S.No. District Scheme ID Scheme Name Program Physical Completion Physical Completion (%) Financial Completion Work Cost Released Cost Expenditure Cost Liability Balance Fund Final Cost Scheme Status
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 Kushi Nagar 7892835 Ahladpur EMWQ Scheme NRDWP NO 64.00 NO 287.37 106.88 106.88 0.00 180.49 287.37 Under Construction
2 Kushi Nagar 7894059 Lachhia Deoria GOV AES JE Scheme NRDWP NO 65.00 NO 439.29 206.33 206.33 0.00 232.96 439.29 Under Construction
3 Kushi Nagar 7894075 Gagalwa EMWQ NRDWP NO 62.00 NO 332.01 256.32 256.32 0.00 75.69 332.01 Under Construction
4 Kushi Nagar 7913441 PACH PHERA GP WS SCHEME NWQSM NO 87.00 NO 204.54 110.92 110.92 0.00 93.62 204.54 Under Construction
5 Kushi Nagar 7924199 PARSAUNI GP WSS NRDWP NO 65.00 NO 214.31 168.14 168.14 0.00 46.17 214.31 Under Construction
6 Kushi Nagar 8039028 BADARAHA GRAM PANCHAYAT WS NRDWP NO 38.00 NO 105.16 79.94 79.94 0.00 25.22 105.16 Under Construction
7 Kushi Nagar 8127407 MAILA NRDWP NO 5.00 NO 156.41 102.16 102.16 0.00 54.25 156.41 Under Construction
8 Kushi Nagar 8132396 HATHIYA NRDWP NO 60.00 NO 133.55 126.96 126.96 0.00 6.59 133.55 Under Construction