S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Ballia 7081512 Jawhi NRDWP Jal Nigam YES NO NO 157.40 88.89 88.89 0.00 68.51 157.40 Under Construction 60.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹26.62 lakh. The following works are still pending:- 15% of OHT work, 350 House Connections (FHTCs), 35 meter Rising main, Solar System, 120 m Boundary wall and 10 percent P.H
2 Ballia 7081519 Nwranga NRDWP Jal Nigam YES NO NO 455.51 168.69 168.69 0.00 286.82 455.51 Under Construction 60.00 The Following works are pending - OHT 100% , Pipe laying 11.50 km, Pump house one 10% 2nd 100%, Rising main 445 m, House connection 400 Nos, Boundary wall 180 m and staff quarter 20% Currently work is stopped due to following reasons Pipe Laying Work: The required pipes are to be supplied by the Department. However, Uttar Pradesh Jal Nigam (Urban) has not yet handed over/issued the required material OHT Work: the Water Works area is presently water logged due to the ongoing rainy season.
3 Ballia 7081554 Chai Chhpra NRDWP Jal Nigam YES NO NO 140.44 96.45 96.45 0.00 43.99 140.44 Under Construction 66.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 14.08 lakh. The following works are pending:- 1.20 km of pipeline laying, 60 % of OHT work, 250 House Connections (FHTCs), Rising main 35 m and boundary wall 50%
4 Ballia 7913429 BITHUA GP WS SCHEME NWQSM Jal Nigam YES NO NO 181.50 53.31 53.31 0.00 128.19 181.50 Under Construction 73.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 11.20 lakh. The following works are pending - 500 m Pipe line, 75 % OHT works, 35 m Rising Main, 505 Nos House connection, Staff quarter 15% and Boundary wall 15%
5 Ballia 7913432 BUDHAU GP WS SCHEME NWQSM Jal Nigam YES NO NO 184.05 89.62 89.62 0.00 94.43 184.05 Under Construction 57.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹15.04 lakh. The following works are pending:- 1.75 km of pipeline laying, 70% of OHT work, 222 House Connections (FHTCs), Pump house 20%, Boundary wall 50% and staff Quarter 1 No
6 Ballia 7913459 KAKRI GP WS SCHEME NWQSM Jal Nigam YES NO NO 153.97 53.66 53.66 0.00 100.31 153.97 Under Construction 60.00 Work is in progress The following works are pending:- 3.40 km of pipeline laying, 100% of OHT work, 194 House Connections (FHTCs), Pump house 20%, Boundary wall 30% and Staff quarter 30%
7 Ballia 7913460 MOTIRA GP WS SCHEME NWQSM Jal Nigam YES NO NO 142.05 17.20 17.20 0.00 124.85 142.05 Under Construction 55.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹17.91 lakh. The following works are pending: 900 m of pipeline laying, 100% of OHT work 241 House Connections (FHTCs),Power connection 1 No, Pump House 30%, Rising main 30 m and boundary wall 40 %
8 Ballia 7913471 PACHWAR GP WS SCHEME NWQSM Jal Nigam YES NO NO 153.86 34.11 34.11 0.00 119.75 153.86 Under Construction 74.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹36.21 lakh. The following works are still pending:- 800 m of pipeline laying, 20% of OHT work, 300 House Connections (HTCs)
9 Ballia 7924187 MUDERA NWQSM Jal Nigam YES NO NO 312.75 107.46 107.46 0.00 205.29 312.75 Under Construction 60.00 Work is in progress The following works are pending:- 5.30 km of pipeline laying, 10% of OHT work, 435 House Connections (FHTCs), Pump house 10%, Boundary wall 50% , Power connection 1 No, Rising main 45 m and Staff quarter 40%
10 Ballia 7924189 AMHAR PATTI NWQSM Jal Nigam YES NO NO 309.62 53.11 53.11 0.00 256.51 309.62 Under Construction 69.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 53.10 lakh. The following works are pending: 11.20 km of pipeline laying, 732 House Connections (FHTCs), Pump House 10%
11 Ballia 8132388 Nikasi NRDWP Jal Nigam YES NO NO 323.60 70.34 70.34 0.00 253.26 323.60 Under Construction 71.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 72.68 lakh. The following works are pending:- 9.5 km of pipeline laying, 65% of OHT work, 641 House Connections (FHTCs),Pump house 20%, Boundary wall 50% and Rising main 35 m