Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Gayatri Projects LTD | 20000627 | Dullapur G.P WSS | 286.85 | 151.20 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 11130.00 | 11723.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Bani Kodar | Dullapur | 435811 | Dullapur | 195 | 194 | 99 | Work In Progress | Not Certified | 
| 2 | Barabanki | Bani Kodar | Dullapur | 435812 | Sohansa | 100 | 98 | 98 | Work In Progress | Not Certified | 
| 3 | Barabanki | Bani Kodar | Dullapur | 435813 | Bhausingh Pur | 124 | 123 | 99 | Work In Progress | Not Certified |