| 1 |
Ballia |
7081512 |
Jawhi |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
157.40 |
88.89 |
88.89 |
0.00 |
68.51 |
157.40 |
Under Construction |
60.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹26.62 lakh. The following works are still pending:-
15% of OHT work,
350 House Connections (FHTCs),
35 meter Rising main,
Solar System,
120 m Boundary wall and 10 percent P.H
|
| 2 |
Ballia |
7081519 |
Nwranga |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
455.51 |
168.69 |
168.69 |
0.00 |
286.82 |
455.51 |
Under Construction |
60.00 |
The Following works are pending - OHT 100% , Pipe laying 11.50 km, Pump house one 10% 2nd 100%, Rising main 445 m, House connection 400 Nos, Boundary wall 180 m and staff quarter 20% Currently work is stopped due to following reasons
Pipe Laying Work: The required pipes are to be supplied by the Department. However, Uttar Pradesh Jal Nigam (Urban) has not yet handed over/issued the required material
OHT Work: the Water Works area is presently water logged due to the ongoing rainy season. |
| 3 |
Ballia |
7081554 |
Chai Chhpra |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
140.44 |
96.45 |
96.45 |
0.00 |
43.99 |
140.44 |
Under Construction |
66.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 14.08 lakh. The following works are pending:-
1.20 km of pipeline laying,
60 % of OHT work, 250 House Connections (FHTCs), Rising main 35 m and boundary wall 50% |
| 4 |
Ballia |
7913429 |
BITHUA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
181.50 |
53.31 |
53.31 |
0.00 |
128.19 |
181.50 |
Under Construction |
73.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 11.20 lakh. The following works are pending - 500 m Pipe line, 75 % OHT works, 35 m Rising Main, 505 Nos House connection, Staff quarter 15% and Boundary wall 15% |
| 5 |
Ballia |
7913432 |
BUDHAU GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
184.05 |
89.62 |
89.62 |
0.00 |
94.43 |
184.05 |
Under Construction |
57.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹15.04 lakh. The following works are pending:-
1.75 km of pipeline laying,
70% of OHT work,
222 House Connections (FHTCs),
Pump house 20%, Boundary wall 50% and staff Quarter 1 No |
| 6 |
Ballia |
7913459 |
KAKRI GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
153.97 |
53.66 |
53.66 |
0.00 |
100.31 |
153.97 |
Under Construction |
60.00 |
Work is in progress The following works are pending:-
3.40 km of pipeline laying,
100% of OHT work,
194 House Connections (FHTCs),
Pump house 20%, Boundary wall 30% and Staff quarter 30% |
| 7 |
Ballia |
7913460 |
MOTIRA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
142.05 |
17.20 |
17.20 |
0.00 |
124.85 |
142.05 |
Under Construction |
55.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹17.91 lakh. The following works are pending:
900 m of pipeline laying,
100% of OHT work
241 House Connections (FHTCs),Power connection 1 No, Pump House 30%, Rising main 30 m and boundary wall 40 % |
| 8 |
Ballia |
7913471 |
PACHWAR GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
153.86 |
34.11 |
34.11 |
0.00 |
119.75 |
153.86 |
Under Construction |
74.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹36.21 lakh. The following works are still pending:-
800 m of pipeline laying,
20% of OHT work,
300 House Connections (HTCs) |
| 9 |
Ballia |
7924187 |
MUDERA |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
312.75 |
107.46 |
107.46 |
0.00 |
205.29 |
312.75 |
Under Construction |
60.00 |
Work is in progress The following works are pending:-
5.30 km of pipeline laying,
10% of OHT work,
435 House Connections (FHTCs),
Pump house 10%, Boundary wall 50% , Power connection 1 No, Rising main 45 m and Staff quarter 40% |
| 10 |
Ballia |
7924189 |
AMHAR PATTI |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
309.62 |
53.11 |
53.11 |
0.00 |
256.51 |
309.62 |
Under Construction |
69.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 53.10 lakh. The following works are pending:
11.20 km of pipeline laying,
732 House Connections (FHTCs), Pump House 10% |
| 11 |
Ballia |
8132388 |
Nikasi |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
323.60 |
70.34 |
70.34 |
0.00 |
253.26 |
323.60 |
Under Construction |
71.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 72.68 lakh. The following works are pending:-
9.5 km of pipeline laying,
65% of OHT work,
641 House Connections (FHTCs),Pump house 20%, Boundary wall 50% and Rising main 35 m |