S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Ballia 7347868 sisotar diyara qpv scheme 2015 16 NWQSM Jal Nigam YES NO NO 428.59 168.53 168.53 0.00 260.06 428.59 Under Construction 35.00 The scheme was originally planned in two zones. However, work in Zone-I could not be commenced due to non-availability of the required land. The area is now proposed to be covered through the surface water supply scheme. The following works are pending in the zone 2: OHT: 20% work Rising Main: 35 m Boundary Wall: 20% work House Connections: 450 Nos. At present, the work has been stopped as the required pipeline agreement has not yet been handed over by Uttar Pradesh Jal Nigam (Urban).
2 Ballia 7892373 LAKUHA EWMQ NRDWP Jal Nigam YES NO NO 118.77 0.62 0.62 0.00 118.15 118.77 Under Construction 36.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 22.77 lakh. The following works are pending:- 8.84 km (100 %) of pipeline laying, 100% of OHT work, 127 House Connections (FHTCs),Pump house 1 No, Boundary wall 115 m, Rising main and power connection 1 No.35 m
3 Ballia 7894095 BISOULI GP WATER SUPPLY SCHEME NRDWP Jal Nigam YES NO NO 289.74 15.55 15.55 0.00 274.19 289.74 Under Construction 42.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 21.36 lakh. The following works are pending:- 3.50 km of pipeline laying, 100% of OHT work, 822 House Connections (FHTCs), Rising main 35 m and boundary wall 70%
4 Ballia 7894257 Sahulai Hardo Patti SAGY Scheme NRDWP Jal Nigam YES NO NO 438.67 1.06 1.06 0.00 437.61 438.67 Under Construction 25.00 Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹ 15.10 lakh. The following works are pending:- 28.50 km of pipeline laying, 100% of OHT work, 1221 House Connections (FHTCs), Pump house 1 No., Laying of rising main 45 m, Power connection 1 No, boundary wall 40% and staff quarter 80%
5 Ballia 7913431 DEHRI VILLAHE WS SCHEME NWQSM Jal Nigam YES NO NO 353.54 75.66 75.66 0.00 277.88 353.54 Under Construction 44.00 Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹16.43 lakh. The following works are still pending:- 15.50 km of pipeline laying, 20% of OHT work, 1015 House Connections (FHTCs), Pump house 2 No., Laying of rising main 645 m, Power connection 2 No, staff quarter 65%, and boundary wall 40%
6 Ballia 7913437 SULTANPUR GP WS SCHEME NWQSM Jal Nigam YES NO NO 343.16 64.74 67.74 0.00 278.42 343.16 Under Construction 45.00 Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹13.35 lakh. The following works are still pending:- 14.20 km of pipeline laying, 30% of OHT work, 749 House Connections (FHTCs), 1 No. Pump house , Laying of rising main 35 m, Power connection 1 No, boundary wall 20%, and Staff Quarter 30%
7 Ballia 7924186 SHIVRAMPUR NWQSM Jal Nigam YES NO NO 251.57 41.34 41.34 0.00 210.23 251.57 Under Construction 46.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹8.14 lakh. The following works are pending: 8.84 km(100%) of pipeline laying, 40% of OHT work 729 House Connections (FHTCs),Power connection 2 No, Pump House 1 No.40%, Rising main 545 m and boundary wall 20 %
8 Ballia 7924188 NAGHAR NWQSM Jal Nigam YES NO NO 162.00 40.62 40.62 0.00 121.38 162.00 Under Construction 40.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹15.16 lakh. The following works are pending: 3.50 km of pipeline laying, 100% of OHT work, 376 House Connections (FHTCs),Power connection 1 No, Pump House 10%, Rising main 35 m, Staff Quarter 40% and boundary wall 20 %
9 Ballia 7924209 SIGHI NWQSM Jal Nigam YES NO NO 359.40 47.69 47.69 0.00 311.71 359.40 Under Construction 42.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 23.87 lakh. The following works are pending: 8.50 km of pipeline laying, OHT 80%, 862 House Connections (FHTCs), Pump House 60%, Boundary wall 110 m and Rising main 35 m
10 Ballia 20126188 ARU/FRU Ballia NWQSM Jal Nigam YES NO NO 4351.16 843.48 843.48 0.00 3507.68 4351.16 Under Construction 33.00 ARU/FRU work status detail are as below: 1) schemes Civil works not completed due to fund issue - 15 Nos. 2) ARU/FRU commissioned and in O&M - 15 Nos. 3) Not required due to no contamination- 7 Nos. 4) Civil work completed but due to fund issue work not started - 8 Nos.