| 1 |
Ballia |
7081541 |
Hnuman Garh |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
226.99 |
158.75 |
158.75 |
0.00 |
68.24 |
226.99 |
Under Construction |
82.00 |
Work is in progress The following works are pending:-
259House Connections (FHTCs) and Trial-Testing of pipe line
|
| 2 |
Ballia |
7913426 |
RUKUNPURA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
170.55 |
113.45 |
113.45 |
0.00 |
57.10 |
170.55 |
Under Construction |
80.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹21.76 lakh. Only 80 % of OHT work is pending
|
| 3 |
Ballia |
7913438 |
MOON CHUPRA GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
352.32 |
156.17 |
156.17 |
0.00 |
196.15 |
352.32 |
Under Construction |
78.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹54.57 lakh. The following works are still pending:-
409 House Connections (FHTCs), Rising Main 350 meter and power connection 2 No. |
| 4 |
Ballia |
7913453 |
GAJI PAKAD GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
147.00 |
67.25 |
67.25 |
0.00 |
79.75 |
147.00 |
Under Construction |
81.00 |
Work is in progress The following works are still pending:-
1.00 km of pipeline laying,
45% of OHT work,
51 House Connections (FHTCs),
Pump house 15%, Boundary wall 25% ,Rising main 30m ,and Staff quarter 70% |
| 5 |
Ballia |
7913456 |
KIRTUPUR GP WS SCHEME |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
146.71 |
57.41 |
57.41 |
0.00 |
89.30 |
146.71 |
Under Construction |
80.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹25.50 lakh. The following works are still pending:-
10% of OHT work
214 House Connections (FHTCs), power connection 1 No, Boundary wall 125 m. |
| 6 |
Ballia |
8127588 |
KARNAI |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
442.94 |
173.84 |
173.84 |
0.00 |
269.10 |
442.94 |
Under Construction |
81.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 36.58 lakh. The following works are pending:-
10 % of OHT work
627 House Connections (FHTCs), 10% Pump house, 10% boundary wall and 10% staff quarter |
| 7 |
Ballia |
8132371 |
Bigahi |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
354.00 |
146.68 |
146.68 |
0.00 |
207.32 |
354.00 |
Under Construction |
87.00 |
Work is in progress The following works are pending:-
House connection 150 Nos and Boundary wall 75% |
| 8 |
Ballia |
8132384 |
Kushha Rasidpur |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
190.58 |
98.55 |
98.55 |
0.00 |
92.03 |
190.58 |
Under Construction |
78.00 |
The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 5.58 lakh. The following works are pending:-
500 m of pipeline laying,
20% of OHT work,
138 House Connections (FHTCs),Pump house 30%, Boundary wall 20%, Rising main 35 m and Staff Quarter 50% |
| 9 |
Ballia |
20094368 |
Khatanga Math Ramgiri Gram Panchayat Water Supply Scheme |
NWQSM |
Jal Nigam |
YES |
NO |
NO |
142.59 |
72.09 |
72.09 |
0.00 |
70.50 |
142.59 |
Under Construction |
90.00 |
The work is currently stopped due to the unfortunate demise of the contractor. Re-tendering is presently in progress for the following pending works:
OHT: 20% work pending
Rising Main: 30 m pending
House Connections: 60 Nos. pending |