| 1 |
Ballia |
7347868 |
sisotar diyara qpv scheme 2015 16 |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
428.59 |
168.53 |
168.53 |
0.00 |
260.06 |
428.59 |
Under Construction |
35.00 |
The scheme was originally planned in two zones. However, work in Zone-I could not be commenced due to non-availability of the required land. The area is now proposed to be covered through the surface water supply scheme.
The following works are pending in the zone 2:
OHT: 20% work
Rising Main: 35 m
Boundary Wall: 20% work House Connections: 450 Nos.
At present, the work has been stopped as the required pipeline agreement has not yet been handed over by Uttar Pradesh Jal Nigam (Urban). |
| 2 |
Ballia |
7892373 |
LAKUHA EWMQ |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
118.77 |
0.62 |
0.62 |
0.00 |
118.15 |
118.77 |
Under Construction |
36.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 22.77 lakh. The following works are pending:-
8.84 km (100 %) of pipeline laying,
100% of OHT work,
127 House Connections (FHTCs),Pump house 1 No, Boundary wall 115 m, Rising main and power connection 1 No.35 m |
| 3 |
Ballia |
7894095 |
BISOULI GP WATER SUPPLY SCHEME |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
289.74 |
15.55 |
15.55 |
0.00 |
274.19 |
289.74 |
Under Construction |
42.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 21.36 lakh. The following works are pending:-
3.50 km of pipeline laying,
100% of OHT work, 822 House Connections (FHTCs), Rising main 35 m and boundary wall 70% |
| 4 |
Ballia |
7894257 |
Sahulai Hardo Patti SAGY Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
438.67 |
1.06 |
1.06 |
0.00 |
437.61 |
438.67 |
Under Construction |
25.00 |
Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹ 15.10 lakh. The following works are pending:-
28.50 km of pipeline laying,
100% of OHT work,
1221 House Connections (FHTCs),
Pump house 1 No., Laying of rising main 45 m, Power connection 1 No, boundary wall 40% and staff quarter 80% |
| 5 |
Ballia |
7913431 |
DEHRI VILLAHE WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
353.54 |
75.66 |
75.66 |
0.00 |
277.88 |
353.54 |
Under Construction |
44.00 |
Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹16.43 lakh. The following works are still pending:-
15.50 km of pipeline laying,
20% of OHT work,
1015 House Connections (FHTCs),
Pump house 2 No., Laying of rising main 645 m, Power connection 2 No, staff quarter 65%, and boundary wall 40% |
| 6 |
Ballia |
7913437 |
SULTANPUR GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
343.16 |
64.74 |
67.74 |
0.00 |
278.42 |
343.16 |
Under Construction |
45.00 |
Work is in progress but the pace of work is slow due to non-payment of an outstanding bill amounting to ₹13.35 lakh. The following works are still pending:-
14.20 km of pipeline laying,
30% of OHT work,
749 House Connections (FHTCs),
1 No. Pump house , Laying of rising main 35 m, Power connection 1 No, boundary wall 20%, and Staff Quarter 30% |
| 7 |
Ballia |
7924186 |
SHIVRAMPUR |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
251.57 |
41.34 |
41.34 |
0.00 |
210.23 |
251.57 |
Under Construction |
46.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹8.14 lakh. The following works are pending:
8.84 km(100%) of pipeline laying,
40% of OHT work
729 House Connections (FHTCs),Power connection 2 No, Pump House 1 No.40%, Rising main 545 m and boundary wall 20 % |
| 8 |
Ballia |
7924188 |
NAGHAR |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
162.00 |
40.62 |
40.62 |
0.00 |
121.38 |
162.00 |
Under Construction |
40.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹15.16 lakh. The following works are pending:
3.50 km of pipeline laying,
100% of OHT work,
376 House Connections (FHTCs),Power connection 1 No, Pump House 10%, Rising main 35 m, Staff Quarter 40% and boundary wall 20 % |
| 9 |
Ballia |
7924209 |
SIGHI |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
359.40 |
47.69 |
47.69 |
0.00 |
311.71 |
359.40 |
Under Construction |
42.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 23.87 lakh. The following works are pending:
8.50 km of pipeline laying, OHT 80%,
862 House Connections (FHTCs), Pump House 60%, Boundary wall 110 m and Rising main 35 m |
| 10 |
Ballia |
20126188 |
ARU/FRU Ballia |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
4351.16 |
843.48 |
843.48 |
0.00 |
3507.68 |
4351.16 |
Under Construction |
33.00 |
ARU/FRU work status detail are as below:
1) schemes Civil works not completed due to fund issue - 15 Nos.
2) ARU/FRU commissioned and in O&M - 15 Nos.
3) Not required due to no contamination- 7 Nos.
4) Civil work completed but due to fund issue work not started - 8 Nos. |