Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in

S.No. District Scheme ID Scheme Name Program Physical Completion Physical Completion (%) Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 Bareilly 8129102 TAH PYARI NAWADA OLD RETROFIT YES 100 YES 37.04 34.37 34.37 0.00 0.00 34.37 O&M
2 Bareilly 8135923 MEHTARPUR TEJ SINGH OLD RETROFIT YES 100 YES 52.20 47.94 47.94 0.00 0.00 47.94 O&M
3 Bareilly 20096345 bhamora water supply scheme(retro) OLD RETROFIT YES 100 YES 46.26 15.53 15.53 0.00 0.00 15.53 O&M
4 Bareilly 20096374 Churai Dalpatpur water supply scheme(retro) OLD RETROFIT YES 100 YES 37.05 28.62 28.62 0.00 0.00 28.62 O&M
5 Bareilly 20096380 Hardaspur water supply scheme(retro) OLD RETROFIT YES 100 YES 61.03 42.80 42.80 0.00 0.00 42.80 O&M