Jal Nigam ongoing and retrofit new scheme completion plan

District : Pratapgarh

Sno Scheme Id Scheme Name Scheme Completion Remarks Expected Completion Date
1 8130768 Dharauli Gram Panchayat Water Supply Scheme Gap closing work 50% pending BOE restoration 1.3km, Pipe laying 6.0 km, FHTC 40% 31-Dec-2026
2 8130701 Kadipur Gram Panchayat Water Supply Scheme Gap closing work 60% pending BOE restoration 2.0 km, Pipe laying 5.5 km, FHTC 45% 31-Dec-2026
3 8130665 Teliyani Gram Panchayat Water Supply Scheme Gap closing work 90% pending BOE restoration 1.0 km, Pipe laying 16.0 km, FHTC 85% and Boundary wall work pending, Pump House 15% pending. Staff Quater 15% pending, Pump Lower pending 31-Dec-2026
4 8130432 Dulhipur Gram Panchayat Water Supply Scheme Pump House- 20%, Boundwary Wall- 30%, Staff Quarter- 20%, OHT- 40%, FHTC- 30% 31-Dec-2026
5 8130426 Manaitapur Gram Panchayat Water Supply Scheme Pump House- 100%, Boundwary Wall- 100%, Staff Quarter- 100%, OHT- 100%, Pipe line- 90%, FHTC- 100% 31-Dec-2026
6 8130687 Chaupai Gram Panchayat Water Supply Scheme Gap Closing pending work Pipe line- 60%, FHTC- 60% 31-Dec-2026
7 8130726 Kadharpur Gram Panchayat Water Supply Scheme Pump House- 30%, Staff Quarter- 30%, OHT- 100%, Pipe line- 100%, FHTC- 100% 31-Dec-2026
8 8130580 Amari Gram Panchayat Water Supply Scheme Pump House- 20%, OHT- 20%, Boundary wall- 20%, Staff Quarter- 20%, Pipe line- 20%, FHTC- 100% 31-Dec-2026
9 8130825 Lohang Patti Gram Panchayat Water Supply Scheme OHT-55%, Pipe line- 85%, FHTC- 100%, Staff Quarter- 80%, Boundary wall- 80% 31-Dec-2026
10 8131586 PURAB GAON work Pending OHT-15%, Pump House- 55%, Boundary wall- 100%, FHTC- 55% 31-Dec-2026
11 8131581 Saruanwa Work Pending OHT- 15%, Pump House- 20%, Staff Quarter- 20%, Boundary wall- 20%, FHTC- 40% 31-Dec-2026
12 8130599 Umari Gram Panchayat Water Supply Scheme Pending work Pipe line- 30%, FHTC- 75% 31-Dec-2026
13 8130879 Lachhipur Gram Panchayat Water Supply Scheme Work Pending Pump House- 10%, OHT- 10%, Boundary Wall- 10%, Pipe line- 10%, FHTC- 100%, Staff Quarter- 100% 31-Dec-2026
14 8130712 Kishungarh Gram Panchayat Water Supply Scheme Work Pending Pump House- 10%, OHT- 15%, Boundary Wall- 10%, Pipe line- 10%, FHTC- 20%, Staff Quarter- 10% 31-Dec-2026