S.No. District Scheme ID Scheme Name Program Name Department PWS Exist Physical Completion Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status Physical Progress(%) Remark
1 Ballia 7081541 Hnuman Garh NWQSM Jal Nigam YES NO NO 226.99 158.75 158.75 0.00 68.24 226.99 Under Construction 82.00 Work is in progress The following works are pending:- 259House Connections (FHTCs) and Trial-Testing of pipe line
2 Ballia 7913426 RUKUNPURA GP WS SCHEME NWQSM Jal Nigam YES NO NO 170.55 113.45 113.45 0.00 57.10 170.55 Under Construction 80.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹21.76 lakh. Only 80 % of OHT work is pending
3 Ballia 7913438 MOON CHUPRA GP WS SCHEME NWQSM Jal Nigam YES NO NO 352.32 156.17 156.17 0.00 196.15 352.32 Under Construction 78.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹54.57 lakh. The following works are still pending:- 409 House Connections (FHTCs), Rising Main 350 meter and power connection 2 No.
4 Ballia 7913453 GAJI PAKAD GP WS SCHEME NWQSM Jal Nigam YES NO NO 147.00 67.25 67.25 0.00 79.75 147.00 Under Construction 81.00 Work is in progress The following works are still pending:- 1.00 km of pipeline laying, 45% of OHT work, 51 House Connections (FHTCs), Pump house 15%, Boundary wall 25% ,Rising main 30m ,and Staff quarter 70%
5 Ballia 7913456 KIRTUPUR GP WS SCHEME NWQSM Jal Nigam YES NO NO 146.71 57.41 57.41 0.00 89.30 146.71 Under Construction 80.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹25.50 lakh. The following works are still pending:- 10% of OHT work 214 House Connections (FHTCs), power connection 1 No, Boundary wall 125 m.
6 Ballia 8127588 KARNAI NRDWP Jal Nigam YES NO NO 442.94 173.84 173.84 0.00 269.10 442.94 Under Construction 81.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 36.58 lakh. The following works are pending:- 10 % of OHT work 627 House Connections (FHTCs), 10% Pump house, 10% boundary wall and 10% staff quarter
7 Ballia 8132371 Bigahi NRDWP Jal Nigam YES NO NO 354.00 146.68 146.68 0.00 207.32 354.00 Under Construction 87.00 Work is in progress The following works are pending:- House connection 150 Nos and Boundary wall 75%
8 Ballia 8132384 Kushha Rasidpur NRDWP Jal Nigam YES NO NO 190.58 98.55 98.55 0.00 92.03 190.58 Under Construction 78.00 The work has been stopped by the contractor due to non-payment of an outstanding bill amounting to ₹ 5.58 lakh. The following works are pending:- 500 m of pipeline laying, 20% of OHT work, 138 House Connections (FHTCs),Pump house 30%, Boundary wall 20%, Rising main 35 m and Staff Quarter 50%
9 Ballia 20094368 Khatanga Math Ramgiri Gram Panchayat Water Supply Scheme NWQSM Jal Nigam YES NO NO 142.59 72.09 72.09 0.00 70.50 142.59 Under Construction 90.00 The work is currently stopped due to the unfortunate demise of the contractor. Re-tendering is presently in progress for the following pending works: OHT: 20% work pending Rising Main: 30 m pending House Connections: 60 Nos. pending