:
1) schemes Civil works not completed due to fund issue - 15 Nos.
2) ARU/FRU commissioned and in O&M - 15 Nos.
3) Not required due to no contamination- 7 Nos.
4) Civil work completed but due to fund issue work not started - 8 Nos. |